Majority
Headnote
1. Contract—Building—Construction.Prior to December, 1892, the hoard of education of defendant entered into a contract with Isley & Dixon for the construction of a brick schoolhouse on Montgomery street. The building was partially constructed, and then, in December, 1892, the contractors abandoned the contract. On the 31st December, 1892, the board of education entered into a contract with the plaintiff to complete the mason work of the building, in accordance with the plans and specifications of the architect, for a
“When he (plaintiff) took that contract, "he was to tear down the outside wall of the building, from the first floor joists down
to the water table, and relay it. Everything else was all in good shape, np to that point, but the outside was not laid right. 'We put it in the specifications that .the outside wall would have to be taken down, to the water table, and relaid. In other words, the other walls looked all right up to that time. Q. That was the understanding when you made the contract? A. Yes, sir.”
Nothing seems to have been said to plaintiff about protecting the work of his predecessor. The architect had as good or better means than the plaintiff had for knowing whether the walls were not adequately protected. The court did not, we think, err in holding that the plaintiff was not responsible for the neglect of the original contractor, or of the architect, in not having the walls properly protected.
Clearly the work in question was outside of the work for which the price named in the contract was to be paid. The defendant, however, claims that the plaintiff cannot recover, because the value of the extra work was not, before suit, determined by the architect, or by arbitrators, in case of dispute as to the value, in accordance with the provisions of the contract on the subject of extra work. The clause of the contract on which this claim is based, provides that, in case changes are ordered—
“The value of such changes to be mutually agreed on in writing between the architects and contractor beforehand. In default of such agreement in writing, the fair value of the same, as determined by the architects, shall be added to or deducted from the contract price, as the case may be; but should any dispute arise respecting the value, as so determined, then the same shall be valued by two competent persons,—one employed by the proprietor, and the other by the contractor,—and these two shall have the power to name an umpire, whose decision shall be binding on all parties.”
The architect himself testifies that it was practically impossible to estimate beforehand how much the cost or value of the change in question would be. According to the evidence of the plaintiff, which is not denied, he, at the request of the architect, kept track of the material and labor furnished for the particular work in question, and when the work was done he made out a bill for it, and delivered it to the architect in August. This suit was commenced in December. There is no evidence that the amount was disputed, but the position of the defendant, or those representing it, was that they were not liable at all. The plaintiff may well have believed that he had done all that was required in regard to fixing the amount. Besides, at the trial, at the close'of the evidence, the only question then raised was that the plaintiff could not recover- by reason of his neglect to protect the walls from the date of his contract. On the motion for nonsuit, the question' that the amount had not been properly ascertained was not specifically raised. We are inclined to the opinion that under the ruling in the cáse of Seward v. City of Rochester, 109. N. Y. 164;
Judgment affirmed, with costs.
All concur.