Majority
Headnote
City — liability of, to a contractor for a failure to compel an assessment to be made to raise the amount required to pay for the work done by him for it.Action to recover for several jobs of work done by plaintiff’s assignors, at defendant’s request, in and about certain local improvements in the defendant city. Claims for the work were duly presented to the common council of the city, who audited and allowed the same and ordered assessments to be made therefor, at different times between the 2d of July, 1883, and the 15th of December, 1881, inclusive. The gist of the action, as alleged in the complaint, is that the defendant neglected and refused to make or confirm the assessments ordered, or to pay for the work, or to make any provision whatever therefor, whereby the plaintiff suffered damage to the amount of said claims as audited, with interest on each from the date of its audit.
By the charter of the defendant, the expense of local improvements of the character of the work alleged in the complaint is to be defrayed by local assessments, and certain ordinances of the city provide that warrants in payment of work of that character shall not be drawn until the assessment- therefor shall have been confirmed by the common council, and such warrants shall be made payable out of the 'fund when collected, or when the money is actually realized by the city. The counsel for the appellant contend that in view of those provisions the only duty of the city, in the first instance, is to put the necessary machinery in motion to raise the money by assessment. That position, in its literal sense,
It has been held repeatedly that if the failure of the Corporation to realize the fund is owing to its own neglect or unreasonable delay, it is liable presently. The case of Cumming v. The Mayor, etc., of Brooklyn (11 Paige, 596) is an authority in point for the present action. The corporation of Brooklyn contracted with the complainants to grade and regulate one of the avenues of that city, at a specified price, to be paid for out of the moneys which were to be collected from an assessment to be made for such improvement. The work was completed and approved, and in
The defendant’s counsel contend that the city is not liable for the neglect of the assessors; that the assessors are not the agents of
We conceive it needless in this case to determine whether the assessors of the city of Buffalo are to be regarded as the agents of the city in respect to making assessments as required by the charter. The plaintiff’s action does not rest upon the theory that the negligence of the assessors is the negligence of the city. Its theory is, that it is the duty of the city, through its common council or other appropriate agency, not only to set in motion the machinery which the charter has provided for raising the needed funds to pay for local improvements ordered by it, but also to see that such machinery is kept in motion, and to enforce its power in that respect, with reasonable diligence, until the end is accomplished, and that for a breach of such duty the corporation is liable to a party injured thereby. That position, we think, finds support in cases already cited. In Cumming v. The Mayor (supra) Chancellor Walworth said: “ Although the common council may not have a control over the assessors, directly they were bound by their contract to have the assessment made, and if the assessors refused to do their duty the corporation should have applied to the Supreme Court for a mandamus to compel them to make a proper assessment, instead of confirming an invalid one.” In Baldwin v. The City of Oswego (supra) the defendant was held liable “ on account of the neglect of its officers to enforce the legal instrumentalities provided for enforcing payment against the parties primarily chargeable with such payment.”
In respect to the negligence of the corporation there can be no question. The claims in suit W'ere all presented to the common council and audited before the 15th of December, 1884, and no assessment had been made up to the 27th of March, 1886, when this suit was commenced. No excuse is shown for the delay of the assessors or the neglect of the corporation authorities to proceed against them on account of such delay. There being no dispute about the facts, the question whether the delay was unreasonable was for the court. (Bowery National Bank v. Mayor, 8 Hun, 224 , and cases cited by Brady, J., pp. 228, 229.)
The point is made that the plaintiff failed to show that the claim
It is unnecessary to decide whether the appellant’s counsel are right in their contention that the testimony of the plaintiff’s witnesses, as to the time within which the assessors could have made the assessment-rolls was improperly received, inasmuch as, independently of that testimony, the court was justified in holding, as matter of law, that there had been a lack of reasonable diligence.
The appeal-book shows that a motion for a new trial was made by the defendant upon a case and denied, but the order denying such notice does not appear to have been annealed from and it, therefore, stands.
The judgment should be affirmed.
Haight and Bradley, J"J., concurred; Barker, J., not voting.
.Judgment and order affirmed.