Majority
Headnote
1. Guaranty — Consideration.This action was brought in the municipal court to recover against the defendant for a bill of lumber furnished to one Abraham Walty on a guaranty of payment. It appears that on the 23d day of July, 1891, William G. Newbrook, son of defendant George Newbrook, contracted with Abraham Walty to build him a house according to certain plans and specifications contained in a contract, the work and material to be furnished by
The accepted orders were $65 for hardware and two liens for $53.58 and $75.20, respectively. Then after completing the house for $275, he paid the plaintiffs $40.98 on their bill, which made the amount of the contract price, namely, $1,450. It is not stated anywhere in the case that the thousand and eighty dollars and sixty cents paid to Walty includes the two payments to the plaintiff, but it probably does include the $300 paid them, as they received that amount before the date of his abandoning the contract, although they claim to have received it in checks from Mr. Newbrook. On his cross-examination the witness was asked by the defendant’s counsel: “ Leaving the liens out of the question, how much money has been paid out, first and last, on that house, all of it?” and the answer was, “ $1,450.” This is exclusive of the two liens, which amount to $128.83.
The validity of the liens and the amount unpaid to Walty, in the view which I have taken of this case, cannot be of much importance. The liens can only be enforced to the extent of any unpaid balance due the contractor, and it is apparent that at the time of filing the liens the contractor had been overpaid. It thus appears that William G. Newbrook has paid the whole contract price for building his house, leaving the $119.02 of the plaintiffs’ claim unpaid. But I do not think the question is to be determined either from the fact that the contract price has been paid or of the failure of Walty to complete the work according to the terms of his contract. It is claimed that the guaranty was without consideration, and cannot be enforced against the defendant I think the delivery of the lumber was a sufficient
Concurrence
According to the contract of guaranty the defendant agreed to see the amount of the bill paid according to the terms of the contract, and it is necessary to examine the contract to determine how the payments were to be made. It appears that $500 was to be paid when the work was one-third completed, and $500 more when two-thirds of the work was done, and $450 was to be retained by New brook until the work was finally completed, so that when the house was completed the whole amount became due. It is claimed that because the contractor, Walty, did not complete the work, but abandoned the same, and Newbrook was obliged to complete it, that there was no compliance with the terms of the contract, and hence nothing became due on the last payment I do not think such a construction of the contract of guaranty is either just or tenable. The plaintiffs were not a party to the contract with Walty. It was no concern of theirs that the work was not well or completely done, and a failure of a contractor to carry out his contract cannot operate to deprive the plaintiffs of their remedy on the guaranty. We resort to the contract only to determine or to ascertain the terms of payment, and they are to be construed as a part of the guaranty for that purpose. It does not create a condition precedent to the right of the plaintiff to maintain the action against the surety. It simply fixes the terms of payment and the time within which it is to be made, so that when the work was done, no matter who completes it, the surety becomes liable. Any other construction would put it in the power of the contracting parties to defeat any person who might furnish material relying upon a guaranty for payment Evidently the defendant was interested in giving the contractor Walty credit with the plaintiffs, that, he might go on and build the house for his son.
The lumber was furnished by the plaintiffs, relying upon the assurance expressed in the writing of the defendant, that Walty would pay, or, in default thereof, that he would pay the amount of their bill. The contract of guaranty, construed with the undertaking of Walty, is a complete and perfect contract, fulfilling all the essential requirements of the cases cited by the counsel for the defendant. Since the amendment to the Revised Statutes in 1863, it is not necessary to express a consideration in the instrument guaranteeing against the default of another, and the cases cited upon that question are not in point here.
The judgment should, therefore, be reversed, with costs.
I concur in the result reached by Titus, Oh. J., upon the ground that the guaranty, in this case, is to be construed