Majority
Headnote
1. Municipal corporations—Contract—Pleading.On December 27, 1886, one James E. Devlin contracted with the defendants to build a sewer on One Hundred and Forty-eighth street, between Seventh and Eighth avenues, in the city of New York, the work to be commenced at such time as the commissioner of public works should designate, and to be completed within sixty days. At the time of awarding the contract to Devlin the latter executed and delivered to the defendants a bond in the penalty of $2,000, with the plaintiffs as sureties, and conditioned for the faithful performance of the contract by Devlin. The contract, among other things, provided for an assignment thereof by Devlin upon the previous consent in writing to such assignment to be endorsed upon the contract by the commissioner of public works. Devlin, having been duly notified to proceed with the construction of the sewer, delayed the commencement of the work, and was thereupon again notified by the commissioner of public works that, unless the work was begun and completed within. a reasonable time, the contract would be declared abandoned, and he and his sureties held answerable for
After completion of the work plaintiffs demanded payment of the contract price, to wit, $2,851.54, which amount was conceded to be correct, but defendants claimed to be entitled to a deduction of $880 under the contract, being at the rate of twenty dollars per day for forty-four days employed in the construction of the sewer in excess of the sixty days within which the work was agreed to be done. To this deduction plaintiffs objected and thereupon brought suit to recover the full amount and did recover a verdict for the same, with interest, and from the judgment entered thereon defendants have appealed.
The record of this case as the same has been presented to us shows that the contentions of the defendant, upon the trial were threefold:
First. That plaintiffs had not proved the performance of the work and that they have furnished the materials alleged in the complaint, nor their value;
Second. That plaintiffs had not shown either a contract between themselves and the defendant, pursuant to law, for the performance of the work, or an assignment to them of the contract with Devlin;
Third. That defendants were entitled to a deduction of $880 for damages for the excessive number of days employed in the construction of the sewer.
The first contention arose upon a motion for the dismissal of the complaint,- when the plaintiffs rested. The learned trial justice ruled, and we think properly so, that the answer did not admit the work or its value and required plaintiffs to give proof of these facts, and thereupon plaintiffs’ counsel was permitted to introduce in evidence what purports to be a portion of a certificate made by the commissioner of public works. This extract may be found at page 21 of the case on appeal, but it is difficult to understand how it can be construed to be any proof of the rendition of the work, the furnishing of the materials, or proof of the value of any work performed by the plaintiffs, or their assignor. It is at most but a specification of the work therein mentioned with certain prices set opposite, and contains no admission, express or implied, that the work therein mentioned was performed by any person whatsoever.
Nevertheless the motion to dismiss was properly denied. The answer admits that certain worJc was performed in the construction of the sewer, and this entitled the plaintiffs to a recovery of at least nominal damages, and hence it would have been error to dismiss the complaint. The defect in plaintiffs’ proof was subsequently abundantly supplied by the defendants, when defendants’
Defendants’ second contention was disposed of by the verbal stipulation entered into by counsel for the respective parties to this appeal, made in open court upon the argument, to the effect that this court should dispose of the appeal as though the plaintiffs were properly the assignees of the contract with Devlin, and that the pleadings for such purpose should be deemed to be amended so as to contain an allegation of such assignment in the complaint and an admission of the fact of such assignment in the answer. The appellate court has power to allow such amendment, see Reeder v. Sayre, 70 N. Y., 180 ; Volkening v. DeGraaf, 81 id., 268 , and the order to be entered on the decision of this appeal should contain a direction that the pleadings be amended in accordance with the stipulation.
The remaining contention, that respecting the claim of the defendant for $880 liquidated damages, arises out of the following clause of the contract with Devlin, to wit: “ The said party of the second part (Devlin) hereby further agrees, that he will commence the aforesaid work on such day and at such place or places as the said commissioner may designate, and progress therewith so as to complete the same in accordance with this agreement, on or before sixty days thereafter; that the said number of days shall not be construed to mean consecutive days, but the aggregate time of all inspectors who may be employed on the work; and that in the computation of said time, the length of time (expressed in days and parts of a day) during which the work or any part or section thereof has been delayed in consequence of the condition of the weather, or tides, or by any difficult circumstances so unusual that they could not be foreseen previous to or avoided during the prosecution of the work; or by any act or omission of the parties of the first part (all of which shall be determined by the said commissioner of public works, who shall certify to the same in writing), and also Sundays and holidays, on which no work is done, and days on which the prosecution of the whole work is suspended by order in writing by the said commissioner in writing, shall be excluded. * * * And the said party of the second part hereby further agrees that the said parties of the first part shall be, and they are hereby, authorized to deduct and retain out of the moneys which may be due or become due to the said party of the second part under this agreement, as damages for the non-completion of the work aforesaid within the time hereinbefore stipulated for its completion, the sum of twenty dollars for each and every day the aggregate time of the inspectors employed upon said work may exceed the said stipulated time for its completion, which said sum of twenty dollars per day is hereby, in view of the difficulty of estimating such damages, agreed upon, fixed and determined by, the parties hereto as the liquidated damages that the parties of the first part will suffer by reason of such default, and not by way of penalty.”
The decision in that case extends no further than that upon proof by the defendant that the time employed in the performance of the work exceeded the time allotted by the contract, the defendant is entitled to a deduction, from the contract price agreed upon to be paid for the work, of the liquidated damages fixed for each day in excess of the allotted number of days, and. that if the contractor desires to defeat or diminish the deduction for such liquidated damages, it is incumbent upon him to procure a certificate of the commissioner of public works excusing the delay, or part of such delay, or to show that such a certificate had been demanded, and that the commissioner had neglected or refused to act in the premises.
To have availed themselves, however, of the right to deduct the liquidated damages provided for in the contract, the defendants should have pleaded such right by proper averments and recitals. The right to the deduction constitutes either a counterclaim to the amount of liquidated damages claimed, or a partial defense to plaintiff’s cause of action. If relied upon as a counterclaim, the answer should have so stated and asked for affirmative relief, so that plaintiffs upon sufficient notice might have replied thereto if they had so desired, and thus have secured the right to attack the commissioner’s certificate by making the question of the good faith and fairness of the certificate an issue in the action. Equitable Life Assurance Society v. Cuyler, 75 N. Y., 511 . Again, if the allegations of the answer respecting the commissioner’s certificate and the deduction of liquidated damages were intended to be interposed as a partial defense to the plaintiff’s cause of action, the answer was not effective for that purpose because it did not expressly state that the averments were relied upon as a partial defense. See Code of Civil Procedure, § 508.
There was, then, at the time of the trial no issue to be disposed of touching the defendants’ claim for liquidated damages, and this view renders unnecessary the discussion of the objections to the admission and exclusion of evidence bearing upon such claim, as well as defendants’ exceptions to the charge and refusals to charge so far as they refer to the same claim. If defendants were
The judgment and order appealed from should be affirmed, with costs.
Daly, Ch. J., and Pryor, J., concur.