Headnote
1. Contract—Construction of, for Buffalo asylum—Laws 1870, chap. 378.There is no contention on the part of the state that the award in this case is excessive provided it is free from the objections which it makes thereto. Its claim is that there was no liability, whatever on its part for any of the damages embraced in the award. It will conduce to perspicuity and brevity to consider the various objections under separate heads.
(1.) The furnishing contract required the contractors to furnish the stone of the quality known as hard sand stone for the exterior facings of the walls of the asylum buildings, and the cutting contract required them to cut such stone. The contracts contain no description of the buildings, and there is nothing in either of them specifying that the whole exterior facings of the walls were to be of sand stone, and hence it is contended that there was no breach of the contracts in the construction of the walls of some of the buildings of brick with sand stone trimmings. But it is fairly to be inferred from the language of the furnishing contract that the facings of the walls were to be of sandstone.
The contractors were to furnish all such stone required and necessary for the construction of the buildings. The stone was to come from quarries in Orleans county, and the contractors agreed to lease the quarries to the state to-an amount in quantity sufficient for the completion of the buildings, and authorized the state to take possession of the same for the purpose of quarrying and delivering the stone in case of default on their part to perform their contracts. While the plans and specifications do not appear in the record, they must have been put in evidence as it appears to have been assumed on the trial that they did require all the walls to be built with sandstone facing, and-such is the
(2.) In answer to the claim for damages on account of the change from stone facings to brick with stone trimmings, it is said by the learned counsel for the state that such change was authorized by the contracts and that it was not therefore a breach thereof. It is not pretended that there is anything in the terms of the furnishing contract authorizing such a change. According to that contract the contractors were bound to furnish and the state was bound to take from them all the sandstone required for the completion of the buildings according to the plans and specifications.
But the cutting contract, made three months later, contained this clause: “ The party of the second part reserves the right to make any change they shall deem proper in the plans and specifications of said buildings, and the work shall be performed by the party of the first part in accordance therewith, for the prices and compensation above set forth, unless such change shall increase the expense of doing said work, in which case the party of the first part shall be paid a reasonable compensation therefor, to be certified by the supervising architect and superintendent.” It is claimed on the part of the state that the two contracts must be read and construed together, and hence that these clauses must have operation in the construction of both contracts and that it authorized the change from stone to brick facings. But we do not perceive how this clause can be held to have any operation upon the first contract. It does not appear that there was any actual intention to make such an important change in that contract and the parties were not dealing with that contract. ' There was no consideration or inducement to the contractors to consent
But here these instruments were not executed at the same time, but three months apart. They do not relate to the same subject matter. The one relates to the material to be furnished and the other to work to be done, and they were not voluntarily executed after negotiations as to their terms and provisions. But they were awarded after competitive bidding and came to the contractors by operation of law simply because they were the lowest bidders. Under such circumstances the rule above referred to can have no operation.
But if we should suppose that the rule could have operation, and that this clause must be taken as controlling the construction of both contracts, as it certainly must be taken as controlling the construction of the contract in which it was inserted, yet we are of opinion that it cannot have the effect claimed for it and that it did not authorize the change made. What change did the state reserve the right to make ? It certainly had no right to omit entirely the construction of all or any of the buildings. The asylum buildings referred to in the contracts were the central or administration buildings, the five connecting wards on each side and the outbuildings. These were all to be built. The size and height of them were fixed and the material to-be put in the walls was determined. The general character of the buildings could not be changed so that the buildings would not be the same contracted for; if it could be, then a public letting in such a case would not be a useful and might be an idle ceremony. Under such a reservation could a building planned for five stories be reduced to two ? Could a stone building, let to a stonemason be
The construction we have thus given is fortified rather than weakened by construing both contracts together, as the learned counsel for the state claims they should be. Under the first contract the contractors were required to own or purchase quarries and lease them, or give the control of them to the state, and thus they were required to make considerable investments for the purpose of being able to furnish the stone. Can it be supposed, under such circumstances, that the parties intended by the reservation in the second contract to authorize at the will of the state any change that might substantially destroy the furnishing contract ? Would buildings, with a few superficial feet of sandstone facings, be the buildings in reference to which the competitive bidding was invited and the contracts were let ? We think not, and that the contracts were broken by change from sandstone to brick.
(3.) After the resolution of May 25, 1816, under which the change from sandstone to brick, with sandstone trimmings, was made, the contractors furnished and cut the sandstone for the trimmings and received pay therefor in full under the contracts, and therefore the state contends that they practically construed the contracts as authorizing the change, and that their conduct constituted a waiver of any claim for damages by reason of such change. If the contractors had in any way induced the change, or if they had taken any advantage therefrom, or if their conduct had thereafter imposed any loss upon the state, there might have been some reason for the contention now made. But it does not appear that they knew that the change was contemplated until it was irrevocably accomplished, and if they had known it they could not have prevented it.
They furnished and cut the stone for the trimmings under their contracts, and this they had the right to do.
But here there was not silent acquiescence in the change. The contractors did not in any way assent thereto, and the finding that they protested against the same has some support in the evidence. A finding that ■ they condoned a serious violation of them rights and effectually released and waived a large claim of damages, should have something substantial to rest upon.
(4.) The plan of the outbuildings was also changed from sandstone facings to brick with sandstone trimmings, and they were built upon the changed plan. There does not appear to have been any formal resolution making this change. But it was nevertheless made by the representatives of the state at the same time with the change in wards O., D. and E., and a part of the same scheme for the-completion of the asylum buildings. The contractors furnished the sandstone trimmings for the outbuildings, and were paid therefor the contract prices. ■ They could not prevent the change and did not assent to it. What we have said about the change in the' wards applies to changes in the outbuildings, and the claim for damages on account of the breach of the contracts in reference to them has not been effectually answered.
(5). The largest portion of the award made to the claimant is founded upon the omission of the state to construct
The state was bound by its contracts just as an individnal would have been bound. It might violate them but could not repudiate or destroy the obligation of them. It was bound through its legislature to make the necessary appropriation of money for them and to do whatever was necessary for performance on its part. The contractors did not, in entering into the contracts, take the chances that the legislature would pass the acts requisite for performance on the part of the state; but they had the right to expect and demand performance on the part of the state as if it were an individual. Now what did the state do ? After the central building the five male wards and the out-buildings were completed, and while the contractors were there with their material ready to continue performance on their part, the managers representing the state by resolution on the 5th day of
We are therefore of opinion that the award is not open to ■ any of the assaults made upon it on behalf of the state, and that its appeal should fail.
We will now proceed to examine the questions raised by the claimants appeal.
(6) After the board of claims had determined that the contractors would have made, as profits from the performance of the two contracts the sum of $105,200.42 computed as stated in the findings of facts, they deducted from that sum $30,000 and awarded the sum of $75,000 as the aggregate profits which would have accrued to the contractors from the performance of the two contracts.
The larger sum was reached by taking the difference between the contract prices and the estimated cost of the stone and cutting, and was the result of a mathematical calculation based upon data furnished by the witnesses. The general statement of the rule of damages in such cases is the difference between the contract price and the cost of performance, and in the case of contracts requiring for their performance a few acts and a brief period of time, the rule is not difficult of application and wifi generally produce results sufficiently certain for the purposes of justice. But in the case of contracts requiring for their performance many acts and a series of years, the application of the rule is attended with more uncertainty, and the question of damages becomes a complex problem not so easily solved. In such cases accidents and contingencies may and usually wifi intervene to vary results. Here the board of claims were dealing with contracts which would take several-years for their performance. The contractors were required to take the stone from quarries in Orleans county and transport them about one hundred miles to the asylum
In reaching the allowance or deduction of $30,000, for the care, labor, trouble, risk and responsibility which would have attended the performance of these contracts, we cannot say the board erred. It is true that that sum is in great measure arbitrary and based upon no definite data. But it is as certain as any amount which may be taken as profits upon such contracts requiring years tor their performance with all the risks, uncertainties and contingencies which must ordinarily attend such performance. The following cases are sufficient authority for the action of the board in determining the amount finally awarded. Masterton v. The Mayor, 7 Hill, 61 ; Danolds v. The State (supra); United States v. Speed, 8 Wall., 77 .
(7). The claimant contends that the board of claims erred in not allowing him interest upon the amounts found due from the date of filing his petition against the state. If this had been a common law action against an individual to recover damages for breach of contracts under precisely the same conditions, we are of opinion that interest could not legally have been allowed to the plaintiff even from the commencement of the action. The claim is in every sense unliquidated. There was no possible way for the state to adjust the same and ascertain the amount, which it was liable to pay; and hence within the decision
We have, therefore, .come to the conclusion upon the' whole case, that neither appeal should prevail, and the award should be affirmed, without costs,, to either party.
All concur (Gray, J., as to state’s appeal, and is for reversal as to interest), except Haneorth, J., who dissents.