Majority
Headnote
Contracts—Building—When work may be charged by measure and value.This action was brought to foreclose a mechanic’s lien affecting premises located in Brooklyn. The appellant, Kate McCormick, is the owner of the property. The respondent, Feldrnann, was the contractor for the erection of five houses on the premises, and the other respondent’s have mechanic’s liens. The case was tried before a referee, who found that Feldrnann, in August, 1885, entered into a contract with one James Gardner, the general agent of said Kate McCormick, the owner, to erect the five houses for the sum of $23,400, to be paid for in installments as the work progressed, the final payment, when the work was completed, to be $5,400. The referee further found that, after the work was commenced, the contract was, by mutual consent of the owner and contractor, so far departed from as to 1he work to be done, that, as a whole, the work was not substantially that called for by the contract; that'such departures'involved serious and material increase in the cost, and that the parties did not agree that the work should be done for the contract price, nor for any certain price, nor that the houses should be completed as a condition for the payment of any part of •the price. The referee also finds that Feldrnann did not entirely complete said houses; that the value of the labor and materials done and furnished was $24,200,-and that the payments amounted to $17,200, leaving a balance due of $7,000, with interest; that neither the original contract, nor the evidence, furnishes data from which it can be ascertained what the parties originally estimated or agreed upon to be the value of such of the labor and materials done and furnished as the original contract cálled for, or what was agreed to be paid therefor, or that any certain sum was agreed to be paid therefor. The referee orders, judgment in favor of the lienors, and for the balance after paying the liens, in favor of Feldrnann, the contractor, and the owner, Kate McCormick, appealed from the judgment entered in conformity to the referee’s report.
The learned counsel for the respondents Goodwin and Feldrnann quotes in his brief from Addison on Contracts (foot paging 585, 586), and the law applicable to the points ■ raised on this appeal is there correctly and concisely stated. “If work has been agreed to be done, and materials supplied, under a building contract for certain estimated price,, ■and there has subsequently been a deviation from the original plan by consent of the parties, the contract and ' estimate are not, on that account, excluded, but are to be the rule of payment, as far as the contract can be traced to<
We have quoted freely from the referee, and in his own words, and shall also assume that the law is as stated in the foregoing quotation from Addison; but when we examine the testimony we are unable to agree to the findings of fact of the learned referee. It appears that there were many variations from the contract, that such changes were made by consent of the parties, and it also appears that Feldmann, or some witness in his behalf, was able to detail the alterations and estimate the fair value of each deviation, and that during the progress of the work no new express contract was .made. Where the facts are as above stated, then the contract work surely can be traced and the extra work can be figured out.1
The contractor Feldmann furnished a list of the alterations and values for same: Change of gable end fence, worth forty dollars; basements and fence doors of corner house, ash trim instead of,pine, $350; .panelled ceilings, $300; wainscoting and cap instead of chair board, wainscoting back of boilers, he could not give an estimate; seven slate mantels instead of marble, for which Mr. Gardner paid the bill; parlors and halls, cabinet trimmed and other extra work on parlor floors, $816; extra work on second floor, cabinet trim in second floor and wainscoting raised, $181.70; raising upper story of the fifth house instead of mansard roof, $500; extra doors in corner house, $600; extra skylights, fifty dollars. The above claim could not much exceed $2,300. The plumber had an extra bill, itemized, amounting to $485.10. There were other extras, but substantially the changes from the contract have been given in the above statement, and in every case where an alteration was made, testimony was, or could have been, offered showing the value of the extra work.
Testimony was also given on behalf of the respondents for the purpose of showing that Mr. Gardner interfered with the workmen and gave directions,. and the conclusion was sought to be drawn that he did the work himself, and not Feldmann; but the testimony is insufficient to justify such a conclusion. According to Feldmann, he once told the workmen to put more cement in the mortar, and on another occasion he told a man to do something around the chimney, and Mr. Feldmann could not remember any other time. Fol: 150.
The contract called for payments by installments as the work progressed, and every payment was made according to, the contract as the work was done, and Mr. Feldmann
Even though Gardner was officious, and though he ordered many extras, yet we think on the- whole it is clear, as matter of fact, that the work was substantially done under the contract, and that the contract work was traced by the witnesses for the respondents, and also the extra work, and that the value of the extras could be ascertained from their testimony. We, therefore, hold that the judgment must be reversed-on the law and the- facts, the order of reference vacated, and a new trial granted, costs to abide the event.
Van Wtck and Osborne, JJ., concur.