Majority
Headnote
1. Contract—Performance.action was on a building contract to recover a balance of the contract price of building two barns, and the value oLcertain extra work and materials done and furnished by the contractors. The defendant by her answer denied that the contract had been performed according to its terms, and set up a counterclaim of damages for its non-performance. Among other ■deviations from the plans and specifications upon which the contract was based, it was conceded that the “ collar beams ” which ■should have joined together the tops of the two “ purloin posts ” in each bent of the grain barn were omitted from the structure, and that nothing was substituted in their place. The plaintiff's contended that the omission was with the consent of the defendant, which she denied, and to that question a considerable portion of the evidence in the case was addressed. The referee makes no specific finding on this question, but his conclusion of fact as to the amount of damages sustained by the defendant by reason of defects of construction shows plainly that he decided that the defendant had not consented to or waived the defect in ■question. And so he says in his opinion, which may be referred to for the purpose of explaining how he arrived at-the conclusions •of his rather meagre report. There he speaks of these collar
The contract price .of the work, completed, was $2,500, of which the defendant had paid $1,500 during its progress. The referee finds that the plaintiffs left the work not entirely finished, and that the defendant completed it at an expense of $126.06, and he finds : “ That at the time the plaintiffs quit work on said buildings the same were worth, by reason of defects in the construction thereof, $750 less than if constructed, in the manner required by the contract and the plans and specifications which were a part thereof, besides the amount expended by the defendant in the completion of said buildings.” And yet the report, contains a formal finding under the designation of findings of fact, to the effect that the plaintiffs constructed the buildings “ substantially in accordance " with the contract and specifications, and as a sole conclusion of law that the plaintiffs are entitled to recover the balance of the contract price and “ extras,” after deducting the damages for defective construction and the sum paid by the defendant for the completion of the buildings.
We are of the opinion that the two findings (1) of the defective-construction of the buildings and the damage occasioned to the defendant thereby, and (2) that they were constructed in substantial accordance with the contract and specifications, do not stand together, and that the two taken together do not support the conclusion of law that the plaintiffs are entitled to recover on the contract.
The entire contract price was $2,500, while the allowance to the defendant for defective construction, in violation of the contract, with the value of the work in completing the buildings left undone by the plaintiffs, amount to the sum of $876, or more than one-third of the entire contract price. So far from being substantially in accordance with the contract, this work seems to have been substantially in violation of the contract, and there is no' rule of law which permits such defects and failures of performance to be disregarded in determining whether a contract has been substantially performed. So we said, in substance, in Oberlies v. Bulinger, 33 St. Rep., 443 , and the failure of performance in that case was certainly not more substantial than in this. The cases there cited, of Smith v. Brady, 17 N. Y., 173 , and Glacius v. Black, 50 id., 145, fully sustain the conclusions in that case, as
The objection is suggested, that the finding of substantial performance is a finding of fact and not subject to exception. That-finding, though coming under the heading of conclusions of fact, is manifestly a mixed conclusion of fact and law. In the case of Glacius v. Black, 67 N. Y., 563 , it was held that the question whether a defect, not more radical or material than that disclosed in this case, constituted a breach of the contract, was not a question for the jury but a question of law for the court. But even if an exception did not lie to the finding denominated one of fact, the exception to the conclusion of law is sufficient to raise the question whether that conclusion is supported by the findings of fact; and, as already intimated, we are of opinion that the two findings of fact are inconsistent with each other, and that together they do not support the conclusion of law.
The judgment appealed from should be reversed, and a new trial granted.
Judgment reversed and a new trial granted, with costs to abide the event.
Macomber and Lewis, JJ., concur.