Majority
Headnote
1. Contract—Building—Construction.The questionwhether or not the trial court erred in dismissing the counterclaim of the appellants is one of mixed law and fact. It will be well to consider first the construction to be given to the contract. The performance or the contract was made contingent upon strikes and boycotts. The appellants claim that the strikes referred to were only such as might occcur in the shops of the contractor. We see no reason for thus limiting the words. The obvious intent in inserting the clause was to protect the contractor from liability of delays which it could not help, so far as-they should be due to strikes. There is no reason to believe that any strike which had a legitimate tendency to retard the contractor was not meant to be covered by the expression in the contract. It does not, however, follow from this that the contractor was at liberty to order material from a striking factory and then rely upon the clause for its protection. A duty rested upon it to perform the contract if possible, and to exercise care, diligence and skill to this end. All that was obtained was immunity from the general rule of law which refuses to accept inevitable and unforseen accidentas an excuse for the nonperformance of an absolute agreement. Harmony v. Bingham, 12 N. Y. 99 .
The facts are that the contractor made a contract with the Columbia Iron & Steel Company in March, 1892, providing generally for the furnishing of material of the sort required later in performing this contract; that on July 7th, the day when the contract was signed, the president of the Carr ere Works wrote the Columbia Company notifying it, and directing the forwarding of material; and that he learned a day or so later that the Columbia Company’s men were not at work, but took no immediate steps to place the-order elsewhere. He testifies:
“Previous to the signing of -the contract w’i-th the Puck people, on July 7th, we received bids, or tried to receive bids, from other concerns; and there was no concern that I would have liked to-have intrusted that work with at that time, outside of one, which were so busy that I did not think it advisable to go to them, especially as I had the promise of the vice -president and the manager of this mill that, if the contract were given to them, it would take precedence over all others.”
It also that this was the of the Homestead strike, and that the beam manufacturers were having a good deaf of difficulty in supplying orders. Mil liken, who had been engaged in the business of iron construction for fifteen years, testified that, it took anywhere from six to eight weeks in August and September to fill an order, on account of the demand during the summer months.. But the precedence which had been promised to the Carrere Works resulted in a delivery within two weeks from the time the works of the Columbia Company started up. Milliken’s estimate was probably conservative for this particular year. He was asked: “Were you delivering continuously at that time (August, September, and October, 1892)?” and he replied: “No. We were not delivering continuously. Some of our orders we were back three months on.” It also appeared by the evidence of the secretary of the Columbia Company that not until the end of July
The view we have taken renders it unnecessary to discuss the testimony in detaill, or to consider at length the other question presented by counsel. Our conclusion, however, is that the delay caused by the strike in furnishing the beams was immaterial, in view of the tardiness of the mason, and that the acts of the appellants constituted a waiver of the delay. Our judgment might well rest upon these grounds, quite independent of the view we have taken of the strike clause. We have also examined the record as to the minor details of the work, notably the mullions, lintels, and shutter eyes; and we think that the decided weight of evidence favors the view that the contractor was not in default in any of these matters.
The judgment should be affirmed, with costs.
All concur.
Cases cited
- Harmony v. Bingham 12 N. Y. 99 p. 257