Majority
Headnote
1. Contract—Conditions—Arbitrary withholding of certificate.This action was brought against the defendant to recover upon two causes of action; the first being for the sum of $1,400, which the plaintiff claims the defendant agreed to pay for equipping his factory at Astoria, Long Island,' with its dry pipe system of automatic sprinklers, under the terms of a contract between the parties dated September 19,
The plaintiff itself having made the condition precedent that the money for the contract work should not be payable until after a certificate of approval had been issued by the New York Board of Fire Underwriters, was bound by it, and could not maintain the action as to that, unless it were arbitrarily or unreasonably refused by the board, but if arbitrarily and unreasonably refused then it could recover notwithstanding such refusal. Highton v. Dessau, 19 N. Y. Supp., 395 ; 46 St. Rep., 922 ; Thomas v. Fleury, 26 N. Y., 33 : Bowery N. Bk. v. Mayor, 63 id., 339; Nolan v. Whitney, 88 id., 650 ; Smith v. Alker, 102 id., 90; Doll v. Noble, 116 id., 232; 26 St. Rep., 629 ; Flaherty v. Miner, 33 id., 681 ; Thomas v. Stewart, 132 N. Y., 580 ; 43 St. Rep., 881 ; Crouch v. Gutmann, 134 N. Y., 45 ; 45 St. Rep., 470 .
In contemplation of the contract the certificate ought to have been given when it was fully completed, provided there was no valid reason for the board of underwriters refusing the same. The fact that the pump was not of adequate capacity and that there was no guarantee that steam would be maintained at all times to work it, were conditions over which the plaintiff had no control, and were fully within the control of the defendant, and, therefore, the refusal of the certificate on that ground would not have shielded the defendant from payment, because he could not take
In order to show that the withholding of the certificate' upon the ground last named was arbitrary and unreasonable, the plaintiff asked the following question of Mr. Yan Giesen: “Were those premises in Astoria beyond the reach of a fully organized fire department ? ” which was objected to by the defendant, and the objection sustained. He was also asked the question if the premises which were located in Astoria had been located in the Metropolitan district of the board of fire underwriters, what would have been the use of that certificate, which was also objected to by the defendant, and the objection sustained. To both of these rulings the plaintiff duly excepted. We think under the peculiar circumstances of this case these questions should have' been allowed, as it was essential to the plaintiff to prove the withholding of the certificate, upon the ground that it was beyond the reach of a fully organized paid fire department, was arbitrary, and the questions tended directly to prove that, or at least to prove circumstances from which it could be inferred.
We also think that the evidence of extra work done, and the authority for doing it, was sufficiently established to require the submission of that question of fact to the jury, and it was error to dismiss the complaint as to it.
The judgment should, therefore, be reversed, and a new trial ordered, with costs to the appellant to abide the event.
Bischoff and Pryor, JJ., concur.