Williams v. Boehan

44 N.Y. St. Rep. 220 Court N.Y. Super. Ct. Decision date 1892-01-29 English

Delivered by Gildersleeve, J.

Contents

Majority

p. 220
Richard Williams et al., Resp’ts, v. Daniel Boehan et al., App’lts.
(New York Superior Court, General Term,
Filed January 29, 1892.)

Headnote

1, Contract—Building — Variance between, original and working plans.
Defendants entered into a contract to alter certain buildings for plaintiffs for a certain price, based on the plans and specifications alone. After they had done part of the preparatory work they received the working plans, which they claimed were materially different from those on whjch. they estimated, and which largely increased the cost, and they therefore abandoned the work. In an action for breach of the contract they counterclaimed for the work they had done. Held, that if there was a, material variance defendants were justified in abandoning the contract and were entitled to recover on their counterclaim.
2. Same—Charge—Harmless error.
The court charged that if there was a material variance defendants could either go on with the contract or go off ; that they chose to go ofl: and that was an end of their counterclaim. Held, error; but that as the-verdict in favor of plaintiffs established that there was no material variance, such error was not available.
Appeal from a judgment entered on a verdict of a jury in favor of the plaintiffs, and from an order denying defendants’ motion for a new trial.
Lachman, Morgenthau & Goldsmith, for app’lts; M. Owen Roberts? for resp’ts.

This action was brought to recover damages for the breach of a building contract Messrs. King & Small,, architects, at the request of plaintiffs, had prepared plans and specifications, setting forth the character and extent of the mason and stone work required to be done. These plans and specifications were given into the possession of the defendants to enable them to estimate the cost of the work, and make a bid therefor. The defendants had no other information as to the nature of the work or materials necessary for the same. Their estimate was-based thereon, and they agreed with plaintiffs to do the work for $5,827, “ in accordance with said plans and specifications.” The work consisted of alterations for the purpose of changing certain dwellings into stores. The defendants entered upon the performance of their contract by commencing to take down the fronts of the dwellings and doing such preliminary work as was. necessary before the work of reconstruction called for by the plans- and specifications began. When the value of the work thus done-had reached the sum of $114.15, as defendants claim, the defendants refused to continue the work and complete the contract. At this stage of the work, but prior to such refusal, the “detailed drawings ” or “working plans,” prepared by the architects, were-placed in the hands of the defendants. The defendants claimed there was a substantial variance between the “working plans'” and the “ elevation plans,” upon which they had estimated; that the “ working plans ” called for two inches higher sills, an addition of four to four and a half on the cornices, and other variations. involving much greater expense, whereby the value of the work

p. 221
was increased $950. The plaintiffs insisted upon the defendants; working according to the plans as altered, and performing the-extra work as part of their original contract, without extra compensation. This the defendants refused to do, for the reasons-above stated, claiming that this insistence of the plaintiffs was an attempt to arbitrarily modify the agreement, without defendants’' consent.

The plaintiffs procured other parties to do the work at a cost-over and above the contract price with the defendants of $923, and brought this action tor a breach of contract, setting up the said sum of $923 as the measure of damage^. The answer is a. substantial admission of the agreement, an averment that the defendants entered upon the performance of the work thereunder, and an allegation “ that the drawings given to them to estimate on, called the ‘ front elevation plans,’ were changed in the detailed or 1 working drawings ’ so as to materially increase the amount of work to be done,” and séts up a counterclaim of $114.15 for work done prior to their abandonment thereof. To-this counterclaim the plaintiffs duly replied. The trial proceeded for the purpose of determining the rights of the plaintiffs to the-former sum, or any part thereof, and the rights of the defendants-to the latter sum, or any part thereof.

The defendants had a right to refuse to continue under their contract, if the work which the plaintiffs, required under the-“working plans” was substantially different from that which had been submitted to them and upon which they made their estimate. If the defendants could establish this, there was no breach of contract on their part, and hence no cause of action in the; plaintiffs; and if this right to abandon their contract was satisfactorily established by a preponderance of evidence, the defendants-were entitled to recover under their counterclaim. Was there a substantial variance ?

This disputed question was submitted to the jury by the learned trial judge, with perfect fairness to the litigants, and with a concise, clear and accurate statement of the law applicable thereto. The jury were at liberty, and under the evidence properly could, render a verdict for either the plaintiffs or defendants. Their ■verdict under the charge, which we have already said was correct-in this respect, depended upon the conclusion that they reached as to the degree of variance. The jury found in favor of the-plaintiffs, and assessed the damages at $800.

But the learned trial judge, in his charge to the question of defendants’ counterclaim, used the following language: “ So far as the defendants’ counterclaim is concerned, it seems to me that when they discovered that these plans were different from what they supposed they were, if they did discover that, that they had what is called in law a locus pcenitentice, place for repentance, had time for repentance; they could either go on with the contract, or go off. They chose to go off; so I think that is about the end of their counterclaim, and the question gets right back to this question of whether the variations were material,” etc. The defendants duly excepted to this portion of the charge, and also to

p. 222
the refusal of the learned judge to submit the counterclaim to the jury.

On the disputed question as to the degree of variance, the learned judge said in his charge to the jury, “If you find that there was a material and substantial difference, one not justified by the usages and customs of the trade, and that the defendants and their subcontractors were in consequence deceived to their injury, induced to take a job and make a bid they never would have taken or given, the defendants had the right to withdraw from their contract, and are entitled to a*verdict in their favor.”

The defendants were entitled in this connection to have their ■counterclaim submitted to the jury for determination. The court should have instructed the jury substantially as follows : That in the event of their reaching the conclusion that there was a substantial variance between the “ working plans ” and the “ elevation, plans,” and, therefore, that the defendants were justified in abandoning their contract, that it would then be their duty to determine the defendants’ right to the counterclaim.

It was error, therefore, on the part of the trial judge to refuse •to submit to the jury the question arising upon the counterclaim, as herein stated. But, in view of the facts established by the verdict, the error is not available to the defendants. The verdict established that there was no substantial variance, and that the defendants were not justified in abandoning their contract. From this it follows that the jury never reached the question relating to the counterclaim; and that even if they had been correctly instructed in respect to it, they would have been bound to "disallow the counterclaim.

The judgment and order appealed from are affirmed, with costs.

Freedman, J., concurs.