Majority
Headnote
1. Guaranty—Construction—Conditions—Underwriting Contract.The defendant demurred to the complaint in this action on the ground that it does not state facts sufficient to constitute a cause of action. The demurrer was overruled, and an appeal has been taken from the interlocutory judgment entered thereon.
It is claimed that the complaint is defective in that it fails to allege the performance of certain acts or the existence of certain conditions upon which it is insisted by the defendant his liability depends. The action is upon a written instrument dated the 10th of November, 1902, made between the Brunswick Construction Company, the Knickerbocker Trust Company (the plaintiff herein), and individual contracting parties, among whom is the defendant. It is recited in that instrument that the construction company proposes to acquire real property in the city of New York, and to construct thereon a hotel, and to authorize an issue of $7,500,000, per cent, bonds secured by a consolidated mortgage, which would be a lien upon the property to be purchased subsequent only to a first mortgage of $4,000,000, “for the retirement of which provision shall be made by reserving $4,500,000 of said consolidated mortgage bonds; and it is desired to secure underwritings for at least $2,000,000 of the remaining $3,000,000 of said consolidated mortgage bonds, and to secure a loan from the trust company.” The agreement then provides that, in consideration of the premises, the individual signers “hereby severally, but not jointly, agree with the company to take and pay for, as hereinafter provided, the amount of said consolidated mortgage bonds set opposite their respective signatures hereto, or such reduced amount as shall be allotted to them as herein provided, at the price of seventy-five per cent, of their pár value, together with accrued interest.” The terms and conditions material at present are the following: The agreement was to be binding on the individual subscribers when the amount of at least $2,000,000 of “such bonds” shall have been underwritten by accepted underwriters, and when the trust company shall have agreed to make the loan provided for. The trust coihpany agreed to advance to the construction company on certain terms, the amount to be paid by the underwriters, or such part thereof as should be called for from time to time by the construction company for one year from the date of the first advance. “Such advances shall be made in such amounts as are called for by the company [meaning the construction company], provided that the bonds underwritten, or interim bonds representing the same, to the amount of $!,••
The defendant became an underwriter for $100,000 of the issue of $2,000,000 bonds; his subscription being at the rate of 75 cents on the dollar. The amount was afterwards reduced. He failed to pay the amount of his subscription, and thereupon this action was brought to enforce his liability.
In the complaint there is set forth the making of the agreement and supplemental or modifying agreement, and the defendant’s subscription to the bonds; that on the 15th of December, 1902, and at various times thereafter, the plaintiff loaned and advanced upon the securities and guaranties in the agreements provided for to the Brunswick Construction Company various sums, amounting in the aggregate to $1,687,500, payable, with interest at 6 per cent.; that the loan was evidenced and secured by the several promissory notes of the construction company, duly made and delivered to the plaintiff at or about the respective dates on which the aforesaid sums, aggregating $1,687,500, were respectively-advanced ; that the amount thus loaned was 75 per cent, of the amount agreed to be paid by all the underwriters under the agreements; that there had been deposited with the plaintiff at or-about the time the advances were made contracts assigned in blank, as provided for in the
It is insisted by the defendant that the complaint is insufficient because certain conditions were contemplated in the agreements which should have been performed before he became liable upon his guaranty, and they are: First, that the construction company should have acquired the real estate; second, that it should have constructed the hotel thereupon; third, that it should place or .cause to be placed thereon a first mortgage of $4,000,000; fourth, that it should have authorized an issue of $7,500,000 consolidated bonds, and that out of said bonds it should have reserved $4,500,000 to retire the first mortgage; and all that having been done, $2,000,000 of the remaining bonds should have been set aside, and that his subscription bound him only to take a proportion of bonds so specifically selected and set aside, being a part of the remaining $3,000,000 of bonds so specifically selected and set aside after the retirement of the first mortgage had been provided for.
We agree with the court below that it was not incumbent upon the plaintiff to make further allegations than those contained in the complaint to set forth a cause of action against the defendant. His guaranty is a general one. The plaintiff did not by the agreements bind itself in any way to the performance by the construction company of any of the matters contained in the recitals as being within the purposes and intention of the construction company. Those recitals are not representations or stipulations of the plaintiff. It is expressly stated in the agreement of November 10, 1902, that the recitals therein are made by the construction company and the underwriters, and that the trust company is not to be responsible therefor. The purpose- of the agreements
It was not incumbent upon the plaintiff, in order to maintain its action, to make further allegations than those contained in the complaint, and the interlocutory judgment should be affirmed, with costs, with leave to the defendant to withdraw the demurrer, and answer the complaint within 20 days after the service of the order to be entered on this decision, and on payment of costs in this court and in the court below.
All concur.