Majority
Headnote
1. Reference — Findings cannot be objected to as against evidence where referee allowed to inspect premises.On the 28th day of September, 1886, John 'Strachen, a mason and contractor of the city of Rochester, entered into a written agreement with Max L. Gutmann, of the same place, to build and finish a four-story brick block and apartment-house in the city of Rochester, in pursuance of drawings, details and general specifications made by James C. Cutler, an architect.
The building was to be completed by the 1st day of April, 1887. • The price, $16,500, to be paid in installments to the amount of eighty per cent as the work progressed, and the balance *>n the proper completion of the work; payments only to be made on the architect’s certificate. All the drawings or specifications are either embodied in or referred to in the agreement On the same day John Wadsworth & Son, contractors, of the village of Brockport, entered into a written contract with John R. Strachen to construct the carpenter work of said building for the sum of $6,000, payments to be made as the money should be received by Strachen from Gutmann on his contract, and on the architect’s certificate. The drawings and specifications of the original contract were referred to as a part of this. The job was to be finished at the same time.
On the same day Frank P. Crouch executed a bond to Strachen for $6,000, the condition of which was that if Wadsworth & Son should in all things perform their contract, the agreement should be void; otherwise in full force.
The plaintiffs in Mo. 1 brought the action to recover a balance alleged to be due of $1,650 on the $6,000 contract, over and above all payments. It is alleged' this claim was assigned to the plaintiffs by the Wadsworths. It is also alleged that on the 27tk
“Rochester, N. Y., June 27, 1887.
" Max L. Gutmann:
“Please pay to G. W. & F. P. Crouch sixteen hundred and fifty ($1,650) dollars, and charge the same to our contract.
(Signed) “ John Wadsworth & Son.”
This was accepted in the following form:
“ August 6, 11:30 A. M.
“ This order is accepted, payable out of any balance which may be due Messrs. Wadsworth & Son when the building is completed, to the extent of such unpaid balance, and no more, and on the architect’s certificate only.
(Signed) “Max L. Gutmann.”
It is alleged that the order or paper as accepted was assigned to the plaintiffs. The defendant denied performance by Strachen and Wadsworth & Son, and asked a dismissal of the complaint. In No. 2, the plaintiff seeks to recover the amount of the bond upon the claim of non-performance by Wadsworth & Son. The complaint alleges an assignment by Strachen to the plaintiff, and further states Wadsworth & Son did not perform, and that thus Strachen was prevented from performing. The answer alleges substantial performance and asks a dismissal of the. complaint. Both cases were referred to the same referee. In No. 1, the referee reported $633.67 for the plaintiffs. In No. 2, the complaint was dismissed. Judgment was entered by the successful party upon each report, and the defendant in No. 1 and plaintiff in No. 2 appealed to this court.
As the rights of all the parties depend upon the same questions, the cases were practically tried as one action, with a stipulation that the testimony in one case so far as applicable should apply to the other.
In No. 1 the referee finds the contracts, and that on the 5th day of August, 1887, Strachen served written notice to make no further payments to Wadsworth & Son. That the Wadsworths commenced work on the building about the 1st of November, 1886, and on the 1st day of February, 1887, stopped work at the instance of the architect, and also on account of inclement weather. At this time the roof was on the building. Work was after that resumed and continued until the 30th day of July, 1887, when it ceased. A strike in April caused a delay of two weeks, and there were some other delays. That Strachen substantially performed the work on his part, and that he was paid, from time to time, $8,500.45, which with the $6,000 contract and the amount allowed for deductions equalled the contract price, $16,500. The referee also finds that the Wadsworths substantially performed their contract, except in certain particulars in which they were guilty of no willful or intentional violation of their contract; that the work not performed by the Wadsworths was of the value of $145.
That the order of June 27th was given to the plaintiff for lumber which was furnished to the Wadsworths and used in the erection of the building. _ That plaintiffs had requested the architect for a certificate, but he had refused to give one, and that such refusal was unjust and unreasonable. That the plaintiffs or the Wadsworths did not receive notice to complete the job. That Strachen and the architect had a settlement on the 8th day of August, 1887. That on this settlement the $6,000 was deducted from the contract price of $16,500, and also $1,499.55 for damages under the contract, which included $1,300 for lost time. That the assignment to the plaintiffs "was for a valuable consideration.
The findings in No. 2 were substantially the same as those in No. 1, with the additional finding that no consideration was paid to Strachen for the assignment of said bond. It was stipulated that the referee might inspect the building, which he did.
It thus appears that before the 1st day of August, 1887, the defendant paid Strachen $8,500.45, and that afterwards and
All controversies between the original contractors are elimi"nated from the case, and a consideration of what occurred under, or whether it was performed, is only important as it affects the parties to these actions. It must be assumed that the stipulation that the referee inspect the building was intended to aid him in weighing the evidence before him, as well as secure the information an inspection would impart, in the absence of any limitation as to the uses which the referee might make of a personal examination. In support of his findings, he was not restricted to what he discovered or actually viewed, but he was at liberty to construe the testimony in the light of the information thus obtained.
In West v. Kiersted et al., 15 N. Y. Wk. Dig., 549, it was held that “ where, by consent of parties, the referee inspects the premises in dispute, his report must practically be conclusive on all the facts whil;h carne within his observation; the court cannot tell what he saw.”
To the same effect is Claflin v. Meyer, 75 N. Y., 260 .
The exceptions, therefore, based upon the assumption that certain findings are against or without evidence, are not available.
The substantial question upon which these appeals depend is based upon the referee’s findings. The, learned counsel for the appellant contends that those findings negative the claim of a subtantial performance, and would defeat a recovery in No. 1 and ecure a different result in No. 2.
The case shows that all the parties treated the original contract o far completed that the defects might be paid for by deducting heir cost from the contract price. This was the theory upon hich the parties proceeded in their settlement.' If it should be daimed that the expectation of recovering full damages for nonerformance'from the obligor in the bond was one of the elements vhieh produced the settlement, the natural answer would be that t cannot be assumed on these appeals that the appellant contemlated an injustice to the bondsman as one of the conditions of ettlement between the parties to the original contract Such a ontention by the appellant ought not to aid' him in securing a versai
The conclusions of the referee as a whole seem to have been substantially just and equitable, and the exceptions do not seem to warrant a reversal of either judgment.
Judgments must be affirmed.
Dwight, P. J., and Macomber, J., concur.