Majority
Headnote
Sale — Breach oe contract to deliver.This was not a sale of goods “to arrive” within . the proper meaning of that term. The goods were not purchased to be shipped from Germany under the direction or at the risk of the purchasers, nor were the goods purchased while in transit on the ocean. By the contract the defendant sold 500 tons of kainit, to be delivered from a vessel in New York harbor, and the plaintiff agreed to pay for it on such delivery. In this respect the case differs from Heller v. Allentown Manufacturing Co., 39 Hun, 547 . The contract here was an absolute present sale, and for failure to deliver the defendant is liable. The fact that part of the kainit was pumped overboard and the balance was injured, while at sea, simply proves that the defendant, without any fault on the part of the plaintiffs, was unable to perform his- part of the contract in regard to delivery in New York harbor. The plaintiffs had no interest in the shipment of the goods, nor the method of shipment. These matters did not concern them. The contract expressly provided, in unmistakable language, capable of no other meaning, that the kainit should be delivered by the defendant from a vessel in New York harbor, and that the terms of payment were cash on such delivery at New York.
All the risks in regard to peiformanee devolved upon the de
By this construction of the contract the legal propositions involved are simplified and freed from the technicalities which appear in many of the reported cases. In short, the case resolves itself into the ordinary one of breach of contract to deliver, and this is what we think it is. There was no request to go to the jury, and no dispute as to the amount of the damages sustained. It follows, that the judgment appealed from must be affirmed, with costs.
McAdam, Ch. J., Ehrlich and Holme, JJ., concur.