Majority
Headnote
Damages—Measure of—Breach of contract—Failure of buyer to PERFORM.—It appears from the evidence that on the 15th of January, 1880, the plaintiff and defendants entered into a written contract, by which the former was to furnish and the latter to pay for two thousand tons of iron rails, to be delivered during the months of May and June, of that year, on board cars at the works of the plaintiff, at Springfield, in the state of Illinois, in equal quantities in each month, together with certain fist-plates or splice-bars for the iron rails.
By a subsequent agreement between the parties, the time for the delivery of the iron rails and of the fist-plates was extended from May and June, 1880, to June and July of that year, but there was no other modification of the original agreement made by the parties. Subsequently to this time, certain negotiations were entered into between the parties with a view, on the part of the defendants, of an extension for a considerable time of the period in which the iron should be delivered. The main contention on the part of the learned counsel for the defendant is that these negotiations resulted substantially in an agreement by which the delivery should be had in equal parts on the 15th day of October and the 15th day of November, 1880. If this contention were true, as matter, of fact, it would follow that this action could not be maintained, because it was begun before the ldth day of October, 1880, and consequently before the time in which the defendant was required, by vir
The evidence shows the fact to be that the defend ants, in violation of their agreement, failed to permit the. iron to be delivered to them and failed to make any payment therefor, either within the time limited by the original agreement or within the period by which the time of the fulfillment of the original agreement was extended by consent, or within a reasonable time after being notified so to do. They also failed to comply with the plaintiff’s peremptory demand of performance made early in October following. Such being the fact as found by the referee and as conclusively established by the evidence, the only other question was the amount of damages to which the plaintiff was entitled.
The testimony upon this subject, which is given by numerous witnesses, is quite uniform and we think the learned referee was justified in his conclusion as to the amount of damages which should be awarded to the plaintiff, based upon the proper measure adopted by him, which was the difference between the contract price and the actual value of the property at the time of the beginning of this action which was the 12th day of October, 1880.
We are unable to see that the defendants have any right to counter-claim against the plaintiff, damages by reason of the alleged failure of the plaintiff to deliver 390 tons of iron named in another contract. That contract was not with the defendants although possibly'they may have had some interest as stock-holders in the Bail way construction Company, so-called, with which the contract'was made. No privity is shown between the defendants and the plaintiff in regard
We have examined the several exceptions to the reception and rejection of evidence as well as the exceptions to the requests and refusals to find in accordance with the defendants’ views of the case, and find in these no error which would warrant us in reversing the judgment.
The judgment should be affirmed, with costs.
Van Brunt, P. J., and Bartlett, J., concur.