Majority
Headnote
Arbitration agreement, construction of — a sub-contractor not bound by the awao'd against the principal contractor — waiver.This was a proceeding msrauiea Dy me plaintiff to foreclose a mechanic’s lien, filed on December 19, 1884, against the property of the appellant, the Odd Fellows’ Fraternal Union. It appears that on the 81st day of March, 1884, the defendant, Florus F. Dieffenbacher entered into an agreement with the defendant, the Odd Fellows’ Fraternal Union of the city of Rochester, to erect and furnish all the carpenter, joiner and other work in accordance with drawings, details, etc., of a five-story annex to the building known as the “ Odd Fellows’ Fraternal Union,” on the corner of Clinton and Division streets, in the city of Rochester, for the sum of $3,653, the building to be completed on or before the 15th day of November, 1884. It was stipulated in the contract that the appellant, the Odd Fellows’ Fraternal Union, should have the right and privilege, at any time during the progress of the building, to make any alterations, deviations, additions or omissions in the work or materials contracted for, without making void the contract; but the true value of such alterations,
A dispute did arise between tbe parties, and they thereafter and on tbe 8th day of April, 1885, entered into a written agreement to submit to tbe arbitrators named therein all matters in difference between them, and agreed to abide by the decision of tbe arbitrators ■as final and conclusive according to the true intent, meaning and spirit of tbe contract. Notice of this submission to arbitrators, with tbe time and place that tbe arbitrators would proceed with tbe bearing, was served upon tbe plaintiff, and be notified to be present and ■submit such evidence as be wished to have considered. He did not .appear, however, and tbe arbitrators so selected proceeded with tbe bearing and made an award in which they found that tbe defendant Dieffenbacher should be allowed for extra work on tbe contract tbe sum of $188 60, and that tbe defendant, tbe Odd Fellows’ Fraternal Union, as owner, should be allowed as damages tbe sum of $2,252.33; that included in tbe latter sum was an item of $1,520 for seventy-six days’ delay on tbe part of tbe contractor in completing tbe work, .at twenty dollars per day. This allowance more than paid tbe ■contractor, and left a balance due from him to tbe appellant of $1,270.10. A copy of the award was served upon tbe plaintiff, who thereafter instituted these proceedings. Tbe appellant set up tbe arbitration and award as a defense. Tbe referee has held that tbe award was binding upon tbe plaintiff as to all matters except tbe said item of $1,520.
The first question, which it becomes necessary to determine, is whether or not the stipulated damages for the non-performances of the contract within the time stipulated was embraced in the contract as one of the subjects to be determined by the arbitrators. The language, as we have seen, is that in case dispute arises as to-the true value of the alterations, deviations, additions or omissions-in the work or material contracted for, it shall be determined by the arbitrators, etc. The language used in this clause is identical with that used in the former paragraph of the agreement, in which it is-provided that the Odd Fellows’ Fraternal Union shall have the right, and privilege at any time during the progress of the building “ to-make any alterations, deviations, additions or omissions in the work or materials.” The matter thus agreed to be submitted to arbitrators was evidently intended, and must, therefore, pertain to the-alterations, deviations, additions or omissions in the work or materials-which the appellant had the right to make under the contract. It-does not include the damages which was agreed to be paid in case-of non-performance of the contract; but the agreement between the appellant and the defendant Dieffenbacher, subsequently made, submitting their matters in controversy to arbitrators, did embrace the claim for damages in not performing the contract within the time stipulated, and, consequently, the award that was made was-binding upon the appellant as well as the defendant Dieffenbacher. But was it binding upon the plaintiff ? He, as surety or as subcontractor and lienor, was not a party to the agreement submitting the matter in controversy to arbitrators. He, as surety, was bound by the building contract, and to the submission in so far as it was-authorized and required by the building contract, but could he be further bound? It is true, that as sub-contractor and lienor his-
But the general rule is that judgments bind only parties and their privies, unless there is express covenant that the person shall be bound by the judgment, as in case of undertakings given under the. provisions of the Code, wherein the surety stipulates to pay the damages awarded by judgment, etc. The distinction between such cases is. sufficiently pointed out in the case of Thomson v. MacCregor ( 81 N. Y., 592 -597). (See, also, Jackson v. Griswold, 4 Hill, 522 ; People ex rel. Tuthill v. Russell, 25 Hun, 524 ; Thomas v Hubbell, 15 N. Y., 405 .) True, the plaintiff is not seeking to maintain his action as surety; he is seeking to establish his lien instead. But if a surety is not bound by the determination, we fail to see why a lienor should be. Upon the filing of his claim the statute gives him a lien to the extent of the amount due or to become due upon the contract. It, in effect, operates as an assignment of so much of the contractor’s claim and the contractor, as such, cannot, after the filing of such claim, enter into any agreement, make any admissions or do any act that will impair or defeat the hen so acquired. We, therefore, conclude that the plaintiff was not bound by the award in so far as it determined the damages for the delay, it not being stipulated in the building contract that that matter should be submitted to arbitrators.
A large mass of evidence was taken upon the subject of delays in completing the work. The referee has found, as a fact, that there were ninety days’ delay in the entire completion of the work, fifty which arose from the acts or default of Dieffenbaeher or the plaintiff.
It is claimed that these findings are not supported by the evidence. We have carefully read the evidence appearing in the appeal book, and have reached the conclusioh that the finding is not so clearly against the weight of evidence as to justify this court in interfering. It consequently follows that the judgment must be affirmed, with costs.
Barker, P. J., Bradley and Dwight, JJ., concurred.
Judgment affirmed, with costs.