Majority
Headnote
1. Contract—Breach—Prospective profits.Defendant was the contractor for the construction of a street railway in Lincoln, Nebraska, and entered into an-agreement with plaintiff by the terms of which the latter was to furnish the materials and labor for the entire construction of the railway tracks in consideration of the sum of $56,000, to be paid by the defendant as follows: $5,000 within five days after the execution of the agreement; the market value with the freight added of the materials needed for the construction of the tracks-whenever and as soon as delivered in Lincoln; $11,200 when a half mile of double track shall have been laid, less the amount previously paid for materials used in its construction, and similar payments for each half mile of double track laid. The $5,000 first paid was to be deducted from the last payment due. The plaintiff began the construction of the tracks, and at the request of the defendant prepared to first lay down a single track for the whole distance of two and one-half miles, instead of constructing
Neither cash nor securities were forthcoming, and on Nov. 23 plaintiff telegraphed defendant that its men were idle at Lincoln and it should order them home in forty-eight hours. The defendant replied, proposing other security, and urging plaintiff to lay a half mile more before December 1st. Plaintiff telegraphed requesting defendant to come over the next day and bring the proposed security, and that probably they could arrange matters. Defendant replied that he would be there, but did not come. December 2d plaintiff wrote defendant, formally notifying him that his failure to comply with the terms of the contract had been the cause and was still the cause of considerable loss; that there were constantly daily expenses accruing for men, interest on materials, etc., which it would look to him to make good, and further notifying him that in view of the breach of the contract on the part of the defendant the plaintiff does not consider itself further bound thereby. The defendant replied the next day that he had telegrams and letters from plaintiff stating that it should withdraw its men from Lincoln on a specified date, and that if it had not done so the delay was upon its own responsibility. After this there was some correspondence with reference to the substitution of other parties in place of the defendant, but the plaintiff stated that the negotiations were favored with the full understanding that the defendant, by his own acts of omission to make payments as agreed upon, had already canceled the contract, provided the plaintiff chose to have it canceled. These
In view of the structure of this contract it would seem to be clear that the mere failure of the defendant to make punctual payment of an instalment due according to its provisions was not such a breach of the entire contract as to permit the plaintiff to refuse to proceed further under it, and recover damages for the profits which he would have earned had the contract been fully performed on his part.
In the able and elaborate brief submitted by the learned counsel for the appellant our attention has not been called to any case where the contrary of this proposition has been maintained. While the question does not seem to have been the subject of frequent discussion in this state, authority is not wanting to support this view.
In Moore v. Taylor, 42 Hun, 45 ; 5 St. Rep., 202 , the plaintiff sought to recover prospective profits upon the failure to pay an instalment under a contract for railroad construction similar in its important features to the one before us, and it was held by the general term of thefifth department, Judge Bradley delivering the opinion of the court, that mere default in the payment of an instalment when it becomes due is not such a denial of the right of the contractor to continue in the performance of the service as in legal effect to constitute a breach of the entire contract. Such a failure is not of itself equivalent to a refusal on the part of the defendant to be fur
The plaintiff did request that the jury might be permitted to determine whether the defendant had not abandoned the contract in its entirety ; but before that question could be reached the court was required to decide whether there had not been a rescission and abandonment of the contract by the plaintiff, and having determined that issue adversely to the plaintiff, there could be no recovery. One week after payment became due plaintiff notified defendant that it would not lay any more than one-half mile of single track until more money was sent. The next day it telegraphed the work would stop if more funds were not sent; six days later it telegraphs that the workmen would he ordered home unless the money was received in forty-eight hours; and on December 2d it formallv notified defendant that it did not consider itself as further bound by the contract. This all occurred within twenty-three days of the time when the instalment became due, and while the defendant was importuning the plaintiff to go on with the work, and had remitted $4,000 in part payment, and was endeavoring to obtain the means with which to pay the balance. What may have subsequently occurred is not important, except
There might be cases where mere delay in making the stipulated payments might be so inexcusable or unreasonable, or so indicative of an utter inability to perform the entire contract, as to be equivalent to a refusal to perform, and a denial of the plaintiff’s right to proceed under it, but there is no proof in this record from which an abandonment by the defendant can be inferred prior to the time when the plaintiff must be deemed, for the purposes of this appeal, to have elected to terminate the contract.
But my brethren, while-concurring as to the legal effect of a rescission and abandonment of the contract by the plaintiff, do not agree with me as to the conclusiveness of the verdict upon the record now here. As the plaintiff excepted to the direction of a verdict for the defendant, and requested to have the question submitted to the jury, whether upon all the evidence there was not a total abandonment of the contract by the defendant, it is thought that he is not precluded from now insisting that if the defendant relied at the trial upon a rescission of the contract by the plaintiff, that question should also have been submitted to the jury upon all the evidence in the case.
In this view the jury should have been instructed that if, from all that occurred between the parties relating to this controversy, they found that the plaintiff elected to rescind the contract because of the defendant’s default in not making payment as agreed, the plaintiff was not entitled to recover; but if they found that there had been no rescission, and that the acts, conduct and declarations of the defendant were equivalent to an abandonment by him of the contract in its entirety, the plaintiff was entitled to recover prospective profits as damages, less the amount received by him in excess of the value of the work done and materials furnished.
All concur for reversal and a new trial upon these grounds, except Maynard, J., who is for affirmance for the reasons stated by him.
Judgment reversed, and a new trial granted, costs to abide the. event.