Majority
Headnote
1. Evidence—Contract.Plaintiff in this action sought to recover a balance alleged to be due him for work, labor and services rendered and materials furnished, in the construction of defendant’s building, pursuant to a written contract therefor between the parties, and for extra work upon the same building. Defendant, among other things, denied that plaintiff had completed the work required of him, and that any extra work whatever, other than such as was paid for, had been done at his instance and request. The record shows that plaintiff’s claim for extra work arose in part, as alleged, from the fact that the drawings and specifications submitted to him for the purposes of his estimate of the. cost, preliminary to the making of the contract, called for the construction of a building sixty-five feet and two inches wide; while the building constructed by him under defendant’s direction and that of his architect, was sixty-six feet and four inches in width. The action was tried and resulted in a verdict for plaintiff for an aggregate amount upon both causes of action, from the judgment whereon defendant appealed to the general term of the court below, where it was reversed for rulings on the trial which were prejudicial to defendant and are hereinafter noticed, and a new trial granted. Instead of availing himself of tile new trial plaintiff appeals from the order to this court having given the statutory stipulation for judgment absolute against him in the event of affirmance.
The contract for the construction of the building required plaintiff to do the work therein referred to “ agreeably to the drawings and specifications made by Frederick Lohse, architect, and signed by the parties and hereunto annexed.” Ro drawings or specifications, however, signed by the parties, or otherwise, were annexed to the contract, and thus it became necessary to inquire concerning the drawings and specifications intended, for which purpose resort had to be taken to extrinsic evidence, St. John v. Potter, 46 St. Rep. 883 . Browne on Parol Ev. 125. In this behalf plaintiff was allowed to give in evidence a paper purporting to be specifications relating to the building mentioned in the contract, which was unsigned, but which plaintiff maintained was the paper submitted to him, and from which he estimated the cost of construction at the sum named in the contract subsequently entered into between him and defendant and which the latter thereby agreed to pay. Thereafter defendant’s counsel offered in evidence another paper also, purporting to be specifications relating to the same building, also' unsigned, which defendant had previously testified to as being the same paper which was
The order appealed from should be affirmed and judgment absolute for defendant entered upon plaintiff’s stipulation, with costs of this appeal, and of the court below.