Majority
Headnote
1. Mechanics’ lien—Building Contract.The plaintiff in this case has recovered a judgment against the defendant for the value of his work and materials in altering and repairing a building, and the amount has been declared to be a lien, under the statute, against the premises on which the building stands. The form of the action was such as is usual in the foreclosure of a mechanics’ lien. The complaint, sets out a contract between the parties, and avers in substance that the plaintiff was prevented or excused from performance by reason of certain acts of the defendant The referee has found that in August, 1888, the plaintiff and defendant entered into a contract, in writing, whereby the plaintiff agreed to perform the labor and furnish the materials in making certain repairs, additions and alterations in and upon a dwelling house on the plaintiff’s premises according to plans and specifications, for the sum of $5,544.50. The plaintiff entered upon the performance of this contract and actually continued to work under it until discharged by the defendant, but the work contemplated was never completed by the plaintiff. The most important question in the case is the proper construction to be given to this contract. By its terms it was to be performed on or before December 1, 1888. It was also provided that in case the architect, who was, by the provisions of the contract, to see to its performance in all details and particulars, should certify to the defendant that the plaintiff had neglected, failed or refused to-perform, that then the defendant might terminate the employment of the contractor and employ others to finish the work and furnish the materials, and in that case the contractor should Hot be entitled to any compensation for what he had done under the contract, except to the extent of any balance of the contract price that might remain after paying for the work and materials expended by the defendant after such termination, and if the cost of completing the work after the owner had elected to terminate the contract should exceed the balance of the contract price remaining in his hands,
On the 7th of January, 1889, the architect named in the contract delivered to the defendant a certificate in which it was stated that the plaintiff had refused, neglected and failed to comply with the terms of the contract, and that sufficient ground existed for terminating the employment of the plaintiff, and for employing other persons to finish the work contemplated by the contract and furnish the materials therefor. On the following day the defendant notified the plaintiff in writing that he had been furnished with such certificate, reciting its contents, and that he elected to terminate plaintiff’s employment under the contract and that he proposed to complete the work himself or cause it to be completed. That the work contemplated by the contract was not ■completed when this notice was served is admitted. But the referee has found that the- failure of the plaintiff to perform the contract within the time stipulated is attributable to the refusal of the defendant to pay the instalments of the contract price when they became due. This proposition is deduced from another finding to the effect, that prior to December 1, 1888, the date when the contract was to be performed, the plaintiff had so far made performance as to entitle him to be paid the first two instalments of the contract price amounting to $2,500 and that he had been paid but $1,500.
That the architect unreasonably refused to make and deliver to the plaintiff a certificate that the amount was due and payable under the contract, and that the defendant unreasonably refused to pay the same to the plaintiff, and that such wrongful action, on the part of the architect and -the defendant, greatly impeded and delayed the plaintiff in the prosecution of the work. These findings so far as they embrace and relate to matters of fact were made by the referee upon evidence which was very conflicting .and, therefore, conclusive upon the court, as it cannot fairly be urged that they are wholly unsupported by proof. But when and in what manner the contract price was payable depends upon the construction of the contract itself and presents a question of law. The contention of the defendant’s counsel is that as there was no time specified in the contract for the payment of the price it was not payable until the work was completed, or not at least until the certificate of the architect was furnished that it was due .and payable. The contract was evidently written upon a printed blank form in use for that purpose, and neither the time when nor the contingency upon which the several instalments became due was distinctly expressed. But between the date of the contract in August and the time for its completion on December 1st the whole price was to be paid in four separate instalments, two of $1,000 each, one of $1,500, one of $1,744.50, and the balance of $300 to be paid on December 1st if the contract was fully completed on that day, “provided that in each case the architect shall certify in writing that all the work upon the performance of which the payment is to become due has been done to his satisfae
The referee held that by the payment clause the parties intended that each payment should become due when such proportion of the work was performed as the particular instalment bore to the-whole contract price. The $1,500 paid on the contract by the defendant seems to have been certified by the architect and paid upon this principle. Both parties understood that the plaintiff would, as the work progressed, require money to pay laborers and mechanics and to purchase materials and it was for ■ this reason that the contract price was made payable in sums as the progress of the work might demand on the one hand and justify on the other. The construction which the referee put upon this provision of the contract is just and reasonable and in accordance with what the parties themselves must have intended. White v. Hoyt, 73 N. Y., 505 ; Halpin v. Ins. Co. of N. A., 120 id., 73; 30 St. Rep., 261 ; Tallcot v. Arnold, 61 N. Y., 616 ; Barlow v. Scott, 24 id., 40. It follows that the defendant did not perform his part of the contract and was not in a position to terminate the contract by the discharge of the plaintiff. If, as the referee has found, performance by tbe plaintiff was prevented by the default of the defendant in making the payment according to the terms and meaning of the contract, then the failure of the plaintiff to have the work completed at the time named in the contract is excused. Kingsley v. The City of Brooklyn, 78 N. Y., 200 . When the employer under such circumstances terminates the contract and arrests its-performance the contractor may recover, in a proper action, th& value of the work performed and the materials furnished. Clark v. The Mayor, 4 N. Y., 338 ; Jones v. Judd, id., 412-414 ; Dillon v. Anderson, 43 id., 237; Lawson v. Hogan, 93 id., 39.
Whether the refusal of the architect to give the plaintiff the certificate, upon which by the terms of the contract the payments-were to be made from time to time as the work progressed, was- or was not unreasonable, became in this case a question of fact, depending upon the amount of work done, and the finding concludes us on that question. The contract having been waived by the plaintiff and a recovery sought upon a quantum meruit, the question of the value of the work done and materials furnished, must, in this court, be deemed settled by the findings of the referee upon conflicting evidence.
This conversation between the plaintiff and the architect was wholly immaterial as it was not claimed that the contract was modified or extended but that the failure to perform was chargeable to the defendant. It could have no effect whatever upon the result. The recovery was for the value of the plaintiff’s services, and he took nothing and could not possibly take anything by any arrangement between himself and the architect as to different periods of payment from that prescribed in the contract.
The referee permitted the plaintiff, after his case was closed and after the defendant had rested, to reopen the case and to give testimony in chief, and various objections were made and exceptions taken on this ground. That was- a matter wholly in the discretion of the referee and is not the subject of review Gere. Many of the exceptions referred to related to the value, quality and actual expense of the work on the building by persons employed. by the
On the whole we are of the opinion that the record does not disclose any error that requires, or would justify a reversal of the decision of this referee. The judgment should be affirmed, with costa
All concur.