Majority
Headnote
1. Contract to erect elevator—Employer to do work before contractor begins—When time of contractor begins to run.This action was brought to recover the damages arising from a breach by the defendant of a contract made by it on April 5, 18Y6, with Gill & Mansfield for the construction of an elevator. The complaint alleges, as a breach, that the defendants failed to have the foundations ready for the erection of the elevator at the time they were required to commence work for its construction, and claim damages therefor by reason of increased expense in doing the work and supplying materials, and loss of gain or profits arising from the delay occasioned by the want of readiness on the part of the owners.
Upon the trial all proof on the part of the plaintiff tending to show the cause of action set out in the complaint, with the damages arising therefrom, was objected to by the defendant, and excluded by the court, under the plaintiff’s exception. The decision of the court seems to have been based upon the assumption that there was no covenant on the part of the defendant to have the foundations ready at the time of giving notice thereof, and such seems to have been the opinion of the general term affirming the judgment.
An examination of the terms of the contract is necessary to determine the correctness of the views taken by the courts below. That instrument provided, among other things, that Gill & Mansfield should furnish the materials and perform the work in erecting the superstructure of an elevator over the water upon piers in the Hudson river, between Sixtieth and Sixty-first streets, in New York, and should finish the same within five months from the time of the commencement of the work, and should receive, as their
“The said parties of the first part hereby further agree to commence the erection of the elevator within five days' after notice from the engineer that the foundations are ready, and to complete the same, ready for use of all the lofting elevators, within five months thereafter.” “Whenever the word ‘ engineer ’ is used in the specifications, reference is had to the engineer in chief in charge of the work for the party of the second part to this contract.”
It seems to us that the courts below have mistaken the plain reading and import of this contract. It is true that there is no express provision in it requiring the foundations, or any part of them, to be ready at any particular time. So neither is there any such provision requiring any foundations at all to be built by the owners; but the clearest implications arise from the language of the agreement, and its avowed object and intent, that the property of the owners upon which the building was to be erected should be prepared for the superstructure by such owners, and that the contractors should have notice whenever that time arrived. It was the indispensible condition to the performance of any of the obligations incurred by the contractors that the foundations should be prepared, and unless they were to be so prepared it rendered the whole contract motiveless and nugatory.
It is not denied by the respondents but that the duty of preparing the foundations was assumed by them, but it is urged that there is no provision in the contract requiring them to have all of the foundations, or any particular portion of them, ready at the time Of giving the notice of readiness stipulated for in the agreement. In this we think they are mistaken. It was made the duty of the owners, not only to prepare the foundations for the reception of the work of the contractors, but also to notify them through their agent of the fact of such readiness. The terms of the contract plainly imply that the notice was to be of an actually existing condition, and not the expression of an opinion on the part of the engineer that the foundations were sufficiently advanced to enable the contractors to prosecute their work advantageously. The contractors have not submitted any such question to the decision either of the owners or their engineer, and in view of the heavy
The meaning of a contract is to be gathered from a consideration of all of its provisions, and the inferences naturally derivable therefrom as to the intent and object of the parties in making it, and the result which they intended to accomplish by its performance. It was said by Allen, J., in Booth v. Cleveland Mill Co.,( 74 N. Y., 21 ):
“There is no particular formula of words or technical phraseology necessary to the creation of an express obligation to do or forbear to do a particular thing, or perform a specified act. If, from the text of an agreement, and the language of the parties, either in the body of the instrument or in the recital or inferences, there is manifested a clear intention that the parties shall do certain acts, courts will infer a covenant in the case of a'sealed instrument, or •a promise if the instrument is unsealed, for non-performance of which an action of covenant or assumpsit will lie.”
It was said by Judge Danforth, in New England Iron Co. v. Gilbert Elevated R. Co. ( 91 N. Y., 165 ), that, “although the defendant does not in express terms undertake to do the act or give the notice which shall set the plaintiff in motion a promise to do so” “is clearly to be implied from the covenants and stipulations which were inserted. ” ‘ ‘ There is manifested a clear intention on the part •of the defendant to construct the railway, and for that purpose do certain things; among others, raise the money, provide the masonry, and give instructions to the plaintiff.
The language used in these authorities is peculiarly applicable to the case in hand, and furnishes a safe and just guide by which to determine their rights.
Looking at this contract in the light of decisions referred to, it would seem that the plainest principles of justice require the implication of a covenant on the part of the defendant to prepare the foundations in question so as-to have them in a condition to enable the contractors to prosecute their work to the utmost advantage and economy before giving the notice which set the time limited for their completion in motion. Any other construction would destroy the mutuality of the agreement, and put it practically in the power of one party to defeat performance by the other.
It is quite obvious that the provisions of the contract in respect to time are of its essence, and were regarded by the parties as of primary importance; the contractors being stimulated to great diligence by the prospect of extraordinary compensation therefor, and deterred by the certainty of great pecuniary loss from dilatoriness or delay in the prosecution of their work. A construction which enabled the railroad company to retard the prosecution of the work by the contractors, or disabled them from employing all of the agencies or force which, in their judgment, could wisely and advantageously be used in its performance, would, operate as a fraud upon them, and render their covenant to complete the work in five months a reckless and foolhardy undertaking. The very assumption of such a covenant on the part of the builders implies an understanding on the part of all parties that they were to be unrestricted in the employment of means to perform it, and that nothing which it was the duty of the owner to do to enable the contractor to perform should be left undone. It is unreasonable to suppose that the parties intended to enter into obligations providing for the performance of work by one party, under a heavy penalty for non-performance within a given period, which yet left it optional with the other to facilitate or retard such work at its pleasure or discretion.
It is also claimed by the respondent that the act of the contractor in commencing the work within five days after receipt of the notice in question constituted a waiver of the breach complained of. The evidence establishes the fact that, immediately upon the receipt of the notice, the contractors protested against the act ;of the defendant, and claimed that it was given in violation of the true meaning
The further objection is taken that no valid assignment of the claim in suit was made by his copartner in the work to the plaintiff. The objection that Gill was a necessary party to the action is not taken by the answer; .and, assuming that the assignment was invalid, it does not constitute a bar to the action, because the plaintiff stiff had such an interest in the contract as entitled him to maintain an action for his damages thereon. Independent, however, of this objection, we are of the opinion that the assignment in question was sufficient in itself, or so ambiguous on its face as to authorize parol evidence to explain its meaning. The instrument in question purported to assign to the plaintiff all of Gill’s right, title, and interest to any and all claims and demands which the late firm of Gill & Mansfield have had or now have against the New York Central and Hudson River Railroad Company “for, on account of, and arising from any and all award or awards due said firm from said company under a certain contract for the erection of a grain elevator at the foot of Sixtieth street, in said city, by reason of said Gill & Mansfield having completed the construction of said elevator within a certain time specified in said contract; the said Luther E. Mansfield hereby agreeing that all prosecutions of all claims shall be in bis name individually.”
It is manifest from the language of the instrument that the parties intended to transfer some claim then in existence, arising under the contract in question, and that such
Upon the trial the plaintiff gave in evidence a judgment-roll in an action in the - supreme court, wherein he was plaintiff and the said Grill was defendant, instituted to procure a reformation of the language of the said assignment, so as to make it conform to the real intentions of the parties when it was made, and also an assignment executed by Grill in conformity to such judgment, transferring to the plaintiff all causes of action growing out of the contract between Grill & Mansfield and the defendant. This judgment was rendered after the commencement of the present action, and after one trial thereof had been had.- The defendant objected to the evidence. We think the evidence was competent. As we have seen, it was proper for the plaintiff to give parol evidence of the meaning of the language used in the assignment, and a judgment against Grill, the only party except the plaintiff who had an interest in the matter, determining that fact, was the highest evidence that could have been given upon the issue. The only interest that the defendant here had in that question was to be protected from any claim under the contract by other parties. This judgment bound the parties to it, and effectually protected the defendant from any claim which could be made by Grill.
We have been invited by the appellant to express our opinion upon the question of the damages recoverable in this action, but we do not think that question is before us in such a shape as to authorize an opinion thereon.
The judgments of the court below should be reversed, and a new trial ordered, with costs to abide the event.
All concur, except Raparlo, J., absent.