Majority
Headnote
Contract—Performance—Occupancy or presence of owner of building NO WAIVER OF DEFECTS.This appeal is brought by the plaintiff from a judgment against him, entered' upon the report of a referee dismissing the complaint.
The action was to foreclose a mechanic’s lien, fheci against the defendant, Bertha J. Herman, as owner, and John L. Herman, as contractor.
The complaint alleges that the defendant, Bertha u., was the owner, and that she with her husband occupied the premises in the city af Albany, and that between the 15th and 30th of April, 1889, the plaintiff at the instance and request of the defendants, furnished materials and performed labor as a builder upon such
The defendants answer separately; the defendant Bertha denying any employment by her of the plaintiff to furnish material, or to do work on the building on her premises.
The defendant, John L. Herman, in his answer, set up a special contract under which he alleges such work and material was performed and furnished, and that the plaintiff failed to perform the same, and set up matters as counterclaim, and demands an affirmative judgment for himself.
The issue was tried by a referee, who found that the work done, and materials furnished was done and furnished under a special contract; that the plaintiff had failed to perform the same according to its terms, and was not entitled to recover.
There was a conflict of evidence as to the terms of the agreement between the parties, and, also, aS to the manner of the performance of the work, but that conflict raised purely disputed questions of fact, proper for the determination of the referee, and on a careful examination of the evidence on both sides of these controverted questions we think there was abundant evidence to support the referee’s conclusion upon the facts.
But it is insisted on the part of the appellant that the material furnished and work done was all done under the observation and special direction of the defendants, and that they cannot now object to the manner of performance.
But upon this branch of the case, as well as the other, the referee finds the fact against the plaintiff, and upon sufficient evidence to uphold his finding on appeal.
The plaintiff also insists that the sash furnished by him, and of which the defendant John complains, were accepted by the defendants without objection, and that they 'acquiesced in the use of the same, and that, therefore, they are estopped, and will not be heard to complain for the purpose of avoiding payment.
It is quite true that the sash were placed upon defendant’s building, and they, with the balance of the structure, were used by the defendants, but the evidence discloses that objections to their kind and quality were made by the defendant John, and the referee finds that they were not accepted by the defendants.
“ Whether a contract of this character has been substantially performed is a question of fact, depending upon all the circumstances of thecase.” Nolan v. Whitney, 88 N. Y., 650 , and cases there cited.
It is a general and quite elementary rule of law that a party must perform his contract before he can claim the consideration due him upon performance; but the performance need not be in all cases literal and exact,.but it must be a substantial compliance with the contract, and whether there has been a substantial compliance is a question of fact to be determined, as we have seen, by the trial court, especially in cases of conflicting evidence.
The work and material having been applied upon the premises, the owner has no other alternative than to occupy with additions upon the property; to hold such occupancy to be waiver of a performance would" be to compel the property owner to accept an imperfect or incomplete performance of the contract, or forfeit the use of the building when the builder neglects or refuses to complete the contract.
In Kidd v. McCormick, 83 N. Y., 392 , it was held that when the builder under contract abandons the building before completing the contract, the owner may complete the work, and still insist on the terms of the contract
This case largely turns upon questions of fact which were considered and passed upon by the referee. And his findings are all supported by evidence.
We see no'reasom for reversing the judgment
Judgment-affirmed, with costs.
Learned, P. J., and Landon, J., concur.