Majority
Headnote
1. Mechanics’ Liens—Notice—Partial completion oe work—Fact must BE STATED.The defendant and appellant Moses, in 1887 and 1888, was the owner of certain property in West 134th street, on which she erected five houses. The plaintiff and the other defendants were mechanics who did certain work and furnished certain material on those houses. The respondents Verdón and
The plaintiff, Brandt, filed his notice of lien on or about March 9, 1888, which contains the following: “ The nature and amount of the labor and service performed, and the materials furnished, is as follows: That on or about the 10th day of November, 1887, the said William H. Brandt entered into three several contracts with Lizzie M. Moses, to do the slating, tinning and iron work on the premises hereinafter mentioned and described, and said Moses promised and agreed to pay for said work the sum of twelve hundred and fifty dollars. That said William H. Brandt has actually done said work on said premises. That said Moses has paid on account of said contracts the sum of $340, and there still remains due and unpaid the sum of $910."
The complaint in substance alleges the same thing. The referee has found however, that instead of three, there were four separate contracts, which in the aggregate amounted to the sum of $1,250. But the appellant has made no point of this variance, and we do not see that it could have been of any material injury to her. The referee has further found that two of the contracts were partly in writing and partly verbal, and the other two were wholly in paroi. He has also found that seventy-five per cent, of the amount of each contract was to be paid as the work advanced. To these findings the defendant Moses excepted, and on this appeal contends that the referee erred in this respect, especially as to the two contracts which she claims were wholly in writing; but what are called contracts consist of Tetters which are only estimates by the plaintiff as to what certain work would cost, and acceptances by her of those estimates; none of them in any way mention the terms of payment and it is quite probable these were agreed on verbally, as the plaintiff testified. There certainly is not that preponderance of evidence in favor of the appellant which would lead us to reverse the referee’s conclusion on these questions.
The referee has further found that the first, second and fourth contracts were performed, with some trifling exceptions for which proper deductions were made, and that they were not fully performed on account of defendant’s neglect. The evidence as to the performance was very contradictory, but we see no reason for disturbing his findings in respect to these contracts.
The third contract was one by which the plaintiff agreed to put up three bay windows on the houses in question, according to plans submitted to him, for the sum of $490, payable as the others were. From the evidence it appears that the plans for these
This we think must have been known to the plaintiff to have been an evasion, but in the view we take of this case, it is not necessary for us to decide now whether or not a mechanic will be permitted to acquire a lien for work done by him contrary to law, and in order to evade it, for the referee has found the work called for under this contract was not fully completed, but that nearly one-third was left undone. He also fails to find that what was done was done in a good and workmanlike manner, and in his opinion says it was not. He, however, finds that as the plaintiff at all times was ready and willing to complete the contract if the defendant would pay him according to its terms, that he should have a lien for the amount of work actually performed by him, which he found to be $332. This is in conformity with the law. Haden v. Coleman, 73 N. Y., 567 ; Graf v. Cunningham, 109 id., 369; 15 St. Rep., 524 .
This raises the only real questions of law in this branch of the case. As before stated, the plaintiff in his notice of lien claimed he had “actually done said work on said premises,” meaning that he had done all the work required by his contracts, and further claimed that there remained “due and unpaid the sum of $910,’* being the full contract price for all the work. These statements, in view of the referee’s findings, .are evidently untrue; all the work had not been done, and there was due on this contract for all the work done by him under it only $322, instead of $490, the contract price. Under precisely this state of facts the supreme court in Foster v. Schneider, 50 Hun, 151 ; 19 St. Rep., 449 , held that, where the whole of the work had not been performed, it was requisite that the notice of lien should state that fact, and state how much had been performed, and that a failure to conform to the statute in that respect made the filing of the notice invalid, so that it created no lien. This decision was followed by this court in Close v. Clark, 16 Daly, 91 ; 30 St. Rep., 671 ; and the same doctrine was announced in Luscher v. Morris, 18 Abb. N. C., 67 . We consider the rule extremely salutary and useful, in order that all parties_ may be _ apprised of the true state of affairs. In the case first cited, Daniels, J., delivering the opinion of the court, referring to the notices of lien, said: “ They should have stated the extent of the services performed, and of the material used, and of the residue of the work remaining to be performed. * * * „
required this to be done in clear and direct language. And it is one of the directions to be observed by the claimant to insure the creation of the lien for the amount of the indebtedness upon the property benefited by the work and material. * * * It was intended in this manner to exact a truthful statement of the facts to be contained in the notice, and that probably was intended for the benefit of other claimants as well as of the owner of the property and the truthful information of the court,
But this conclusion raises another question, and. that is, whether or not the notice, being inoperative to effect a lien under the third contract, is sufficient to create a lien under the other contracts. As far as we are aware, this question has never been determined. In all the cases before cited, the notices were founded upon single contracts, although in Foster v. Schneider, supra, separate liens were filed upon each house, and the court strongly criticised such a course. In this case, however, there were four separate contracts, and but one notice in which the various contracts were mentioned. It would have been proper to have filed separate notices under each contract; had this been done the notice actually filed would have complied with the statute as to the first, second and fourth, and failed as to the third. Consequently neither the owner nor any of the lienors .could have been misled as to the performance of these contracts; in fact, as found by the referee, it was correct as to them. The plaintiff followed the better practice in filing but one notice for all the liens, and should not fail in three because the .notice was misleading as to a fourth. We think justice and equity will be done by holding the notice good as to the first, second and fourth contracts, and bad as to the third. But, for the error before pointed out, the judgment so far as it affects plaintiff’s claim must be reversed, and a new trial ordered, with costs to the appellant to abide the event, unless the plaintiff within five days elects to reduce the sum awarded him by $332, as of the date of the entry of the judgment, together with any interest which may have been added on so much of the award on the entry of judgment, and if so re
As to that branch of the case which refers to the defendants, Yerdon & Knapp, appellant urged the same defective notice, but this we think was not sustained, for their notice did comply with the statute, in that it stated the nature and amount of the work to be performed and materials to be furnished, and that all of it had been done and furnished except $200 worth, which had not, and contained a detailed statement of what had and had not been done or furnished.
These defendants had the contract for doing, the plumbing and gas fitting in these buildings, and the laying of sewer pipes, etc. One of the principal objections to the work done by them under this contract was in respect to the way they had laid the drain and sewer pipes, and that it was not done in a good and workmanlike manner nor according to the specifications or the contract. The evidence does undoubtedly tend to show that when this work was done it exhibited serious defects, which caused the water to back up and in certain instances to overflow the cellar, or a portion of it. This work was all included under that portion of the contract upon the completion of which the first payment became due, and the referee has found that the defendants performed their work in accordance with the plans and specifications, and that the same was approved by the board of health, and has also found that the work was approved by the architect and a certificate therefor was given to the defendants. It is true that all of these findings are controverted by the defendant-appellant, but we think that the evidence, if not conclusive, was at least sufficient to warrant his findings in; that respect, and we will not disturb them.
The next important objection urged against the work done by the defendants, was the imperfect manner in which the leaders to the houses were put up, and the failure to properly pack the pipes in mineral wool, and in consequence thereof the pipes burst or leaked and damage was done to the building. The evidence tends to show that the packing of the pipes in mineral wool was not required by the defendant Moses, but that she through her agent modified the contract and altered the specifications in such a manner that the defendants, Yerdon & Knapp, could not pack the pipes with mineral wool, and that such non-packing of the pipes was not only consented to by the defendant Moses, but that it was through her own acts and directions given by her agent that the defendants, Yerdon & Knapp, could not pack the pipes in this manner; also that the defendants, Yerdon & Knapp, placed the pipes in position in accordance with the modifications of the contract, and that the bursting and consequent leakage was not caused by any negligent or unskilful workmanship on their part, but in consequence of the unfinished condition of the houses and because they were not properly taken care of by the defendant Moses. The referee has found that all the work was done in a skilful and workmanlike manner, and that the reason for the nonperformance of certain of the work was because the defendant
.The appellant contends that she was justified in not making the second and third payment because of the refusal of the architect to give the proper certificates. But the referee has found, and we think upon sufficient evidence, that the defendant Moses, through her agent, waived the certificate as to these payments; and from the evidence of the architect it seems to us that his objection to the giving of the second certificate was for trifling matters, the performance of which, as before stated, the defendant Moses waived. The non-payment of the second instalment according to the terms of the contract relieved him from going on with the work contemplated under the third payment, and the referee properly found the amount of work which he had actually done under that part of the contract. Haden v. Coleman; Graf v. Cunningham, supra.
We therefore think there is no error in regard to his conclusions as to the claim of Yerdon & Knapp, and that the judgment as to them should be affirmed, with costs to the respondents.
Bischoff and Pryor, JJ., concur.