Majority
Headnote
1. Municipal Corporations—Streets—Change of Grade—Injury to Property Owners—Remedies.This action is .in equity to abate a nuisance. The claim of the plaintiff is that the defendant, in changing the grade of its streets, “negligently and improperly” filled up the natural channels and the ditches, diverting the water from its usual course, and as a result thereof the accumulating water, whenever there were heavy rains, was discharged on the premises of the plaintiff, accompanied with “mud, filth, rubbish,” etc.. The ground of the demurrer to the complaint was that it failed to state a cause of action. The particular objection urged was the failure to allege a compliance with the provisions of the charter of the defendant hereafter referred to. The nuisance is a continuous one, recurring whenever there is high water, and the damages could not be ascertained when the action was commenced. The chief relief sought is to restrain the discharge of water and filth allowed to collect through the negligence of the defendant, and the past damages are a mere incident to the principal cause of action.
We think the charter (Subdivision 3, § 63, c. 63, p. 166, Laws of 1902) of the city of Fulton is not applicable. The subdivision mentioned provided that a person having a claim for damages arising from the change of grade of a street “must present to the board of public works a verified claim therefor within 60 days after such change of grade is completed.” In the event of a failure to agree with the owner upon the amount of the damages to be awarded him, he may “within thirty days after the presentation of the claim * * * apply to the Supreme Court for the appointment of three commissioners to determine the compensation to which he is entitled.” That subdivision refers to damages computable in a fixed sum. of money. The claim.of the plaintiff did not mature within 60 days after the change of grade. The floods which caused the damage occurred at intervals, and in all probability will continue from time to time. The method of determining damages, therefore, by commissioners appointed by the court, set out in the statute, does not relate, to the case of a continuing nuisance. That practice applies where a “verified claim” has been presented and no agreement has been made within 30 days after its presentation. If the cause of action has not ripened within the 60-day statute' of limitation, the claim cannot be presented as required by the statute. The deposit of filth and water may be immeasurably greater a year after the completion of the change of grade than within the 60-day period, or there may be no invasion at all until after the lapse of that time. Accordingly an action in equity will arise to prevent the re-' peated invasion of the plaintiff’s premises.
Section 230 of the defendant’s charter (Laws 1902, p. 219, c. 63) provides that no action to enforce any “claim, debt'or demand against the city shall be brought” until 30 days have elapsed after the claim has been presented for audit. If the claim is of such a nature that it cannot be'presented at all, of course, the section does not apply. The
Interlocutory judgment affirmed, with costs, with leave to the defendant to plead over, upon paying the costs and disbursements of this appeal and the costs of the demurrer. All concur.
Cases cited
- Sammons v. City of Gloversville 175 N. Y. 346 p. 705
- Ahrens v. City of Rochester 97 App. Div. 480 p. 705