Majority
Headnote
1. Railroad—Contract to construct—Evidence—Burden of proof.The corporation defendant was organized November 30,1881, by the consolidation of certain New York and Pennsylvania Railroad companies and it entered into contracts with Brown, Howard & Co., a construction company to construct and complete the unfinished portion of its road. On the 1st of August, 1882, that company entered into a contract with Greorge H. Thompson & Co., to
Extra work: “Nor shall any claim be allowed for extra work, unless the same shall be done in pursuance of a written order from the engineer in charge, and the claim made at the first settlement after the work was executed, unless the chief engineer, at his discretion, should direct the claim, or such part as he may deem just and equitable to be allowed.”
In pursuance of their contract with Thompson & Co., the plaintiffs entered upon their work, and at a certain point upon the road they cut through a considerable elevation and after they had substantially completed the cutting, a large amount of earth from one of the sides caved into the cutting at four different times in the months of December, 1881, and January and February, 1882, and this earth the plaintiffs excavated and removed each time. It is for the expense of this work mainly that this action was brought, the plaintiffs claiming that they did it under contract with the defendant and for its benefit. The defendant interposed to the complaint a general denial and an allegation of payment.
To maintain their action it was incumbent upon the plaintiffs to show by satisfactory evidence that they did
The plaintiffs coming into court alleging that they had •done work for the defendant under an agreement with it, had the burden of establishing their allegations, and if there is any defect or obscurity in the proof it is their misfortune. We know of no rule of law by which it can be held that that proof is supplied because the defendant did not produce the contract between it and Brown, Howard & Co., or of any of them, and thus obtain some knowledge of their contract with the defendant; and it was incumbent upon them to show that the relations between that company nnd the defendant were such as to make the defendant responsible for the acts of their engineers.
It is not needful or profitable for us here to comment upon all the evidence with the view of showing how we reach our conclusion, as upon a new trial further evidence may be given and the deficiency which we think fatal may be supplied.
But we will go still further. If it be ássumed that Brown, Howard & Co., in some general and undefined way, could be treated as the general agents of the defendants for the construction of the road so that it would be bound by their contract with Thompson & Co., we should still reach the same conclusion. In that event the defendant would be responsible to Thompson & Co. for all the work embraced within their contract according to the terms thereof and in no other way. Under that contract Thompson & Co. were bound to make “all the excavations or embankments connected with or incident to the construction of said railroad'7 on the Buffalo division thereof, and that we think included all the excavation which might be necessary until the road was turned over to the defendant as a completed road. If after a cutting was made the embankment on either side caved in, the contractors would be obliged to excavate and remove the earth at the contract prices. The plain purpose of the contract was to have the road completed and turned over to the defendants in a finished state, and it may well be doubted whether such an excavation would even be extra work.
But if extra work, not covered by the precise terms of the contract, then it is provided in the contract that no claim should be allowed for such work, “unless the same should be done in pursuance of a written order from the engineer in charge, and the claim made at the first settlement after the work was executed.” This was one of the terms of the. contract,, and we are unable to perceive that the engineers had any power or authority to alter or change it. It was inserted in the contract to protect the defendant from claims for extra work which might be based upon oral
We are, therefore, of opinion that the judgment should, be reversed and a new trial granted, costs to abide the event.
All concur.