Majority
Headnote
Mechanic's lien—Judgment.—This is an action to foreclose a mechanic’s lien filed against certain premises in the city of New York, of which the defendant, John E. O’Brien, was the owner. The plaint-
The appeal brings up for review, in the first place, a ruling of the referee with respect to the admission in evidence of what purported to be specifications of the contract referred to. These specifications were necessary in order to show what was required to beyond by the plaintiff. They were admitted in evidence and it was shown that they were the specifications originally made with certain changes, all of which appear to have been by the defendant. When they offered in evidence, the referee stated that, if any objection to their correctness were to be made, he would then hear it, and if none were made the paper would be marked in evidence. It does not appear that any objection was made, but an exception seems to be recorded to the ruling of the referee. There being no ground of objection stated, and nothing appearing upon the record from which the court, could infer that the referee was in error in accepting the paper in evidence, it is unnecessary to make further reference to this topic.
It is claimed by the appellant that the proof does not establish that the plaintiff substantially performed the contract, and we are asked to examine a folios or more of testimony, and a number of exhibits, to extract evidence of seemingly inconsiderable omissions and defects in the work which was done by the plaintiff. There is no certificate in the case that the record contains all the evidence that was submitted to the referee. We have, however, looked into it sufficiently to ascertain that, on all of the matters of alleged defects specified in the fourth point of the appellant’s brief, there was conflicting evidence, and the determination of the referee respecting what was established by that evidence we are not called upon now to interfere with. So far as the details of the work were concerned, we see no reason to differ with the referee in the conclusion that there was a substantial compliance with the contract.
It appears by the record that upon the trial a witness (Arrowsmith) was allowed to give testimony of a conversation had between himself and one Marshall respecting the absence of a certificate of the architect that the work was properly done,
Concerning the form of the judgment, to which defendant states an objection, it is true that it directs that the plaintiff recover of the defendant the whole amount adjudged to be due; but it also provides for the sale of the premises, and that, if there be any deficiency remaining on the sale, the amount thereof be specified in the report of the referee, and that the plaintiff recover of the defendant the amount of the deficiency so remaining, and have ex ecu-cation therefor. There is nothing in this judgment from which it could be inferred that execution was to be issued against the property of the defendant for the whole amount of the lien. The true interpretion is that the premises are first to be resorted to, and that plaintiff have execution against the property for deficiency in case the full amount is not realized from a sale of the premises. On the whole case, we are* of opinion that the judgment should be affirmed, with costs.
All concur,.