Damages—Breach of warranty.The evidence authorizes the finding that plaintiffs warranted that the wheel should be of the capacity stated, and that there was a breach of such warranty. The plaintiffs claim the wheel was not properly set, but the evidence warrants the conclusion of the referee that it was set substantially as the plaintiffs directed. The plaintiffs claim there was no warranty except as coupled with the condition that the wheel should be tried within thirty days and if not satisfactory or made satisfactory then to be returned. Whether there was such a condition was a question of fact for the referee to dispose of. His firuling against it was not against evidence. We must, therefore, assume there was an express warranty, and this, although the contract was executory, the defendant had a right to rely upon; he was not obliged to rescind. Brigg v. Hilton ( 99 N. Y., 529 ), and cases cited.
The matter of damages presents a more serious question. It is claimed by the defendant that the difference between the rental value of the mill with the wheel as furnished
The defendant to sustain his position cites Griffin v. Colver ( 16 N. Y., 496 ), Rogers v. Beard ( 36 Barb., 37 ), Manhattan Stamping Works v. Koehler ( 45 Hun, 150 ; 10 N. Y. State Rep., 60), Cassidy v. Le Fevre ( 45 N. Y., 562 ). In the Griffin Case the plaintiff agreed to build a steam engine, with boilers, etc., for the defendants, and deliver it by a certain day. There was a delay of a week in the delivery, during which time the defendant lost the use of certain machinery which the engine was intended to drive, as the plaintiff knew. The plaintiff sued for the price and the defendants recouped their damages for the delay. It was held that the ordinary rent or hire which could have been obtained for the use of the machinery whose operation was suspended for want of the steam engine could be recovered as damages. In the Cassidy Case the same principle was asserted as applicable to a case where the use of machinery was lost- during the time spent in making repairs to defective boilers. In the Rogers Case there was a neglect to repair a vessel within the time called for by the contract; and it was held that the measure of damages for the delay was the value of the rent of such a vessel as used or chartered at the time. In the Manhattan Stamping Works Case, the plaintiff leased of the defendant for a year certain premises, together with all the steam power the plaintiff needed in a certain business known to defendant. There was a failure by defendant to furnish steam power. It was held that evidence tending to show what was the ordinary rent or hire of the machinery during the time of the deficiency of power was properly rejected, as no claim for damages upon this ground was alleged in the complaint, it being said that if there had been the proper allegation, the evidence would have been admissible. These cases hardly sustain the defendant’s position. Here there was a sale with a warranty as to capacity. No question about delay in delivery. After the wheel was put in, it was in use for two weeks, when the shaft broke. That was soon repaired, and then there was some further use, or opportunity for use, when, upon 24th of May, 1883, $200 of the price was paid. At that time, as the defendant testifies, one of the plaintiffs told him that if the wheel did not turn out all right, he would make it all right. During the summer it
So far as the case shows there was abundant opportunity to test it before the making of the payment. The defendant had no special contracts in which he suffered damage by reason of insufficient capacity. As the wheel was not taken out or offered to be returned, it is a little difficult to see how the expense of putting it in or taking it out is an element of damages. It was not worthless and the defendant has had and still has the benefit of it. If the difference in rental value is an element, what is the limit as to time? Gan it be said that the rental value for an indefinite time was within the reasonable contemplation of the parties?
In Edwards v. Collson ( 5 Lans., 324 ), it was held that a warranty of a steam engine as having a capacity for work to a certain horse power, as sound and in good order and as having the ability to perform labor to the extent of the capacity warranted, is a general warranty and the damages allowed for its breach are merely the difference between the actual value of the engine and that which it would have had if as warranted, and that this would be so although the engine was sold for the purposes of the defendant’s saw mill, then about to be erected and was to be placed in that mill in running order.
, We think this case is quite in point and presents the proper rule for the present case as it is now developed. If the breakage of the shaft is chargeable to the plaintiffs and within the warranty, the damage or expense and delay occasioned by that may be an additional element. So if before the discovery of the defects or reasonable opportunity to do so, there was special damage unavoidably sustained, that would be allowable if within the complaint according to the case of Zuller v. Rogers ( 7 Hun, 540 ).
We are, therefore, of the opinion that the rule adopted as to damages was erroneous and on that ground the judgment must be reversed.
Martin, J., concurs.
I am inclined to the opinion that the long-continued use of the wheel by defendants as disclosed by the evidence warranted a finding that the defendants had accepted the wheel. Brown v. Foster, 108 N. Y., 387 ; 13 N. Y. State Rep., 805.
I assent to a reversal.
Judgment reversed on the exceptions and a new, trial ordered before another referee, with costs, to abide the event.