Majority
Headnote
Contract—Substantial performance.The acceptance of the order given by the Wadsworths to the plaintiffs upon the defendant was in terms conditional and payment made dependent upon completion of the building and on the architect’s certificate. And by the contract such certificate was made a condition precedent to the right to any payments upon the work. No such certificate was obtained by the Wadsworths or the plaintiffs in support of the demand for payment of the amount of the order or any portion of it, but upon application made to him November 29, 1887, by one of the plaintiffs for a final certificate on the work the architect put his refusal in writing of that date as follows:
“ Mr. F. P. Crouch : Replying to your request for final certificate on the Gutman contract. I regret that there are so many things which are imperfect that I am prevented from certifying to the satisfactory completion of the work under the contract
“James G. Cutler, Architect."
The parties to the contract by it made the architect’s certificate ■essential evidence of performance and of the right to payment founded upon it, and unless its production was in some manner waived or its necessity otherwise overcome or obviated, the failure to obtain it constituted a bar to recovery by the plaintiffs. Smith v. Brady, 17 N. Y., 173 . In support of his conclusion the referee found that the contractor Strauchensubstantially performed the work on his part, and that on his adjustment with the defendant there was deducted $199.55 for defective mason work, and $1,300 for delay from April 1 to August 8, 1887, in completing the work. And that the Wadsworths substantially performed the agreement on their part, though in some particulars their work was not first class, but there was no willful or intentional departure on their part from the terms of the contract; and that such
In the present case the defective condition of- the carpenter-work from all causes as described by the findings of the referee were, that the walls of the building settled to some extent, thereby affecting the carpentry work; that the base boards in many cases-parted from the floor; that such shrinkage of the boards was without the fault of the Wadsworths or the material furnished, but. was due to the settling of .the walls and partially to the steam heat; that the materials furnished by them were according to the terms of the contract, except that of the shelving in closets and the maple flooring for the halls, part of which was second-class-material. These facts have some evidence for their support.
The referee further found upon the subject of defects in the carpenter work, that when the Wadsworths stopped work in the latter part of July, 1887, there were defects in their work in the-following respects: “In the bath rooms, in the hardwood floors, pieced casings on windows in rear of building, defective hand rail on front stairs, moulding in some portions of the building not properly smoothed before oiling, imperfect painting on the front-of the building.”
And further, that on the defendant’s three days notice provided by the contract, and given on July 30, 1887, to the contractor to-provide materials and workmen and complete the work, the de
The referee then proceeded by his findings to state that the defective work covered by the specifications and not remedied by Pike consisted of “maple flooring in the halls, in which some cases second class material was used, and the floors themselves in some cases present an uneven surface caused by settling of the building. The window frames in rooms in the rear of the building were not set to correspond in height with the doors in said rear rooms, and the hand rail on front stairs was patched, and there was defective work in the bath rooms, window casings and closet shelves, but the said defects do not prevent the use of the building for the purposes intended.” And that the fair value of the labor and materials necessary to remedy such defective work not remedied by Pike and his painter, was $205. He also found that the Wadsworths failed to provide iron transom guards for rear doors and iron registers for front, for which deduction of $12 should be made. And he added that when Pike had completed his work before mentioned, and on or about September 21, 1887, the defendant took and has since remained in possession of the building, and has rented portions of it to tenants. Although there is a conflict in the evidence in respect to some of such findings, there is in the record some evidence tending to support all of them, and for the purposes of this review they must therefore be deemed conclusive of the facts so found by him.
While the condition of the carpenter work when the Wadsworths left it in July was such as to, indicate defects and omissions, the correction of which would cost $656.29, it may be observed that such defects upon such estimate of the cost to the amount of $439.29 were remedied through the action of the ■defendant, taken pursuant to his right reserved by the contract, to furnish materials and workmen to proceed with the work and charge the expense to the contractor, upon the failure of the latter to do it on three days notice to him to that effect. This work having been done by the defendant in the exercise, by his election, of such right, he cannot effectually assert forfeiture in respect to the deficiency so supplied, but the Wadsworths were entitled to the benefit of the work thus produced and were chargeable to the defendant for the amount of the expense incurred by him in doing it. Murphy v. Buchman, 66 N. Y., 297 . When the application for the architect's certificate was made this work had been done and the defect in the work to that extent removed, and
The amount of damages for want of strict performance was not such as to necessarily defeat the claim of substantial performance. Phillip v. Gallant, 62 N. Y., 256 . The cost of completion of work by remedying defects or -supplying omissions in it to meet the requirement of a contract may be so great as to preclude the conclusion of substantial performance.
In Flaherty v. Miner, 123 N. Y., 382 ; 33 St. Rep., 681 , where the damages allowed were upwards of seventeen per cent of the contract price, the court suggested, without deciding, that if it had appeared “ without dispute that such a substantial portion of the-work remained undone and objection had been properly taken, it may well be that the plaintiff could not have recovered upon the theory of a substantial performance.” It is suggested that it was not within the province of the architect’s duty to make deductions for defective work or' to determine what less than exact or full completion of the work, according to the contract, was such substantial performance as to permit recovery. That may be true in such sense that the refusal of a certificate may on his part have-been without purpose to deny to the contractor that which he may have been entitled, and yet it may be determined on trial that the certificate was unreasonably withheld. The considerations of good faith on the part of the contractor bearing upon the question whether the defective work was willful or unintentional and inadvertent the architect may not be willing to determine. But if he gives a certificate founded upon final estimate that the work is substantially performed, the right to abate recovery for defects in the work is not necessarily defeated.
In Phillip v. Gallant, 62 N. Y., 257 , where the contract price of the work was $865.11, a&d the damages allowed for defective work was $75, the question of substantial performance was held to be one of fact, and the amount of damages was not treated as-inconsistent with the conclusion to that effect. And see Van Clief v. Van Vechten, 42 St. Rep., 736 .
The rule of substantial performance should riot be extended beyond the purpose in view when the relaxation of the strict performance was adopted, which was founded upon equitable considerations in furtherance of justice, and made applicable to cases of honest intention of contractors to fairly perform their contracts, and who shall in the main have done so, with only slight defects or omissions inadvertently and unintentionally caused and appearing in tlje work. The present is a case not free from difficulty in that respect. Nót less so in the extent of the deficiencies than in the character of some
The work which the defendant, following the three days notice before mentioned, caused to be performed, was not completed until about the 21st of September, 1887, when he took possession of the building. Thus intervened a period of upwards of forty days after the time up to which the matter of delay had been adjusted with the original contractor. The referee has found that the sub-contractors were delayed in the work two or three weeks by a strike of workmen, four or five days waiting the decision of the defendant in respect to certain specified work, and that they
Dissent
There were some other matters made the subject of controversy, and to which the defendant’s exceptions call attention, but upon careful examination of the record it is found that none of the find-' ings or refusals to find of the referee are wholly unsupported by evidence. None of the exceptions seem to have been well taken.
The judgment should be affirmed.
(dissenting)—The prevailing opinion goes further than any previous judgment has gone in the direction of holding that the question of “ substantial performance ” is always one of fact. Generally the question is one of fact, but so called performance may be so partial or defective that it is the-duty of •the court to decide, as a matter of law, that the contract has not been so far performed as to entitle the plaintiff to recover upon it. In my opinion, the defective performance found by the referee is sufficient to defeat a recovery on this contract, and besides, the undisputed evidence does not tend to support the finding or conclusion of substantial performance.
The tendency, called equitable, of courts to relieve persons from .the performance of engagements deliberately entered into, and in legal effect to make for litigants new contracts which they never entered into, and which it cannot be supposed they ever would have entered into, has been, and is being carried to a length which cannot be justified in reason. I think the judgment should be reversed and a new trial granted, with costs to abide the event
Judgment affirmed, with costs.
All concur, except Follett, Ch. J., Vann and Landon, JJ., ■dissenting.