Majority
Headnote
^Contract—Alterations—Evidence.There were two building contracts in writing made by Elihu Porter (the contractor and assignor of plaintiff), with the defendant Swan (the owner). One was for the erection of a stable, and the other for the erection of a dwelling. Both were completed, and then taken possession of by defendant. In specifications referred to in each contract, we find this provision, ■“Alterations. It is understood that the owner of the building
The plaintiff brings this action to recover the value of extra-work, or work not included in the contracts, specifications or plans, unless covered by the alteration clause, done by Elihu Porter upon .these buildings at the request of defendant, and for which he expressly promised to pay. On the objection of defendant, all testimony which might show that such work was done,, that deféndant in his conversation requested and employed the-contractor to do this work, expressly promising to pay him for the same, and which might also show defendant to have waived his right to have the value of the work agreed upon in writing,, was excluded, on the ground that it was not in writing in accordance with the specification provision relating to alterations. To-these rulings the plaintiff duly excepted. If it was error to exclude this testimony, then the judgment must be reversed. If this clause deprives the parties thereto of the privilege of mutually agreeing to modify or alter its terms, or of making a new contract in relation to the subject matter thereof, or waiving the requirement that the value of the work shall be reduced to writing, then the rulings cannot be complained of by the plaintiff.. It has always been held that a written agreement could be rescinded or modified by a distinct subsequent oral agreement, provided that such agreement is not invalid under the statute of frauds. 1 Greenleaf on Evidence, 14 ed., §§ 303, 304 and 302.. This clause does not prohibit or enjoin the parties from making a new contract, in whole or in part, in relation to the things contracted about. If they expressly agree to modify the same it is. valid.
It has been frequently held in this state that restrictive clauses, similar to, though not identical with, this one, can be waived expressly or by the acts and conduct of the parties. The common-provision in building contracts, that no payments will be made-without the usual architect’s certificate, is one; the very common-provision in leases that the tenant shall not sublet without the-written permission of the lessor is another. Haden v. Coleman, 73 N. Y., 567 ; Smith v. Alker, 102 id., 87. The very point presented in this case was raised in Stout v. Jones, 9 St. Rep., 570 , general term, fifth department. Therein it was held that a provision in a building contract requiring all orders for extra work to be in writing could be and was actually waived in that case by the acts and conduct of the parties, and ceased to be a prerequisite to a recovery for such.work. This case was affirmed by the court of appeals. 120 N.Y., 638 ; 30 St. Rep., 1017 . This question apparently was: raised in Sutherland v. Morris, 45 Hun, 259 ; 10 St. Rep., 348 , and
For these reasons we are of the opinion that the judgment ought to be reversed, a new trial ordered, with costs to abide the event, and the order of reference vacated.
Clement, Oh. J., concurs.