Majority
Headnote
1. Mechanics’ Liens—Foreclosure—Pleadings—Evidence.The action was brought for the foreclosure of several mechanic’s liens filed by the plaintiff and his'assignors for work and
The court below also found as follows: /
“Twelfth. That the defendant Hardiman failed to live up to the terms of the contract with the defendant Fennan, in that the said Hardiman did not keep the men under the defendant Fennan’s employ supplied with materials with which to perform the work which said Fennan was to perform; that the defendant Fennan had a claim against the defendant Hardiman for some extra work which Fennan performed for Hardiman outside of the work to be performed under said contract between Hardiman and Fennan; and both of which claims were, as understood by both parties, released upon the defendant Hardiman agreeing to pay the men the wages for which they subsequently filed the liens in question.”
The* complaint does not contain any allegations relative to the nonperformance of the contract by either Hardiman or Fennan, or .to a release by one to the other of any claim of nonperformance of the contract, and is entirely silent upon the subject-matter of said twelfth finding. There is no evidence in the record to sustain said finding. The complaint does not allege that Hardiman promised to pay Fennan’s indebtedness to his workmen, nor are there any facts alleged in the complaint upon which to base a -finding of any such promise, or for a personal judgment against the defendant Hardiman, and no demand
The complaint alleges that at the time of filing the notices of lien by the plaintiff and his assignors, Hardiman had so far completed his contract as to entitle him to the payment of $60,000 by the city of Watertown, and that at the time of the commencement of the action there remained in the possession of the city the sum of $800 which the city was to retain until the completion of the building and its acceptance by the city. It appears that at the time of the trial the building was then substantially completed, and that Hardiman had been paid the further sum of $4,000. In Van Clief v. Van Vechten, 130 N. Y. 571 , 29 N. E. 1017 , it was held that under the mechanics’ lien law of 1885, if a contractor abandoned the contract, and the owner completed the building in accordance with and under a provision of the contract providing for it, the lien attached to the extent of the difference between the cost of completion and the amount unpaid when the lien was filed. This lien is embodied in the lien law of 1897, chapter 418, p. 516, Laws 1897, § 4, which in giving the lien provides that “if labqr is performed for or materials furnished to, a contractor or subcontractor for an improvement, the lien shall not be for a sum greater than the sum earned and unpaid on the contract at the time of filing the notice of lien, and any sum subsequently earned' thereon.” If the difference between the cost of completion and the amount up-paid to Fennan at the time the notices of lien were filed was less than the amount unpaid to him upon his contract, so that there is something earned by Fennan upon his contract, the liens will attach thereto. The judgment establishing the liens should be modified accordingly, and, as so modified, affirmed; and adjudging further, that the amount, if any, earned by Fennan upon his contract, be ascertained by the court and entered at the foot of the decree.
The personal judgment against Hardiman is erroneous upon the grounds already stated: First, that at the time of the filing of the liens there was nothing due to Fennan upon his contract; second, that the proof of the alleged promise of Hardiman to pay the indebtedness of Fennan to his employes, was not within the issues, and the promise, if made, was without consideration, and, as a promise to pay Fennan’s past indebtedness, void, within the statute of frauds. And, also, that under section 3412, of the Code of Civil Procedure, a personal judgment can be recovered by the plaintiff only in case he fails to establish a valid lien.
Judgment reversed, and new trial ordered, with costs to the appellants to abide the event
SPRING, WILLIAMS, and KRUSE, JJ., vote for reversal and the granting of a new trial as to all defendants. Opinion by NASH, J., for modification and reversal in which McLENNAN, P. J., concurs.
Cases cited
- Van Clief v. Van Vechten 130 N. Y. 571 p. 8