Majority
Headnote
I. Contract—Recovery on—Performance is condition precedent.In July, 1879, the parties entered into an agreement in writing by which the plaintiff agreed to erect for the defendant a hotel building in the town of Webster, N.Y.,within the three months for the sum of $3,150, payable-in installments, $1,000 when the frame was erected, $1,000 when the mason work and plastering were completed, and the balance when the entire work was finished. The defendant, as the work progressed, paid the first two installments of $1,000 each to the plaintiff. And on January 8,. 1880, he paid him the further sum of $1,000.
The referee found that the building was substantially completed on or before the day last mentioned; that there were some slight defects in the building caused by inadvertence of the builder, but that they and the deviations from the contract were waived and the building accepted by the defendant as finished on or prior to January 8, 1880, and that the plaintiff was entitled to recover the residue of the contract price and $205.69 for extra work, with interest from that day, and directed judgment accordingly.
The evidence on the part of the defendant tends to prove that in many respects the plaintiff had not performed the contract, ancl that the defects resulting from such failure-are quite substantial and pervasive.
By the evidence, the conclusion apparently was warranted that the default of the plaintiff was such, that he was not entitled to recover upon the contract. The performance of the agreement on the part of the plaintiff, was. a condition precedent to recovery, unless such performance was waived by the defendant. In this class of cases, however, the condition precedent, may not require literal performance, but when the contractor has in good faith, intended to comply with his agreement, and has substantially done so, slight defects susceptible of remedy, for which allowance may be made, by way of adequate indemnity to the other party, may not be in the way of recovery upon the
The same remarks are applicable to the matter of the defendant’s counter-claim alleged. And in respect to that it may also be suggested that there is no request or refusal to find upon the subject. It is, therefore, unnecessary to refer specifically to the evidence bearing upon those questions of fact, for the purposes of this review. We have not, however, overlooked any of the evidence, or failed to appreciate the very thorough analysis made of it by the argument of the learned counsel for the defendant, which but for the proposition before stated, would properly require and have a more extended expression of consideration.
The contention that recovery upon the contract cannot be supported, because the action was upon the quantum meruit is not sustained. Ho such question was raised upon the trial, and it is not available when raised for the first time upon appeal. Then the cause of the action alleged is not entirely remote or distinct from that on which recovery was had.
It was, as alleged, for materials furnished and work done in the construction of a hotel for the defendant, which is the subject of the contract in question. Southwick v. Bank of Memphis, 84 N. Y., 420 . The plaintiff called as a witness one Wheat, who was his sub-contractor in the work of construction of the building in question, and examined him at considerable length, and after the defendant had proceeded for some time with the cross-examination of the witness, the further cross-examination “was suspended by
The referee properly denied the motion to strike out all the evidence of the witness. The question arises upon the exception to the refusal to strike out the portions permitted to remain of those specified in the defendant’s motion. The view of the referee evidently was that the cross-examinatian taken had relation to the subject of the portions allowed to remain of those embraced within such specifications of the evidence in chief of the witness.
While this was correct as to some of it, there were other portions of it that do not seem to have been covered by the cross-examination. A party is entitled to the opportunity and benefit upon a trial of the cross-examination of a witness whose testimony in chief has been taken by the adverse party. And if without his fault and for causes beyond his control he is denied that right, the evidence of the direct examination cannot properly be made available to the party taking it. People v. Cole, 43 N. Y., 508 ; affirming 2 Lansing, 370.
The burden was with the defendant to make it appear in the case that the motion came within the rule which made its denial error.
In Forrest v. Kissam ( 7 Hill, 463 , reversing 25 Wend., 651 ), where it appeared that at the close of the direct ■examination by the defendant, of a witness, the further hearing was adjourned by the referees for their own accommodation, to a future day by the consent of the parties, the ■court held that the death, in the meantime, of the witness furnished no right to reject the testimony taken in chief. The reasons for the result given by the several members in the court of errors who delivered opinions in that case were not entirely in harmony, and the views of some of them went further than was necessary to support the conclusion adopted upon the facts there presented. And while those views are criticised by the court in People v. Cole (supra),
The adjournment must, as in Forrest v. Kissam, be deemed to have been had with the consent of the defendant, and the opportunity to cross-examine the witness lost without any fault of the plaintiff. The case before us is silent as to the circumstances attending the act of adjournment. And nothing appears showing that the defendant was deprived of the opportunity of then completing the cross-examination if he had desired to do so. And while the day to which the adjournment was taken was Monday, the day of the adjournment does not appear, but the last day of the hearing, as represented by the case, prior to that to which this adjournment was taken, was May 17, 1882. We are, therefore, not otherwise than by that advised by the record of the length of time for which the adjournment was taken. In view of the situation presented by the case no error in the ruling of the referee upon the defendant’s-motion is made to appear. In the cited case of Price v. Wilson ( 67 Barb., 9 ), the witness whose evidence in chief was stricken out because he declined or failed to appear and submit to cross examination was a party defendant to the action, and his direct examination had been taken in behalf of the defense. That case is not necessarily applicable to-the question presented here.
There was a large number of exceptions taken by the defendant to the exclusion and reception of evidence on the trial, some of which require attention.
After making the contract before mentioned, with the defendant, the plaintiff, by an agreement of the same date with Wheat, employed the latter to do the work of construction of the building. Wheat became a sub-contractor of the plaintiff to that extent, and proceeded with the work. By witnesses called on the part of the defendant, the latter offered to prove statements made by Wheat in respect to the portion of the work in which he was at the time engaged. The evidence was excluded and exception taken.
There were several such offers and rulings. And without specifying them with particularity, we think the rulings so far as they excluded the evidence of what he said in reference to the character of the work and materials as to which he was at the time engaged in performing and using were erroneously made. These statements were of such a character that it cannot be seen that the defendant may not have been prejudiced by their exclusion. They were inadmissible as part of the res gestee. They may have been treated as. characterizing the acts in which he was then engaged, and may have had some bearing on the question of good faith,
The plaintiff was permitted against objection and exception of the defendant to give evidence of a conversation, said by him to have taken place between the parties shortly prior to the execution of the written agreement to the effect that the defendant promised to give his personal supervision, care and attention to the work as it progressed, and to relieve the plaintiff from such care in view of the fact that it was understood that the latter would sublet the performance of the work to Wheat. Also that there was some understanding then had between them as to the requisitely seasoned condition of the timber, or some portion of it, to be used in the construction of the building. These statements of the understanding between them were not in accordance with the provisions in the written contract, but may be deemed to be in contravention of its terms. This evidence was incompetent to qualify or modify the terms of. the written contract, which is presumed to embrace the final consummation of the negotiation in respect to all matters embraced within its provisions. And if the existence and force of the contract, as such, may be deemed to have unquestionably been established at the time such evidence was received, its reception was error. But it
The judgment should be reversed and a new trial granted, costs to abide the event, unless the plaintiff stipulate to deduct from the recovery one hundred and fifty dollars and interest thereon from January 8, 1880. And in that event the judgment be so modified, and as modified, affirmed, without costs of this appeal to either party.
Haight and Dwight, JJ., concur; Barker, P. J., not sitting.