Majority
Headnote
1. Condemnation proceedings—Superstructures.This is a proceeding instituted by the plaintiff, a domestic railroad corporation, for che purpose of acquiring by
The plaintiff was organized under the statutes of the state for the purpose of maintaining and operating a railroad in Livingston county, New York, which had been theretofore constructed by the Erie & Genesee Valley Bailroad Company, and operated by that company and by the New York, Lake Erie & Western Bailroad Company as lessee of the said Genesee Valley Company. The Genesee Valley Company, after it was organized, instituted proceedings to condemn a right of way across the defendant’s farm, and carried on such proceedings down to the negotiations with the defendant for the right of way and without prosecuting them further, entered upon the defendant’s land against his remonstrances, graded a track and constructed superstructures thereon,, consiting of bridges, sluices, ties, rails, fences and other improvements, and thereupon comihenced the operation of its road and ran its trains across the defendant’s lands, until the first of Januar}r, 1872, when it leased its railroad and franchises to the New York, Lake Erie & Western Bailroad Company. The latter company entered into possession and operated the road until 1891. The defendant Hammond, in 1884, commenced an action of ejectment against the Erie & Genesee Valley Company, and the New York, Lake Erie & Western Bailroad Company to recover possession of this strip of land, and in the year, 1887, recovered a judgment against the defendants, adjudging that he was seized of an estate in fee in said lands, and. was entitled to possession thereof, and by virtue of the judgment and execution, the sheriff put the defendant in possession of the land on the 6th day of November, 1891. The plaintiff acquired title to the franchises andproperty of the Genesee Valley Boad in October, 1891, through foreclosure proceedings, and thereafter, and on the 20th day of November of that year, instituted these proceedings to condemn the right of way above described across the defendant’s land. Issue was joined and a trial was had before a referee, who made a decision by which he found and decided that the plaintiff was entitled to take and hold the property described in the petition for railroad purposes, and reported that in ascertaining the compensation to be made to the owner, the commissioners should estimate the value of the superstructures upon the land above mentioned, and he further decided that the defendant was entitled to recover costs and disbursements of the proceedings against the plaintiff. An interlocutory judgment was entered upon the said decision, the plaintiff appealed from said judgment and asks for a reversal of so much thereof as "relates to the direction to the commissioners to ascertain the value of the superstructures, and to such part thereof as awards costs. It is his contention that the referee did not have jurisdiction to pass upon these questions. The order of reference was in the ordinary form, to the effect that upon reading and filing the petition of the plaintiff, praying that it may be adjudged that the public use requires the condemnation of the real property therein described, and that the plaintiff may be adjudged entitled to take, hold and possess such property for the purpose of
The commissioners are required to view the premises, hear the testimony, reduce it to writing, and fix the amount of compensation which ought to be made to the owner, and make report to the court of their proceedings with the minutes of the testimony taken. The report and testimony must be filed, and any party to the proceedings may move for its confirmation. The court may confirm the report or may set it aside for irregularity or for error of law in the proceedings before the commissioners, or upon the ground that the award is excessive or insufficient. There are provisions regulating the awarding of costs upon the final disposition of the proceedings.
The only provision for costs upon the preliminary hearing before the court or referee is in case the petition shall be dismissed, then the defendant is entitled to costs. The petition presented
The learned referee probably embraced in his decision the provision requiring the commissioners to appraise the superstructure because of the allegations in the petition mentioned. The allegations in the petition in reference to the superstructure were unnecessary and superfluous, except, perhaps, as affording some explanation of the failure of the parties to come to an agreement as to the value of the land sought to be condemned. There was no demand in the petition to condemn the superstructures, on the contrary, the plaintiff claimed to be the owner of them, hence there was no necessity or propriety in asking for their condemnation. As the plaintiff was not asking for the condemnation of the superstructures, the defendant was not required by the provisions of the condemnation law to make answer regarding that allegation. It may be held ultimately, in view of the judgment in the ejectment action that the defendant is the "owner of said superstructures, but that question will arise before the commissioners when they are assessing the value of the property sought to be condemned, and before the court upon the application for the confirmation of their report.
If the superstructures belonged to the defendant, the commissioners may take that into consideration in fixing the value of the piroperty.
The plaintiff cannot be said to have consented that the referee should pass upon this question and is therefore estopped from raising it upon this appeal, for such a finding on the part of the referee could not have been anticipated, and the plaintiff duly excepted to such finding.
The referee erred in giving costs to the defendant. As we have seen, the only case in which the defendant is entitled to costs upon the preliminary hearing, is where he succeeds in having the petition dismissed. The petition was not dismissed in this case, but
Dwight, P. J., Haight and Bradley, JJ., concur.