Majority
Headnote
Municipal cobfobation—Conteact.The release was a good answer to the second cause of action alleged in the complaint, founded on the delay on the part of the city to remove the obstructions in the street, thereby-preventing the plaintiff from proceeding with the performance of the contract Seymour v. Minturn, 17 Johns., 170 ; Gray v. Barton, 55 N. Y., 68 ; Coulter v. Board of Education, 63 id., 366; Simson v. Brown, 68 id., 355.
The claim to recover the sum retained by the city for inspectors’ fees for the 375 days beyond the 320 days allowed by the contract for the completion of the work is based on the ground that performance was prevented by the neglect of the city to remove the obstructions from the street. The plaintiff requested the court to submit the question to the jury, which request was refused, and the plaintiff excepted. There was no error in this ruling. The contract provides that in computing the time exceeding the 320 days, “ during which the work of completing the contract is delayed in consequence of any act or omission of the party of the first part
If the commissioner had neglected or refused to act when called upon to do so, a different question would be presented. Smith v. Brady, 17 N. Y., 176 .; Bowery Nat. Bank v. Mayor, etc., 63 id., 337; Nolan v. Whitney, 88 id., 648.
The point that it was not proved that the inspector, Fitzgerald, who was paid for 304 days’ inspection, had ever performed the work of inspection, is not presented by the case, as the deposition of Fitzgerald, which was read on the trial, is not printed, and this evidence may have supplied the proof which is now absent.
We find no error in the judgment, and it should, therefore, be affirmed.
All concur.