Majority
Headnote
1. Municipal corporations—Liability for local improvements—When general funds liable—Charter of the city of Buffalo.Action to recover for several jobs of work done by plaintiff’s assignors, at defendant’s request, in and about certain local improvements in the defendant city. Claims for the work were duly presented to the common council of the city, who audited and allowed the same and ordered assessments to be made therefor, at different times between the 2d of July, 1883, and the 15th of December, 1884, inclusive.. The gist of the action, as alleged in the complaint, is that the defendant neglected and refused to make or confirm the assessments ordered, or to pay for the work, orto make any provision whatever therefor, whereby the plaintiffs suffered damage to the amount of said claims as audited, with interest on each from the date of its audit.
By the charter of the defendant, the expense of local improvements of the character of the work alleged in the complaint is to be defrayed by local assessments, and certain ordinances of the city provide that warrants in payment of work of that character shall not be drawn until the assessment therefor shall have been confirmed by the common council, and such warrants shall be made payable out of the fund when collected or when the money is actually realized by the city. The counsel for the appellant contend that in
It has been held repeatedly that if the failure of the corporation to realize-the fund is owing to its own neglect or unreasonable delay, it i hable presently. The case of Cumming v. The Mayor, etc., of Brooklyn (11 Paige, 596), is an authority in point for the present action. The corporation of Brooklyn contracted with the complainants to grade and regulate one of he avenues of that city, at a specified price to be paid fox rut of the moneys which were to be collected from an assessment to be made for such improvement. The work was completed and approved, and in March, 1831, the corpox-ation ordered the assessors to make an assessment for the improvement. The assessors accordingly made an assessment of the expense of the im-.
The defendant’s counsel contend that the city is not liable for the neglect of the assessors; that the assessors are not the agents of the city in respect to making assessments, but are an independent board of public officers, whose duties are prescribed by the legislature, and who act, not for the city, but for the public at large. In support of that position, they cite the well known case of Maxmilian v. The Mayor ( 62 N. Y., 161 ), and many other analogous cases. To the cases cited, may be added the recent one of Heiser v. The Mayor, etc., of New York ( 5 N. Y. St. Rep., 558 ), in which it was held that the-board of assessors of the
We conceive it needless in this case to determine whether the assessors of the city of Buffalo, are to be regarded as the agents of the city, in respect to making assessments as required by the charter. The plaintiff’s action does not rest upon the theory that the negligence of the assessors is the negligence of the city. Its theory is that it is the duty of the city, through its common council or other appropriate agency, not only to set in motion the machinery which the charter has provided for raising the needed funds to pay for local improvements ordered by it, but also to see that such machinery is kept in motion, and to enforce its power in that respect with reasonable diligence, until the end is accomplished; and that for breach of such duty, the corporation is hable to a party injured thereby. That position, we think, finds support in cases already cited. In Cumming v. The Mayor (supra), Chancellor Walworth said: “ Although the common council may not have a control over the assessors, directly, they were bound by their contract, to have the assessment made, and if the assessors refused to do their duty, the corporation should have applied to the supreme court for a mandamus to compel them to make a proper assessment, instead of' confirming an invalid one.” In Baldwin v. The City of Oswego (supra), the defendant was held hable “on account of the neglect of its officers to enforce the legal instrumentalities provided for enforcing payment against the_parties primarily chargeable with such payment.
By the charter of the city of Buffalo, among the officers of the city, to be elected, are three assessors (Title 2, § 1), who shall constitute a board of valuation and assessment, a majority being a quorum (Id., § 39), by whom all local assessments shall be made. Title 6, § 2. They are required to publish notice of completed assessment rolls in their hands, the first week of each month (Title 6, § 5), and to give notice that such rolls will remain in their office, open for inspection and revision for ten days. At the expiration of that time they are to deliver a copy thereof to the city attorney, when the functions of the assessors in regard to such roll, appear to cease. The general duties of the assessors are prescribed by the charter. Tlie details of their duties, where the charter is silent, may be prescribed by the
In respect to the negligence of the corporation there can be no question. The claims in suit were all presented to the common council and audited before the 15th of December, 1884, and no assessment had been made up to the' 21th of March, 1886, when this suit was commenced. No excuse is shown for the delay of the assessors or the neglect of the corporation authorities to proceed against them on account of such delay. There being no dispute about the facts, the question whether the delay was unreasonable was for the court. Bowery National Bank v. The Mayor, 3 Hun, 639 , and cases cited by Brady, J., pp. 228-9.
The point is made that the plaintiff failed to show that the claim upon which he seeks to recover was presented to the common council before the commencement of the action; or, in other words, that as the plaintiff did not notify the common council that he claimed to recover the amount of the bills audited on the ground of the alleged neglect of the defendant, the provision of the charter requiring all claims to be presented, etc. (title 3 §, T), stands in his way. We think the position is untenable. The claims for the work were presented, as the statute required, and nothing more was necessary.
. A complete cause of action having been made out, the plaintiff was entitled to recover as damages the amount of the bills as audited, with interest on each from the date of its audit, and we understand the recovery to be on that basis.
It is unnecessary to decide whether tho appellant’s counsel are right in their contention that the testimony of the plaintiff’s witnesses as to the time within which the assessors could have made the assessment-rolls was improperly received, inasmuch as independently of that testimony, the
The appeal book shows that a motion for a new trial was made by the defendant upon a case and denied, but the order denying such motion does not appear to have been appealed from, and it therefore stands.
The judgment should be affirmed.
Haight and Bradley, JJ., concur; Barker, J., not voting.
Cases cited
- Beard v. City of Brooklyn 31 Barb. 142 p. 322