Majority
Headnote
1. Contbact — Breach — Abandonment—Damages—Prospective Profits.There was some controversy on the trial in respect to the quantity of work performed under the contract.
The accuracy of the estimates presented by the evidence of the respective parties, was the subject of fair criticism. Those furnished on the part of the plaintiff were made without measurements, and those on the part of the defendants were estimates aided by partial measurements only. Thus was presented
There is not a very clearly defined division of the work into that done before and that done after the 25th of July, 1882, but there is some evidence on the subject which enabled the referee to make the severance, and to support his conclusion in that respect. The defendants allege the abandonment by the plaintiff of the work which he undertook to perform under the contract, and that a large number of persons gave notice to the railway company of their claims for labor done, and filed liens against the company for materials furnished and used in the work of construction under the contract in question; that the defendants paid such claims, amounting to $6,940.10, and took assignments. They sought to charge the amount so paid against the plaintiff as counter-claims. The referee did not allow to the defendants the sums so paid, but found that the plaintiff sub-let the work of construction except the trestle-bridge, and the pile bridge work, to Moore and Sullivan, who entered upon the performance of the work; that in the latter part of July the laborers on the work became clamorous for their pay, and insubordinately refusing to work unless paid, and that they did quit on or before July 29th; that Moore and Sullivan with plaintiff’s assent on that day requested the defendants to pay the men or to furnish the money for that purpose, and proposed to give the defendants security that the money should be paid to the laborers in case they furnished it, which the defendants refused to do, after which the plaintiff made the demand that payment should be made to him; that on July 29th, and during several following days, the defendants procured a large number of the laborers to make and file their claims for unpaid services
But the work being done pursuant to a contract originally made with the railroad company, it and its property could be charged on default of the contractors, or sub-contractors, to p>ay the laborers, etc. Laws of 1850, ch. 140, § 12, as amended by Laws of 1871, ch. 669, § 2; Laws 1872, ch. 895; Laws 1870, ch. 529. And in the event the company should be required to pay such claims, it might require reimbursement from the party with whom it had contracted to do the work out of which they arose. As a consequence the party taking such contract would have an interest in seeing to it that such claims were paid by his immediate, or any subsequent contractor. And the obligation is implied, if not expressed, that each suceeding contractor will protect the party from whom he takes such relation by contract to perform the work or any part of it embraced in the original contract with the company, against such claims and liabilities by him incurred.
The defendants seemed to have been apprehensive that the money might not-be applied in payment of the claims of the character before mentioned, and therefore required assurance that it should be so appropriated. The plaintiff was unwilling to give a receipt for the money• containing sucha condition.
And the referee has found that Moore and Sullivan, with plaintiff’s assent, requested the defendants to pay the men or to furnish the money for such purpose.
By making such payment with the assent of the plaintiff and Moore and Sullivan, the liability to them to that extent of the plaintiff would be discharged, and the payment would be deemed made by the defendants for the plaintiff. And in that view there might be no difficulty in charging the latter with the amonnt if the defendants had not taken assignments of the claims for which they advanced the money to pay. By reason of taking such assignments it is contended that Moore and Sullivan remain liable to the defendants upon the claims, and therefore they cannot be asserted in this action against the plain iff. Treating the primary liability as that of Moore and Sullivan, only, to the men, that is so, unless the peculiar situation and relation of the parties and the right of the claimants to charge the company, and that of the latter to seek reimbursement from the defendants, may be considered and given effect to afford the relief sought by them here. The proceeding attending the act of payment, of having notices served upon the engineer of the company under the statute, and taking assignments, was evidently taken as a matter of precaution, so that the payments might be deemed as made to discharge the company and its property from a liability to pay, and thus protect themselves from liability to it. And while the apparent effect of the assignments was to vest in the defendants the title to the claim as against the parties primarily and personally liable to pay, the purpose evidently was to take such title only as a means of making more effectual their purpose to apply the money so advanced upon the amount of compensation which they, by their contract, had agreed to pay the plaintiff for the work of construction of the railroad, and not with any view to create a liability of any other party to them for the .amount so paid. They in this way have done and probably did do more than was necessary to put themselves in a position to charge the plaintiff with the payment so made, although the question of voluntary payment otherwise may have been raised. Senear v. Woods, 74 N. Y., 615 . The question presented here is not without some difficulty, but we think these payments should and may be allowed to the defendants in this action No. 1. Proceedings were taken to charge the company, and it is not important what the
The defendants had no right to maintain any action against the company on account of such claims. As between it and them the primary liability was with the defendants, and as to the company,' the workmen were deemed paid by tMs act of the defendants in any view that could be taken of the assignments. TMs action is brought upon the contract between the plaintiff and defendants to recover for tMs work, and as between them it was deemed done by the plaintiff in performance of such contract. It was on account of tMs work that such payments were made. And they were made with the consent of Moore and Sullivan, who were M some manner acting through or under the plamtiff in the performance of the contract between the latter and the defendants. We think the amount of these payments so made by the defendants, properly should, and can be, allowed to the defendants by way of abatement of the plaintiff’s recovery. The evidence about fares, etc., of the men, said to have been paid by Moore and Sullivan, is somewhat indefinite. NotMng appeared on the pay-rolls in that respect.
They say they informed the defendants’ agent that deduction should be made on that account from the moneys earned by the laborers, which he denies. Moore and Sullivan knowrng that the defendants were proceedmg to pay the men, and consenting to it, gave no information to enable them to make such deduction or to attempt to do it. And it does not appear that
But in action No. 2, such abandonment, its cause and effect have some importance. The referee finds, and it is assumed here that the defendants refused to pay to the plaintiff on the first day of August, 1882, the sum he was then entitled to demand :and receive for work done up to July 25th, and that on or about the 12th day of August the plaintiff abandoned the work for the reason that the defendants refused to pay the amount due on the first of that month. The important question arising upon this state of facts is, whether the plaintiff in consequence of this breach of the contract was entitled to recover by way of damages prospective profits, or such profits as would result to him from a complete performance of the contract. The referee found that by this refusal to pay the plaintiff, he was deprived of •“ the means to pay off his laborers and procure their continu
The more serious inquiry remains, and is, whether in any view which may be taken of the evideuce, the plaintiff was permitted to recover as damages the prospective profits which the completion of performance by him of his contract would have given him. The right- to such relief does not arise out of every breach
The cause which permits the recovery of such damages rests upon a rule of law, having some degree of certainty, and is founded in the fact that the one party is prevented by the act of the other from realizing the benefit which the contract furnishes. And he is therefore entitled to recover the value of the stipulation or covenant he has taken of hint who defeats such right. Such value is the amount of profits to result from performance. An agreement to make payment is generally an essential one, and the consequences of default in payment, may, in fact, be more or less prejudicial according to circumstances, but in legal contemplation they are the same. The pecuniary condition and responsibility of the parties have no bearing upon this question. The rights at law flowing from or produced by a breach of contract, .arise at once from it, and will support an action. If default in payment alone would afford a remedy as for exclusion from further performance the right of action and of recovery of the entire value of the contract would immediately follow failure to pay, although it arose from mere temporary want of readiness to make payment.
In this case the legal right of the plaintiff to proceed in the
There is no finding on that subject in this action No. 2, to that effect. And in view of the evidence there is no occasion here for considering that question as bearing upon the proposition now under consideration. The men became insubordinate and quit work, because they did not receive their pay as promptly as they desired, and this was probably occasioned by the default of the defendants, and may be attributable to a breach by them in that respect of the contract, and as one of its consequences, as it is likely that the plaintiff was not, nor were Moore and Sullivan, prepared to pay them without receiving the funds from the defendants, but the latter early offered to furnish the money for that purpose upon the condition that it should be used to pay the men. We do not regard this as important upon the question here in its legal aspect.
The views taken of this case lead to the conclusion that the plaintiff was justified by the breach on the part of the defendant in abandoning the further performance of the contract and entitled to recover for the work done; but the breach not being such as to deny to him the right and power to go forward with the work and perform, he could not recover as damages the value of his contract or (what may be understood to mean the same thing) prospective profits.
There is nothing in the terms of the contract characterizing the consequence of default in payment of an installment other than such as may be implied by law. In view of the finding by the referee of the quantity of work done under the contract, it amounted to.$22,76 48
The recovery in Action No. 1, $12,824, and payment, $5,000 . 17,854 00
The balance unpaid is.$4,907 43
This result is reached by giving to the plaintiff the benefit of the payments provided by the contract to be made on the final estimate of the work, when completed, in stock, for which the breach of the contract as found by the referee permits the allowance, to the extent of the work performed. Pinney v. Gleason, 5 Wendell, 393. This computation makes the amount awarded by the referee as damages, $11,080.94.
If these views are correct the judgment in action No. 1, should be reversed and a new trial granted. Costs to abide the event, unless the plaintiff stipulate to deduct from the amount of the recovery, $6,940.10, and interest thereon from August 5th, 1882,
And in Action No. 2, the judgment should be reversed and a new trial granted, costs to abide the event unless the plaintiff stipulate to deduct from the amount of the recovery, $11,080.94, and interest thereon from August 17th, 1882. And in that case the judgment be so modified, and as modified, affirmed without costs of this appeal to either party.
Smith, P. J., Barker and Haight, J. J., concur.