Majority
Headnote
1. Easement—Bight to take water from spring—Location.Plaintiff has succeeded to the rights acquired by William Colson under the grant and easement executed by the defendant on the 20th of August, 1852. He is entitled to all the rights, privileges and enjoyments mentioned in that instrument While the instrument is indefinite in respect to the location of the pipe to be taken from the spring mentioned in the instrument, three-quarters of an inch in diameter, to a certain point in the meadow of defendant, where the union of the pipe with the one-half inch in diameter is to be made to carry the water across the remaining portion of the defendant’s premises to the lands of Colson, yét as the parties made a practical location and usage, laying both the pipes in a track assented to by the parties to the instrument, and enjoyed by them, that portion of the agreement became definite and certain by reason of the acts of the parties in the premises. Tyler v. Cooper, 47 Hun, 94 ; S. C., 16 N. Y. State Rep., 545.
When the instrument of 1852 was executed, Colson and the defendant owned adjacent farms in the town of Hamilton, as the instrument recites; and the instrument also recites that “ there is a spring of water situated in and upon the land ’’ of the defendant; and it also recites that “ said spring is situated west from the dwelling house of the party of the first part” The instrument also recites a consideration moving from Colson to the defendant, which was an agreement on the part of Colson binding him “ to convey the water from said spring in f- inch lead pipe, which is to be laid under ground of sufficient depth to preserve said pipe from injury by frost or other causes.” The evidence discloses that the consideration or agreement was fulfilled, as Colson shortly after the agreement was entered into laid a pipe so as to conduct the water from the spring a distance of some twenty rods, having a size of three-quarter inch, and for some eighty rods of one-half inch in diameter, in accordance with his agreement to cany the water “ into the meadow of the ” defendant, which in the instrument is declared in express words to be the consideration for the grant made by the defendant to Colson and his assigns and heirs. The instrument then proceeds to state, viz.: “The party of the first part has hereby granted, bargained, sold, released and confirmed, and by these presents does bargain, sell, release and confirm unto the said party of the second part, his heirs and assigns, all the water of said spring which can be conducted through one-half inch lead pipe; the party of the second part has the right to all the water which can run through said one-lialf inch pipe, said half inch pipe to be inserted at the termination of the three-quarter inch pipe, as before described, to be constructed and kept in repair at the cost, charge and expense of the party of the sec
Again the grant contains the following definite language in respect to the conduit to be used, and the manner of its use, and names the party on whom the burden rests of keeping it in repair■ as in the instrument we find the following language, in respect to the conduit: “ To be constructed and kept in repair at the cost, charge and expense of the party of the second part, to have and to hold all and singular the same easement and privilege to the said party of the second part, his heirs and assigns forever, as appurtenances belonging to his and their lands as aforesaid.” The instrument serves as an express grant and is itself “ the creation of the easement ” and in clear language it expresses the nature and extent From that language in connection with the circumstances existing at the time of making the instrument the nature and extent of the grant is to be determined. 2 Washburn on Beal Estate, 278, 3d ed. If the construction was doubtful the interpretation according to authority should be given favorable to the grantee. Fi sk v. Wilber et al., 7 Barb., 395 . The language used very clearly casts the burden upon the dominant estate to keep in repair the easement and its incidents. Such is the general rule in respect to easements. Mr. Washburn says, p. 311, 2d vol., viz.: “ As a general proposition, the dominant estate is bound to repair the way it enjoys over the servient estate, though the owner of the latter may, by grant, or reservation or by prescription, be bound to make the necessary repairs in order to its enjoyment.” The important and substantive thing granted is the use of the water, as well as the privilege of conducting it from the mentioned
If the lowering of the tub or box a few inches, if clearing the earth from under it fifteen inches and letting the tub down, were acts necessary to secure to the plaintiff the use of such water as would flow through the prescribed pipe, then they were acts which were lawful and reasonable; and after they were performed and the site put in situation to yield the required quantity of water the plaintiff had the right to have it remain in that situation. The defendant had not the right to disturb; to interfere or displace the reasonable arrangements made to secure the quantity of water conveyed by the grant The defendant had. undertaken that the owner of the dominant estate should have “ the privilege ” of “ all of the water of said spring which can be conducted through a one-half inch lead pipe,” and in view of the grant the plaintif f has the right to all the water which can run through said one-half inch pipe.” In this connection the language used by the
Attention has been called to Phelps v. Nowlen, 72 N. Y., 39 , where it was held: “A party is not liable for the consequences of an act done upon his own land, lawful in itself and which does not infringe upon any lawful rights of another, simply because he was influenced in the doing of it by wrong and malicious mo five; the courts will not inquire into the motives actuating a person in the enforcement of a legal right.' It our construction of the grant already intimated is correct, that case does not aid the re spondent, who, having conferred a right upon the plaintiff, was not at liberty to infringe upon it by preventing by direct acts the plaintiff from the enjoyment of the right secured to him by the grant. Attention has been given to Bliss v, Greeley, 45 N. Y., 671 , so much relied upon by the respondent to sustain the judgment before us. In that case that was a limited and specific grant of “the right to dig and stone up a certain spring, and conduct the -water therefrom through the grantor’s land, by a specified pipe, to the grantee’s house, with covenant of warranty.” It was held that such a grant “ does not render the entire premises servient to the easement; and the grantor may lawfully sink another spring, but twenty-seven feet distant, although the effect is to render the first one useless.” In the course of the opinion delivered in that case it is said: “ The grant and the covenants of the grantor are the precise measure of the plaintiff’s right,” and after stating that the grant conferred “the right to' dig out and box this spring, and to put a pipe in it,” the pertinent question is asked by the judge: “Did he thereby covenant that he would not use the rest of his farm in a farmer-like manner ? ” and the burden of the opinion is to answer in the negative, and later on the learned judge says: “This grant prevents the grantor and his assigns from any substantial interference with the spring or the pipe. It does not prevent their improvement or use of the residue of the farpa.”
In Johnstown Cheese Mf’g Co. v. Veghte, 69 N. Y,, 23 , the case is referred to in the following language, viz.: “ The case of Bliss v. Greeley, 45 N. Y., 671 , is cited on the part of the defendant as in conflict with this judgment; but the facts of that case were very different. In that case there was simply a grant of a right to dig and stone up a certain spring and to conduct the water there
It is claimed by the learned counsel for the respondent that the burden imposed cannot be made greater than it was at the time of the execution of the conveyance, and he has called our attention to Roberts v. Roberts, 7 Lansing, 55; S. C. affirmed 55 N. Y., 275 . We do not understand that this is in conflict with the views already . expressed, for, as we understand it, it is held “ that the burden imposed cannot be made greater than it was at the time of the conveyance.” According to the evidence the plaintiff’s right secured by the grant, and the privileges, of the easement mentioned therein, are valuable and important, and are entitled to the protection of a court of equity. The foregoing views lead to the-conclusion that the result at the special term was erroneous.
Judgment reversed, and a new trial ordered, with costs to abide-the event.
Martin and Merwin, JJ., concur.