Majority
Headnote
Mechanics’ lien—Appbopbiation op payments.This action was brought to foreclose a mechanic’s lien against two buildings known as Nos. 128 and 180 West Thirty-first street, in this city, belonging to the defendant Constantine Y. King, who had discharged the lien by giving a bond. King as owner made a contract with the appellant Colleran, whereby Colleran undertook to erect the buildings in question; he sublet the contract for such erection, with the exception of the plumbing work, to Robert H. Andruss; Andruss made sub-contracts with various mechanics, including one for the bluestone with the respondent. After proceeding with the work for some time, Andruss abandoned it before the third payment became due according to the terms of the contract. At that time respondent had done work and furnished materials to the amount of $1,217, as found by the trial judge. It is conceded by all the parties that the respondent before filing his lien had received of the moneys paid to Colleran on this job, by the owner, the sum of $1,114, part of which had been paid by Colleran, the principal contractor, and part by Andruss, the first sub-contractor. Five hundred dollars of the monej's received from Andruss was applied by the respondent (with consent of the former, as it is claimed), upon an old debt due him from Andruss arising on other transactions entirely disconnected with the work in question; there is no evidence however that the principal contractor knew of this appropriation until after Andruss stopped work, and when it came to his knowledge he objected to such appropriation and claimed that it should be applied to the payment for the work done by the respondent upon the buildings in question, as appears by the testimony of the respondent himself. The appellant Colleran in his answer claimed that this $500 was paid on account of the work done by the respondent, and maintained this position on the trial. But the learned trial judge .held that the respondent had the right to apply it as he did, and refused to allow it as a payment upon the contract made by the respondent with Andruss.
This raises a novel question, and that is whether a contractor may appropriate moneys' received under a building contract to the payment of an old debt, or must apply it under the contract under which he does the work.
That he may apply it as was done in this case is supported with much ingenuity by the respondent. It is quite true that until a mechanic files his lien he is only a general creditor of the
This leaves out of view entirely the scheme and object of the .Mechanics’ Lien Act. It has been uniformly held that moneys ■due or to grow due from the owner on a building contract constitute a fund to which the liens of sub-contractors attach when filed in conformity with the statute. To support this, it is only neces.sary to refer to some of the later decisions on that subject. Crane v. Genin, 60 N. Y., 127 ; Payne v. Wilson, supra; Post v. Campbell, 83 N. Y., 282 ; Gibson v. Lenane, 94 id., 183; Larkin v. McMullin, 120 id., 206; 30 St. Rep., 902 .
Most of the cases last cited are also authority for holding that this fund can only be diverted from its object by bona fide payments made by the owner in accordance with the terms of his ■contract. Consequently it has been held that as between the ■owner and one who has furnished labor or materials to the contractor, the owner can plead only damages growing out of the original contract' through the fault or negligence either' o£ the ■contractor or subcontractor, abandonment of the contract, defective work and the like. Cheney v. Troy Hospital Ass’n, 65 N.Y., 282 ; Miller v. Moore, 1 E. D. Smith, 739; Gourdier v. Thorp, id., 698; Develin v. Mack, 2 Daly, 100 .
A general indebtedness cannot be set off as against a mechanic by parties standing between him and the owner; Hagan v. American, etc., Soc., 14 Daly, 131 ; 6 St. Rep., 212 ; Hoyt v. Miner, 7 Hill, 525 ; Develin v. Mack, supra; Bullock v. Horn, 5 Western Rep., 198. In the latter case it was held that where a mechanic who, under the employment of a contractor and with the knowledge of the owner, had performed 'labor upon the construction of .a building, had taken the necessary steps to obtain a lien upon the premises, and brought his action against the owner to recover the amount due and have the samé declared a lien, such ■owner could not be allowed to set off a claim against the contractor not growing out of the contract, acquired by him after the labor was performed, although such claim was acquired before ■notice that the mechanic’s,demand had not been paid. To such .an extent have the courts gone to preserve the fund for the payment of the material men and laborers.
And in Stevens v. Reynolds, 27 St. Rep., 497 , where a material man had filed a lien for material furnished a contractor, and after-wards the contractor gave to another material man who had also furnished material an order on the owner for a sum in excess of that due him for the material furnished, the excess being intended .as payment on another debt,- it was held that the order was good only for the amount actually due for the material furnished upon the work against which it was drawn. This was undoubtedly
But again, the owner is only liable to the contractor and subcontractors for the amount of the contract; he cannot be compelled to pay more. Laws 1885, chap. 342, § 1; Larkin v. McMullin, supra. 'The principal contractor is only bound to pay the aggregate amount of his sub-contracts, according to their terms. Hagan v. Amer., etc., Soc., supra; French v. Bauer, 16 Daly, 309 ; 32 St. Rep., 326 . The intent of the statute with relation to the sub contractor is that he should be subrogated to the rights of the contractor with respect to the funds due or to become due under the-contract. Herbert v. Herbert, 57 How. Pr., 333 ; Schneider v. Ho bein, 41 id., 232; Hofgesang v. Meyer, 2 Abb. N. C., 111 ; Cheney v. Troy Hospital, 65 N.Y., 282 ; McMillan v. Seneca, etc., 5 Hun, 12 .
And the lien of the sub-contractor, in view of- the fact that he i's merely subrogated to the contractor’s rights, attaches only to the moneys due or to become due on the contract with the owner. Crane v. Genin, 60 N. Y., 127 ; Gibson v. Lenane, supra; Post v. Campbell, supra. It is, therefore, clear that in this case Andruss.. even had he completed the work, could not have compelled Colleran to have paid him the $1,114 he had already paid for the plaintiff’s work; and if Andruss could not, it is difficult to see how the plaintiff can.
By the decision of the learned trial judge, however, he has only been credited with a payment of $614, and according to the judgment in this case would be compelled to pay $500 more than the, contract price for the work done by the respondent. This is-manifestly unjust. We, therefore, conclude that the money due-under building contracts cannot be diverted to the payment o£ debts not arising under such contracts.
The erroneous decision of the court below in regard to this, question led it to hold that the respondent was not bound to complete his contract when requested to do so by Colleran until he-had been paid over again for a part of his work, which was also-error.
The judgment should be reversed, and a new trial ordered, with; costs to the appellant' to abide the event
Bischoff and Pryor, JJ., concur.