Majority
Headnote
Contract— to produce platy—damages for breach, of.The defendant was the proprietor of a theater in Boston, in which he agreed to produce and exhibit a play, dramatized by the
The contract was made by telegraph, and no substantial difference exists between the statement made of it in the complaint, and the nature of it as the dispatches exhibit it. In the complaint it was alleged, that, in consideration that the plaintiff would allow the defendant to act and produce the play, and would provide the manuscript and scene plots of such play, he contracted and agreed to produce it, and act and perform the same on the seventh day of Hay, 1870, and pay the plaintiff the sum of twenty dollars for each and every time the piece should be produced and acted at Selwyn’s theater in Boston ; and that he further contracted to produce upon the stage, and publicly represent the play within a reasonable time after receiving the manuscript and scene plots. -The plaintiff then avers that he accepted the contract and agreement, so offered and made, and performed on his part, but that the defendant refused to produce the play, and claims damages for such non-performance.
By the dispatch sent the plaintiff from the defendant’s agent, he was asked : “ What are your terms for Fern ande ? Can I produce it May seventh % ” To this the plaintiff replied: “ Twenty dollars per night. You can announce it for May seventh ; if you conclude, will send scene plots to-night. Answer.” The answer was returned: “ Agreed to terms; piece announced for May seventh ; send manuscript and plots immediately.”
There was nothing in the correspondence by letter, or in the other evidence given, changing or extending these terms. Both the allegations contained in the complaint, and the dispatches which passed between the plaintiff and the defendant’s agent, showed that a contract was made between the parties. But it was not one for any definite or indefinite number of nights; it was, on the contrary, only for the evening of the seventh of May, or, according to the complaint, for some occasion within a reasonable time after the receipt of the manuscript and scene plots. In either case, but one production, or exhibition, of the play was agreed upon. And that was all that the plaintiff could positively require from the defendant for the purpose of performing the agreement made. He undoubtedly expected, and that may have been the anticipation of the defendant’s agent, that the
Brady, J., concurred.
Judgment reversed and new trial ordered, costs to abide event.
* 2 Greenleaf on Ev. (5th ed.), § 254; Hamilton v. McPherson, 28 N. Y., 72 Newell v. Wheeler, 4 Robertson, 253.