Majority
Headnote
1. Landlord and Tenant—Tenant’s Covenant to Repair—Default—Measure of Damages.The plaintiff leased certain premises in the city of New York to the appellant, and the action was brought to recover the sum of $3,450 damages alleged to have been sustained by the landlord through the failure of the tenant to keep its covenant “to make all and every repair of every description whatsoever, both inside and outside of the house, and about the demised premises, and to the roof of said buildings, at his own proper cost and expense,” and “to comply with all the regulations and orders of the health, police, and fire departments, and also all the municipal departments of said city,” and to leave the premises at the expiration of the term “in as good state and condition as reasonable use and wear will permit, damages by the elements excepted.” The decision of this court on a former appeal established the right to recover and disposes of all questions arising on this appeal excepting the right of the plaintiff to recover interest and the award of an additional allowance of costs. 104 App. Div. 420 , 93 N. Y. Supp. 684 .
The court, on submitting the case to the jury, excluded from their consideration the amount of interest by directing that they render a verdict for the damages, “with interest.” When the sealed verdict was reported, the court added the interest before the verdict was entered. The defendant duly excepted to the direction to add interest. There was no waiver of defendant’s right to object to the allowance of interest by its failure to except when the jury went out. The exception taken when by direction of the court the interest was added was
The respondent relies on thé case of Sweeny v. City of N. Y., 173 N. Y. 416 , 66 N. E. 101 . That was an action on a contract to recover the contract price of removing the walls and debris after the old Windsor Hotel fire. The contract price of the work was not a gross sum, but a given price per cubic yard of material removed and for each day’s labor required. After completing the work, the contractor presented a claim for the balance of the contract price, computed on the basis prescribed in the contract. It was held that the damages were capable of ascertainment by mere calculation, and that interest was recoverable. If the city had supervised the work, it would have known how much material was removed and- the number of days’ labor employed. The court did not intend to modify the rule of the common law that a demand must be liquidated or the amount thereof ascertained before interest is recoverable farther than that rule had been previously modified in this state by the qualification that “if the amount due is capable of being ascertained by mere computation the allowance of interest is proper, but not otherwise.” Excelsior Terra Cotta Co. v. Harde, 181 N. Y. 11 , 73 N. E. 494 , affirming 90 App. Div. 4 , 85 N. Y. Supp. 732 ; Delafield v. Village of Westfield, 41 App. Div. 24 , 58 N. Y. Supp. 277 , affirmed 169 N. Y. 582 , 62 N. E. 1095 .; It is quite clear, I think, that the damages for which the defendant is liable were not ascertainable by a mere computation, and therefore interest was not recoverable. The facts were not complicated, but the .case involved novel legal propositions, making it difficult and extraordinary, and the discretion of- the trial justice was properly exercised in granting the additional allowance.
Cases cited
- Excelsior Terra Cotta Co. v. Harde 181 N. Y. 11 at 73 p. 605
- Delafield v. Village of Westfield 41 App. Div. 24 at 58 p. 605