Majority
Headnote
Parties—Supplemental complaint.This is an equitable action for the foreclosing of a mechanic’s lien. The defendant the New York Central & Hudson River Railroad Company heretofore made a motion to have the defendant Louis Marshall made a party to this action. The motion was granted. An appeal was taken therefrom, which was ultimately passed upon by the court of appeals in 145 N. Y. 390 ; 64 St. Rep. 834 , where a full statement of facts of the action are set forth; and it was there held that the defendant Marshall was at least a proper, if not a necessary, party, as the assignee of the original contractor in the case. Thereafter the plaintiff, by supplemental complaint, brought in the defendant Louis Marshall as a party defendant. To that supplemental complaint the defendant Marshall demurred, which demurrer has been sustained in the court below.
That the defendant Marshall isa proper, if hot a necessary, party to this action, has been heretofore decided by the court of appeals, and is not an open question to us here now. The only question open for discussion is whether the plaintiff has pleaded sufficient facts in his supplemental complaint to bring the respondent Marshall in as a proper or necessary party to the action. That Moffett, Hodgkins & Clarke Company were the original contractors in this action, the plaintiff being the subcontractor under them. In this supplemental complaint the plaintiffs have reiterated all the matters and things set forth in the original complaint, and set forth a judgment in an action wherein the. Moffett, Hodgkins & Clarke Company were the defendants, and by which the defendants O’Brien and Boo raen were appointed receivers of the said Moffett, Hodgkins & Clarke Company. Then follows this allegation :
u And, further, that it is claimed by the above-named defendant Louis Marshall that before the appointment of such receiver the Moffett, Hodgkins & Clarke Company assigned to him, the said Louis Marshall, all its interest in any sum which might be found due and' owing to that company from the New York Central & Hudson' River Railroad Company.”
It is claimed here by the respondent Marshall that such allegation is not sufficient as against him. As heretofore stated, the court of appeals has held that Marshall, as the assignee of .the Moffett Company, is a proper party to this litigation. Section 447 of the Code of Procedure reads as follows:
“ Any person may be made a defendant who has or claims to have an interest in the controversy, adverse to the plaintiff, or who is a necessary party defendant, for the complete determination or settlement of the questions involved therein.”
If the assignee of a contractor is a necessary or proper party in proceedings to enforce a mechanic’s lien, is one who claims to be an assignee a proper party? Is he an adverse party to the plaintiff, within the meaning of the Code? It seems to me that within the meaning of the section of the Code I have quoted, any person whom it is necessary or proper to make a party to the proceedings, for the complete determination of the rights of all persons con
For these reasons the order sustaining should be reversed, with costs and disbursements of this appeal, and costs in the court below.
All concur.
Cases cited
- Hilton Bridge Construction Co. v. New York Central & Hudson River Railroad 145 N. Y. 390 p. 650
- Frost v. Koon 30 N. Y. 428 p. 651