Majority
Headnote
1. Mechanic’s lien—Waiver.The plaintiff is a carpenter and contractor. The defendant Young was the owner of a lot in the city of Buffalo, upon which he was, in the summer of 1895, erecting three houses. In December, 1894, the plaintiff and the defendant Young entered into a written agreement, by which the plaintiff agreed to do the carpenter work on each of the three houses for the stipulated price of $1,387.50, and the defendant Young was to furnish the material. The work was to be completed by the 1st day of April, 1895. The times of payment are stated in the contract, the last payment to be made when the houses were completed. On the 1st day of May, 1895, Young conveyed one of the lots, on which the house last completed was erected, to the defendant Pardee, and the deed was recorder in Erie county clerk’s office, June 17, 1895. On the 31st day of July, 1895, the plaintiff attempted to place a mechanic’s lien on the building last completed, claiming there was due and unpaid on the contract, that day, the sum of $280.08 for work and labor which he had done. The property .described, upon which the plaintiff sought to fix a lien, was the part of-the lot upon which the house last completed stood. The statute under which the lien was filed is chapter 342 of the Laws of 1885. For the purpose of disposing of this case the fact is found that, when .the notice of lien was filed, there was due and unpaid the plaintiff from the defendant Young, upon the contract entered into between those parties, the sum of $50 and upwards, and some of the labor done by the plaintiff upon the house and lot sold to the defendant Pardee was after the latter received his deed, and was done with his knowledge and consent. The defendant Young made default, and did not answer.
In disposing of the case, it is unnecessary to examine with close attention the evidence bearing on the questions whether the work was done and performed according to the terms of the contract, and whether the plaintiff was delayed because the defendant Young did not supply the material so that the work could be completed within the time mentioned in the contract. Both of those questions are, pro forma, determined in the plaintiff’s favor for all
The suggestion of the counsellor the plaintiff that the covenant not to file lien did not apply, and did not restrain the contractor after the owner had failed to perform the stipulations to pay for \ the work and labor at the time mentioned in the contract, cannot be recognized as sound: for the covenant is an independent one. continuous and unconditional. It is manifest that in this caso
As to the defendant Pardee, the plaintiff’s complaint is dismissed upon the merits, with costs and disbursements the same as are allowed in civil actions in this court. As against the defendant Young, who made default, the plaintiff is at liberty to proceed and enter up such judgment against him as he is advised he may be entitled to. See section 15, c. 342, Laws 1885.
Ordered accordingly.
Cases cited
- Buel v. Trustees of Lockport 3 N. Y. 197 p. 637
- Bowen v. Aubrey 22 Cal. 566 p. 637