Majority
Headnote
Appeal—Dismissal oe Complaint.The boilers for the destruction of which the plaintiff claims damages, were in the old Hotel Clenham at Fifth avenue and 22nd street, the demolition of which, defendant, as architect and supervisor for the owners, was directing, preparatory to the building of a new structure. He made a contract with one Seagrist to take down the old building, and Seagrist was to have the old material, which included the boilers. Seagrist sold them to the plaintiff before removing them and subsequently, as it is claimed, abandoned his contract, leaving them on the premises. The plaintiff notified defendant of his purchase and tried to sell the boilers back to him. This offer was refused, and defendant notified plaintiff to move the boilers at once. This not being done, within five days thereafter defendant directed one Briggs to take them away, and they were broken up and sold by the latter. There was a question as to whether there was undue delay on plaintiff’s part in getting out the property, which was enclosed in a vault under the sidewalk; and as to whether he stood by and acquicsed in their destruction, when he could have removed them ; but these questions of fact were disposed of by the justice in plaintiff’s favor upon evidence which supports the finding. The plaintiff's title to the property by purchase from Seagrist, which was ratified by defendant, who had authority from the owners, cannot be successfully disputed. The value of the boilers was the subject of conflicting evidence and the finding that they were worth the moderate amount allowed ($75.) ought not to be disturbed.
It is argued that plaintiff failed to prove trespass because he had not possession, or right to immediate possession. The point that he had not proved the cause of the action alleged was not taken in the court below, the motion to dismiss the complaint being made only when plaintiff rested and placed upon the ground
The judgment must be affirmed.