Majority
Headnote
Specific performance—Not decreed where terms - of contract uncertain.The plaintiff contends that it was the intention of the parties that the unsigned instrument should be considered simply as a memorial of terms already agreed upon, and not as the contract by which alone they were to be bound. This position finds some support in the early negotiations between the parties as well as in the first sentence of the receipt given by Mrs. Arnold, through the agency of her husband, for the sum advanced, as it provides that such money “is for the first payment mentioned in (the) unsigned agreement * * * which is to be fulfilled ” when the plaintiff is satisfied. Standing by itself, this would indicate that the instrument was to be “fulfilled” in the sense of performed, or carried into effect, upon the happening of the contingency named. The remainder of the receipt, however, shows, as we think, that the parties intended to leave the matter open and neither to make a binding agreement then nor to treat anything said or done in the past as yet binding. This follows from the requirement to return the money on a day named in case the machines should not be satisfactory to the plaintiff, or if the unsigned agreement should not, for any reason, Be consummated. This language overthrows the theory that any agreement, upon which the minds of the parties had finally met, was then in existence, for it assumes that neither party is yet bound to do anything except with reference to a return of the money advanced. All prior negotiations are presumed to be embraced in this receipt, which is a contract and is the only one relating to the subject that was ever signed by any of the parties. Renard v. Sampson, 12 N. Y., 561 ; Long v. N. Y. Central R. R. Co., 50 id., 76.
Nearly a year after the date of the receipt two of the parties, without the assent of the third, so far as appears, agreed to modify the proposed agreement in two material respects, and that all three should sign it, as amended, on a day named. The modification was not reduced to writing and the instrument, even at the time of the trial, was not completed or ready for the signatures of the parties. Taking the view most favorable to the plaintiff, this was simply an oral agreement to sign an instrument not yet in existence, because it had not been wholly written out. Even the written portion required rewriting in part in order to conform to the wishes of the parties.
It was virtually an oral agreement to prepare and sign a written agreement, not as evidence of an existing contract, but as an original contract. Whether specific performance of an oral agreement
The proposed agreement was blank, also, as to its duration, to the'extent at least of an entire year, a consideration of some importance when it is borne in mind that the amount of the royalties was guaranteed by the plaintiff to be not less than $6,000 a year.
We agree with the learned general term in saying “it is impossible to deduce from this unsigned instrument the terms of a contract sufficiently clear and definite to enable a court to enforce the specific performance- thereof.” We do not think that the parties should be compelled to sign a writing so incomplete and indefinite as to be incapable of enforcement when signed.
The judgment should be affirmed, with costs to the defendants Jennings, but without costs to the defendants Arnold.
All concur.