Majority
Headnote
1. Stipulation—Force of—Condemnation proceedings.Prior to 1889, the property owner whose property, or some portion thereof, is involved in this proceeding, brought an action against the company to restrain it from the further operation of its road in the street in front of the property of such owner, on the ground that it was so operating its road
“SUPREME COURT—County of New Yore. ■“American Bank Note Company against The Metropolitan Elevated Railway Company and the Manhattan Railway Company.
“ Stipulation.
“As a condition of obtaining the stay of the injunction contained in the judgment herein, imposed upon these defendants by an order entered herein on the 8th day of October, 1890, and solely under compulsion of the said order, the defendants above named, and each of them, hereby stipulate that they or either of them will not institute or prosecute any proceedings to condemn the property described in the complaint herein, pending the stay granted by this order ; and that they, and each of them, will contest the plaintiff’s rights only in this action; and that they will prepare a case on appeal at once.
“DatedNew York, October 15, 1890.
“ Davies & Rapadlo,
“ Aitys. for Defts.,
“ 82 Nassau street,
“ N. Y. City.”
Upon signing the stipulation the issuing of the injunction pending the appeal was stayed.,
The judgment upon the appeal was reversed. Subsequent to the reversal the railway company noticed a motion in the condemnation proceedings for the appointment of commissioners in accordance with the amended petition verified in June, 1890. That motion was opposed bv the property owner and denied by
The order denying the application, after reciting the reading of the petitioner’s amended petition and the affidavit of the attorney for the property owner, continues : “And on reading the stipulation signed by the defendants, stipulating to contest the plaintiff’s rights only in the action brought by the plaintiff, and after liearying A. S. Lyman, Esq., of counsel for the petitioner, and William G. Peckham, Esq., of counsel for the property owner, Ordered, that the petitioner’s motion be and the same is hereby denied, with $10 costs.” This order was affirmed in all respects by the general term, and from the order of affirmance the railway company has appealed to this court.
We think the contention of the counsel for the respondent that the order is not appealable cannot be maintained. It is not of that character which the statute makes final and conclusive with the general term of the supreme court. The order which is not appealable to this court relates to the assessment of damages for the taking of the land and everything that could be litigated before and passed upon by the commissioners. All orders which are discretionary with the courts below are also not appealable, unless in cases of abuse of such discretion.
Here the question in this case and upon the record as made up is really one of law as to the proper construction of the stipulation. Upon that question, we think, the courts below have erred. The railway company by that stipulation, for the purpose of obtaining a stay of proceedings upon the judgment awarding an injunction, which would enjoin them from the further operation of their road, agree not to institute or prosecute proceedings to condemn the property pending the stay granted by the order, and that they will contest the plaintiff’s right only in the action. It seems to us that the phrase “ pending the stay granted by the order ” is to be applied to the whole agreement, so that it shall limit the right of the railway company to institute or prosecute proceedings to condemn only pending the stay, and when the stay becomes useless and functus officio by the reversal of the judgment which awarded the injunction, the railway company is, by the proper construction of the agreement, free to act as it was before the judgment for an injunction was obtained or the stipulation entered into. The contrary construction, we think, is not warranted by the terms of the stipulation.
If the railway company do not proceed with proper diligence in the condemnation proceedings, the property owner is not hi the least harmed. It is always at liberty to bring its own action to trial again, and can therein obtain all the relief necessary, or to which it may be entitled. The question is a narrow one, involv
The orders of the general and special terms must be reversed and the motion remitted to the special term for the action of that court under this view of the meaning of the stipulation, with costs to the railway company in all courts.
All concur.