Majority
Headnote
1. Appeal—Finding.The action was originally brought by the An-V sonia Brass and Copper Company to foreclose a lien claimed by it, pursuant to the provisions of the Mechanic’s Lien Law (ch. 342, L. 1885) and against the defendants Charles A. Gerlach, as owner and contractor, and James Curran, as lienor. Subsequent to .the commencement of the action it was discontinued so far as the plaintiff was there affected and directed to proceed upon the issues tendered by the answers of the defendants, Curran and Gerlach, respectively. Curran claimed to he entitled to a lien for work, labor and services rendered and materials furnished, under two certain contracts with Gerlach, one for the supply of the steam heating and fitting „in the building known as “ The Gerlach ” and situated on Twenty-Seventh street between Sixth avenue and Broadway, in the city of New York, the other for gas piping and fitting in the same building, and for extra work. The aggregate amount of the lien claimed was $6,110.55, with interest, of which $4,300 represented a balance of $7,600, the agreed compensation under the contract for steam heating and fitting, $1,092.92, a balance of the fair and reasonable value of the gas piping and fitting, and $717.63, the value of the extra work. Gerlach denied the complete performance of the contract for steam heating and fitting on Curran’s part that the gas-piping and fitting and extra work were of the value claimed by Curran, and that the extra work was such in fact. He furthermore interposed a counterclaim against Curran for expenses alleged to have been incurred in improving the work undertaken by Curran and necessitated by the latter’s negligence and unskillful performance. The referee found, as matter of fact, that Curran had performed the contract for steam ■heating and fitting on his part except to the extent of $322.30 as to which he was prevented by Gerlach, and to $93.25 for work necessarily omitted because of changes and alterations in the plans and specifications which were directed by Gerlach ; and that, after crediting Gerlach with the payment of $3.000, admitted by Curran, there was due the latter from the former $4,184.45 under the contract last above mentioned. The referee further found, as matters of fact, that Curran, at Gerlach’s request, furnished labor and materials which were not included in the contract for steam heating and fitting, of the reasonable value of $717.63 ; and that he also furnished and fitted 16,150 feet of gas-piping for which Gelarch had agreed to pay at the rate of twelve cents per lineal foot, amounting to $1,938, on account of which there had been paid $1,000, leaving due a balance equal to $938, and interest. As additional facts the referee found that, in connection with the gas-piping and fitting, Curran supplied the labor and materials for cutting off and replacing a number of gas centers, which were reasonably worth $144, and for work in the boiler room worth $10.92. Accordingly it was adjudged that there was due Curran from Gerlach the aggregate sum. of $5,995, with interest, for which he had a lien upon the premises described in the complaint. No errors in rulings in the admission or exclusion of evidence are urged upon this appeal, and we are relieved of inquiry concerning the sufficiency of evidence in support of the counterclaim because the
The judgment should be affirmed, with costs.
Bookstaver, P. J. and Prior, J., concur.
Cases cited
- West v. Van Tuyl 2 Silv. Ct. App. 501 p. 199
- Chapman v. Wheeler 50 N. Y. 666 p. 199
- Nolan v. Whitney 88 N. Y. 648 p. 199
- Baird v. Mayor 96 N. Y. 567 p. 199
- Griffin v. Colver 16 N. Y. 489 p. 200