Majority
Headnote
1 Contracts — -Building—Architect.This action is brought to recover a balance claimed to be due on a building contract. On the 24th October, 1890, the plaintiff Duell and the defendant entered into a contract, in writing, for the erection by Duell, on or before April 1, 1891, of a store and tenement block on a lot of defendant on State street, in the city of Binghampton, Specifications and drawings were attached that were made by an architect, Mr. Reynolds. The
“ Sixth. Should any dispute arise respecting the true construction or meaning of the drawings or specifications, the same shall be decided by the architect, and his decision shall be final and •conclusive; but, should any dispute arise respecting the true value of extra work or work omitted, the same shall be valued by two competent persons, — one employed by the owner, and the other by the contractor, — and those two shall have power to name an umpire, whose decision shall be binding on all parties.”
The tenth or last clause was as follows:
“Tenth. The last payment on this contract shall not. be paid until all charges for extra work and allowances for ommissions have been rendered, agreed to, and certified by the architect”
Soon after the contract was executed, the work was commenced, the plaintiff Carrington having, by transfer from Duell, with consent of defendant, become owner of a one-half interest. The rear of the lot was low ground,' and in the specifications there was the following clause:
“ The ground being soft where rear of building is located, it will be necessary to dig a trench four feet deep and six feet wide, and fill with concrete two feet deep, composed of broken stone and the proper proportions of Howe’s cave cement, and as directed by architect. The water in the cave will have to be drawn back and kept pumped out until the foundation is complete. Concrete foundation to be extended forty feet on either side of building, if considered necessary by architect.”
It was soon found that the character of the ground where the rear wall was to be located was such that the concrete foundation specified in the specifications would not answer the purpose. The plaintiffs so informed the defendant, who replied that they must consult the architect about any changes in the foundation. Thereupon the architect, at the expense of the -defendant, caused rows of spiles to be driven as á basis for the rear foundation wall, and upon these the plaintiffs, by direction of the architect, built the wall; and it was agreed between the plaintiffs and the architect, acting for the defendant, that the sum of $65 should be allowed by the plaintiffs to the defendant out of the contract price for the concrete "not used under the rear wall, as,called for by the specifications. The work proceeded, and on or before January 26, 1891, the foundation walls were completed, and soon thereafter they were inspected, measured, and accepted by the architect; and on the 27th March, 1891, he issued his certificate No. 1, stating that $500 was due the plaintiffs. This amount included the first
There is no doubt that the walls settled to some extent, but the evidence is conflicting as to how much, and also as to the effect. The defendant claimed that the settling was mainly due to the improper foundation of the side and center walls, and the failure to bind the center to the rear wall; while the claim of the plaintiffs was that the settling was attributable to the manner in which the piling was placed by the defendant under the rear wall, and the failure to place it to some extent under the other walls. The main defect claimed to exist in the foundation of the side and center walls was the failure to lay a concrete basis. This was not required by the architect, and the defendant suggests that he had no discretion to dispense with it under the terms of the specification on that subject above quoted. We are, however, inclined to think that he had. That was his interpretation of the provision, and under the contract, in case of doubt in the construction or meaning of the drawing or specifications, he was the arbiter. He accepted the walls knowing the concrete was not there.
It is also claimed' that the base course under the side and center walls does not conform to the specifications. It is, however, in effect, found that they were constructed under the direction of the architect, and that when he gave the certificate Ho, 1, which covered the first payment, he knew that the base course was not in all respects such as was called for by the plans and speeifica
It is suggested that the architect had no authority from the defendant outside of that given by the contract, and, at one period in the course of the trial, it seems to have been so conceded. Still, afterwards it was proved, without objection, that defendant em,ployed the architect to overlook and superintend the building, and the finding of the referee on the subject is fully supported. It is quite clear that the plaintiffs, from the conduct of the defendant, had the right to believe that the architect had authority from her to consent to modifications in the character or manner of laying the foundation walls. Thomas v. Stewart, 132 N. Y. 580 ; 43 St. Rep. 881 .
The architect, in certifying that the payment was due which by the contract was payable “ when the foundation is completed,” in effect certified that the foundation was built according to the contract. Ordinarily this would be conclusive, except for fraud or mistake. Wyckoff v. Meyers, 44 N. Y. 143 ; Anderson v. Meislahn, 12 Daly, 149 . The referee finds that the architect, when he gave his certificate as to the basement, did not know of the manner in which one of the side walls was laid over a portion of a stump, and, to remedy this defect, the referee allowed the defendant the sum of $90. He also found, quite favorably to the architect, that he did not know of the failure to bind a portion of the center wall to the rear wall, and to remedy this defect, he allowed the defendant the sum of $220. To remedy minor defects in other portions of the building, the referee allowed the defendant the sum of $111, making in the aggregate the sum of $421 allowed for remedying defects.
Upon the subject of acceptance, the referee finds :
“ That on the 2d May, 1891, the defendant, in company with
The evidence is sufficient to sustain these findings. The defendant afterwards made payments to the extent of $970, the items being above stated, and no certificate was asked for. The defendant took upon herself the adjustment of the Lee claim, and the amount of it was, by consent, deducted from the contract price. The controversy over the Lee claim seems to have been the occasion of the architect’s stopping his certificates. Inferentially, the dispute between Lee and the defendant continued after this suit was commenced. The plaintiffs, before commencing suit, applied to the architect for a final certificate, which he declined to give. The referee allowed extras to the amount of $127.19. The evidence fully sustains this allowance, but the amount was not agreed to by the parties, or the value ascertained in the manner specified in the sixth clause of the contract. It is found, however, that the plaintiffs, before suie, proposed to the defendant that the same be valued by two competent persons, one- to be appointed by the plaintiffs, and the other by the defendant, they to have power to name an umpire, but the. suggestion was not entertained by defendant, and she omitted and neglected so to do. Smith v. Alker, 102 N. Y. 87 .
The referee held that by the agreement of May 2, 1891, followed by the taking of possession by defendant, there was a waiver by defendant of an architect’s certificate as to the final payment, or for the extra work and materials. The authorities
An item of $200 was allowed the plaintiffs by the referee in regard to which some question is made. The plaintiff, Duell, soon after the making of the contract, discovered that he had made a mistake of $300 in his figuring on the brickwork. He informed the defendant of this mistake, and then, as the referee finds, it was agreed between him and defendant that he should go. on and complete the building, and, when completed, he should ' exhibit to defendant his bills, showing the cost of constructing the building, and, if if appeared that he had not made anything upon the contract, the defendant would allow him the sum of $200, in addition to the amount specified in the contract. The cost of construction was in fact, $7,428.39. It is found that after the building was completed, and before suit, the plaintiffs, at different times, demanded of defendant a settlement and payment, and were ready and willing to show defendant their bills and what they' had paid out in erecting the building, and asked defendant to fix a time when she would look over their bills; but defendant neglected and omitted so to do, or to pay plaintiffs the balance unpaid on the contract. It is not claimed that there was not a sufficient consideration for the agreement of the defendant, Munroe v. Perkins, 9 Pick. 298 , 305; Lattimore v. Harsen, 14 Johns. 330 ; Stewart v. Keteltas, 36 N. Y. 892 ; 3 Am. & Eng. Enc. Law, 836; but it is claimed that the plaintiffs did not exhibit their bills. They seemed to have been ready to do it, but the defendant did not care to settle. We think the item was properly allowed. At the trial, one of the questions in dispute was whether the defendant in fact, made a certain payment which the plaintiffs denied. This was clearly a question of fact, and the conclusion of the referee should not be disturbed.
We have thus considered what appear to be the main features of the case. The more important issues were on questions of fact. In view of the acceptance and promise and subsequent occupancy by the defendant, a case is presented where strict performance ini every particular should not be deemed a condition precedent to the plaintiffs’ right of action on the contract; but the rule as to substantial performance, Woodward v. Fuller, 80 N. Y. 312 ; Murphy v. Stickley Simonds Co., 82 Hun, 158 ; 63 St. Rep. 744 , and cases cited, should be applied, and the plaintiffs be allowed to recover the balance of the contract price,' less the damages from defects attributable to the plaintiffs, and not waived by the defendant. The referee has proceeded on this basis, and we find no good reason for disturbing the result.
Judgment affirmed, with costs.
All concur.
Cases cited
- Thomas v. Stewart 132 N. Y. 580 p. 166
- Wyckoff v. Meyers 44 N. Y. 143 p. 166
- Smith v. Alker 102 N. Y. 87 p. 167
- Fallon v. Lawler 102 N. Y. 228 p. 168
- Lattimore v. Harsen 14 Johns. 330 p. 168
- Woodward v. Fuller 80 N. Y. 312 p. 168