Majority
Headnote
1. Contracts—Construction.George T. Ells, doing business under the name and stvlemf the Ells Manufacturing Company, entered into a written contract with the defendant, dated" April 4.. 1893, the terms of which are substantially as follows: Defendant orders Ells to manufacture and deliver to it fifty dozen chairs, for which it agrees to pay a price to be thereafter 'agreed upon. It further agrees to advance to Ells money sufficient to buy the timber for
It appears from the statement rendered by Ells (which is found on page 76 of the appeal book), and it is not disputed by the plaintiff, that the total demands made by Ells for wages, up to November 11th, amounted to $1,150.96. In this amount there was included the sum of $444, as wages to himself at the rate of $3 per day. The amount, therefore, used for wages, other than to himself, up to such date, was $706.66. The defendant had advanced, up to such date, the sum of $740.96, as also.appears from such statement. Therefore, unless defendant was obligated, under the contract, to advance wages to Ells himself, it was not in default at the time it ceased paying. It had, up to that time, performed all that it agreed to do, and no breach of its contract had occurred when Ells stopped his work under it. It was Ells’ duty, under the contract, to at least continue the work, and furnish the chairs, so long as defendant actually advanced the funds which it had agreed to advance. We are of the opinion that under the contract the defendant was not bound to advance money to pay for Ells’ services. The phraseology of the contract is quoted above. In substance, it is to advance to Ells weekly, and on his statement, wages to pay the men. The idea that money was to be advanced to Ells for his own services is not to be found in the language used. On the contrary, it is excluded. It is to pay the men, — evidently men ern. ployed bv Ells,—and it is to pay the wages of men so employed.
If, however, it be conceded that a breach of contract by defendant has been shown, it seems that the referee has fallen into an error in estimating the damages which Ells sustained. Ells was in the business of manufacturing this kind of a chair when this order for 50 dozen was given. He entered upon the performance of the work, and, up to November 11th, had, as the referee finds, expended $1,335.93 for labor and material therein. At that date he ceased the work; having delivered to defendant 483 chairs, and having on hand a large amount in process of construction. This appears from the statement rendered by him to defendant in November, and is found on page 79 of the appeal book. The value of that material, as then fixed by him, was $692.80. All this property was retained by the plaintiff, who refused to give it up on the defendant’s demand. The referee, in making up the damages against defendant, charges it with the cost and expenses of all work done by Ells under the contract, amounting to $1,335.93. He gives the defendant credit for the money paid by it on account of wages, $740.96, and he gives it credit for $45, value of chairs and materials retained by plaintiff; and for the balance, of $549.97, he orders judgment against defendant. Manifestly, if the defendant is to be charged with the whole expense of the work done under the contract Ells should be charged with the fair value to him of the material in process of construction, which he never delivered, and upon which much of the work charged against defendant was done. In any method adopted for ascertaining what Ells has actually lost by defendant’s breach of contract, the fair value of the property so retained by him for the purpose^ of being finished into chairs would seem to be an element which should be charged against him. As hie expresses it in the statement sent, “There is enough stuff ready to put up (or nearly so)
These conclusions require that the judgment should be reversed. Judgment reversed, and a new trial ordered; costs to abide the event. All concur.