Majority
Headnote
Mechanic’s lien — Building contract.The principal question in this case was one of fact. The plaintiff is a builder and the defendant McGuire owned a lot of land upon which the plaintiff agreed to erect a. building for an agreed price. The first payment of $1,500 was paid. The second payment of $2,000 was due “when cornice is set, siding on and floors laid.” Proof was given tending to show that the payment was due and payable; that the work called for was done and the certificate of the architect delivered; that a portion of the siding was not on, but this could be done better at a later stage of the work, and that a full performance in this respect was waived. Notwithstanding this, the owner refused to pay the instalment and the contractors stopped work. The-architect testified that the siding omitted was small places between the stone front, and that the stone front was to be put up first. This was included in the third payment The owner at first made no objection to the omission, but promised payment of the second instalment. The trial court could not, therefore, find otherwise than that the second payment was due and payable. The plaintiff proved extra work beyond this to support the finding of the court that there was due at the time of the breach of the contract the sum of $2,500, with interest thereon from 27th April, 1887. Whether the building was larger than the specifica
The judgment should, therefore, be affirmed, with costs.
Dykmakt and Pratt, JJ., concur.