Majority
Headnote
1. Hew York city—Contract—Forfeiture of deposit.In this case certain parts of the defendant’s answer were stricken out as sham and the rest of it overruled as frivolous and judgment ordered for the plaintiff for the sum demanded in the complaint The defendant appealed from the ■order which thus disposed of its answer and also from the judgment.
The plaiptiff claimed that the defendant was indebted to him in the sum of $1,000 and the interest thereon, that being the amount deposited by him in the form of a certified check with the proper ■officer under the laws and ordinances governing the letting of ■'contracts in the city of Hew York for public work, and the defendant claims that the same has been, under the law, forfeited to the city, and that it is entitled to retain it. The complaint alleges that notice was published inviting bids and proposals for regulating' a street to be made to the department of public works ■and requiring that the bids or proposals for doing the work be accompanied by a bond of $20,000 with two sufficient sureties, •conditioned for the faithful performance of the work embraced in the bid, 'and also a certified check upon a state or national bank, doing business in said city, for five per cent of the amount ■of the bond which, in this case, called for a check of one thousand dollars.- '
On the 14th of July, 1886, the plaintiff, in conformity with the notice, presented to the department his bid with the bond and the check, which was made payable to the comptroller. The complaint then avers that other proposals were in like manner presented by others, for the same work, with bonds and certified checks as required by law, but the plaintiff was found to be the lowest bidder. That thereupon the commissioner transmitted his bid with the bond and check to the comptroller for his approval, if the bond was found sufficient, but the comptroller, although ■the bond was good and the sureties sufficient, arbitrarily, unjustly and illegally refused to approve and notify the commissioner thereof, but did improperly and unjustly notify him that the ■sureties had failed to qualify, which was in fact untrue. That the ■commissioner did not make an award of said contract to the plaintiff and did not notify him of any such award, but subsequently re-advertised and awarded the contract to another. That the comptroller retained the check till about August 23, 1890, when, upon demand being made by the plaintiff for its return to him, it was
The mere fact that a party who has made proposals for public work in the city of Hew York is the lowest bidder and knows that fact does not necessarily entitle him to the contract and does not constitute an award to him of such contract, within the meaning of the law regulating the letting of. work upon competitive bids. The officer charged with the duty of awarding the contract may and in some cases would very properly determine that the interests of the city would be best subserved by rejecting .proposals to enter into a contract with a party who, though he might be the lowest bidder, yet did not possess such advantages and facilities for the performance of the contract as to render his proposal on the whole for the interests of the city. The commissioner may reject all the bids and readvertise the work if in his judgment and discretion such course is for the best interest of the municipality. The awarding of the contract on the part of the officer to one of several bidders requires the exercise on his part of judgment and discretion and the award itself should be manifested by some formal official act on his part and ordinarily reduced to writing and made a part of the records in his department. In no other way can the rights of the parties be preserved, at least prior to the actual execution of the contract. The mere arithmetical operation of ascertaining which bid is the lowest does not constitute an award. The duty of the commissioner to examine the proposals and award the contract is judicial in its nature and character, East River Gas Light Co. v. Donnelly, 93 N. Y., 557 ; People v. Gleason, 121 id., 631 ; 31 St. Rep., 903 , and the award is the result of a judicial act. The statute contemplates and requires three things on the part of the city or the proper officer after the proposals, bond and check have been presented. (1) That the contract shall be readvertised and relet whenever the lowest bidder shall neglect or refuse to accept the contract within five days after written notice that the same has been awarded to his bid or proposal, or when he accepts but does not execute the contract and give the proper security. (2) That the comptroller shall return all the checks to the persons depositing the same, except that of the lowest bidder, within three days after the decision as to who is such lowest bidder. (3) If the lowest bidder shall, within five days after due notice that the contract has been awarded to him, neglect or refuse to execute the same the chéck deposited or its proceeds shall be forfeited to the city as liquidated damages and paid into the sinking fund, but if he execute the contract within that time, the deposit shall be returned to him. When the city seeks to retain the proceeds of such deposits as forfeited to it under the statute it ought to be prepared to show all the facts necessary to sustain its claim. An answer to a suit by the owner of the check confined to denials of legal conclusions and which evades the real issue is not entitled to very
The answer in this case was served only after seven different extensions of the time to answer had been given by the plaintiff to the defendant and after judgment by default had been entered and opened on application to the court. When interposed, it was held by the special term to be bad in form and substance. We think this conclusion was right, and that the judgment and order appealed from should be affirmed, with costs.
All concur, except Gray, J., not voting.