Majority
Headnote
1. Pleading—Affirmative defense.The plaintiff and the defendant entered into a contract in March, 1882, by which the plaintiff agreed to do the work of laying water mains in Jerome avenue, in the city of New York, and the defendant agreed to pay therefor on basis specified. The work was performed by the plaintiff in due course, and accepted by the superintendent of public works. Payments were made from time to time to the plaintiff down to and after the commencement of this action ; the last payment being $1,119.71. Plaintiff’s claim on the trial was that after the last payment there remained due to him $2,191.81, being for 337.4 cubic yards of rock excavation at $2.95 per yard; 2,504.2 cubic yards of earth excavation at thirty-three cents per yard, and 2,843.1 cubic yards of filling at. thirteen cents per yard; such being the prices specified in the contract for such work. The contract provided that the trench should be excavated two feet wider than the diameter of the pipe and one foot deeper than the bottom of the pipe, and that whenever, in the opinion of the engineer, it should be deemed necessary to place the pipe deeper, the trench should be excavated to such a depth as the engineer should direct, and the pipe laid accordingly. It appears that the plaintiff has been paid for excavation and filling on that basis. But each piece of pipe laid was twelve feet from' hub to hub, and, according to the testimony adduced in behalf of
“ To prevent all disputes and litigations, it is further agreed by and between the parties to this contract that said engineer shall in all cases determine the amount or the quantity of the several kinds of work which are to be paid for under this contract, and he shall determine all questions in relation to said work and the construction thereof, and he shall in all cases decide every question which may arise relative to the execution of this contract on the part of the said contractor, and his estimate and decision shall be final and conclusive, and such estimate and decision, in case-any question shall arise, shall be a condition precedent to the right of the party of the second part to receive any money under this agreement.
The, question which we are required to pass on is whether the court erred in receiving the evidence upon which its decision was finally grounded. As the evidence stood when plaintiff rested, it appeared that the plaintiff had performed under and in pursuance of the contract an amount of work for which he was justly entitled to recover the amount claimed by him, and that he had requested the engineer to include the excess of work at the joints in his certificate, which he had refused to do. The court, therefore, properly denied the defendant’s motion for a dismissal of the complaint. The defendant, for the purpose of establishing a defense, offered in evidence the engineer’s final certificate of the amount of work done under the contract. This the plaintiff objected to, but his objection was overruled, and the paper was received, which led to the direction of a verdict against him. The effect of the certificate, supplemented by the engineer’s testimony was not to show that plaintiff had not done the amount of work testi
After the court had directed a verdict in favor of the defendant, the learned counsel for the defendant, appreciating that the defense upon which he had succeeded was not to be found in the pleadings, asked that the answer be amended by inserting an allegation setting forth the clause in the contract in respect to the certificate of the engineer, and an allegation that the certificate which had been offered in evidence was given by the engineer. While the motion was granted by the trial court, it has not helped the situation, for the granting of it was error. The general rule that the court may so amend pleadings as to conform them to the facts proved is not applicable to this case. It is not a case of mere variance or defect, but an attempt to amend a pleading after trial by alleging a defense not hinted at in it, and where the evidence upon which the motion was founded was received against the objection of the plaintiff. If this could be done, the useful objects which pleadings now serve in our system of jurisprudence would not be achieved. Instead of advising an adversary of the issue tendered, it would be possible to recover on a cause of action entirely different from that alleged, or, as in this case, to succeed upon a defense when the plaintiff has had no warning that he would be called upon to meet it.
The j udgment should be reversed, and a new trial granted, with costs to appellant to abide the event.
All concur.