Majority
Headnote
1. Mechanics’ lien—Right of sub-contbactob.This is an action to foreclose a mechanic’s lien. The defendant Kahn was on the 1st day of May, 1886, and still continues to be, the owner of premises 87 Pike street, in the city of New York. On that day he entered into an agreement in writing with the defendant McMullin to make .certain.alterations .in the .building .on said premises for the aggregate price of $9.00. This, sum was to be paid in four instalments, upon obtaining the certificates of the architect, of the prosecution of the work up to the points required for such payments under the contract. The plaintiffs and the defendant Schmohl are respectively subcontractors, having furnished materials which were used in said work under contracts with said McMullin. Both the plaintiffs and said Schmohl have filed liens, and are seeking to foreclose them in this action. No technical objections are made to the form or sufficiency of such liens. The owner’s defense is a claim that when they were filed he had paid his immediate contractor in full, and that, therefore, under the final clause of section 1, of chapter 342, of the Laws of 1885, the sub-contractors have no right of action. The learned referee has so held, and thereby, as it seems to me, fallen into an error of law which would result in a grave injustice. The language of the clause in question is as follows:
“But in no case shall such owner be liable to pay by reason of all the liens filed pursuant to this act, a greater
sum than the price stipulated and agreed to be paid in such contract, and remaining unpaid at the time of filing such hen, or in case there is no contract, then the amount of the value of such labor and material remaining unpaid, except as hereinafter provided.”
The facts of the case at bar are that the contractor, McMullin prosecuted his work so far as-to obtain in regular course the first two payments. He was, also, paid $100 on account of the third payment, making in all $550 that was received by him, and leaving an unpaid balance of $350 on the contract price. He never carried out his contract systematically thereafter, or completed it, so as to entitle him to the certificates required for the third and fourth payments, though he did do considerable work upon both sections of the contract which were to be covered by such third and fourth payments respectively. The contract was subsequently abandoned by the contractor and finished by the owner. This statement should perhaps be qualified by saying that the owner contends that the building never has been actually finished and is incomplete to this day. Still, the evidence shows that it was substantially completed and it has been occupied by a tenant for a considerable period of time. The architect (who was the owner’s witness), virtually admits that the work which Schmohl subsequently was employed by the owner to do, and which he actually did, was all there was to be done in order “ to finish McMullin’s job.”
It appears that adding to the total amount actually paid McMullin, the contractor, the amount paid to Schmohl, under the subsequent contract with the owner in consideration of his finishing “McMullin’s job,” and, also, several additional items, concerning which there is a dispute as to whether they were comprehended in the original contract or to be classed as extra work — adding all these sums together, there is still quite a large balance between the aggregate amount thereof and the original contract-price.
To this difference between the original contract-price and the total expense the owner has been put to in order to compióte the contract, these mechanic’s liens should attach. There is the strongest possible equitable reason for so holding, for, presumably one of the causes why the owner has been able to complete at so much less than the contract-price, is that these very materials which have gone into his building have not been paid for. The referee has given a construction to the mechanic’s lien act which I do not think the legislature ever intended. It would certainly make of it, as far as the present case is concerned, anything but a remedial statute.
There is nothing in Hagen v. American Baptist Society (6 N. Y. State Rep., 212) which conflicts with this view. It is there conceded that a sub-contractor’s lien attaches to “ the extent of what is due or to become due upon this contract.”
The judgment must be reversed and a new trial ordered, with costs to abide the event. Upon such trial it will be well for the court or referee to find specifically upon the question how much was required to complete the building, or, rather, “to finish McMullin’s job,” and, therefore, how large a balance there is to which these liens may attach. This may include the determination of just what was comprehended in the McMullin contract, and how much that the owner has since paid for must legitimately be considered extra work, and, therefore, not deductible from the fund accessible to the liens. These, and perhaps other questions of fact, will have to be definitely, found upon in order that the case may be tried and the liens made effectual on the theory above set forth.
Van Hoesen and Daly, JJ., concur.