Majority
Headnote
Contract — when a demand, before suit, of the amount claimed must be alleged and proved.The number of frivolous and untenable objections raised upon this appeal for the purpose of overturning the judgment, clearly indicate to us, as they did, undoubtedly, to the learned trial judge, that the defenses interposed were without merit and the object sought delay. "VVe regret, under these circumstances, to be obliged to interfere with the judgment. But one question is presented which, though to some extent technical, can be made available in obtaining a further delay, which, apparently, is the object sought by the defendant.
From the facts it appears that the defendant owned the premises •on the corner of Kutgers slip and Cherry street. Plaintiff was a builder and had a contract for the erection of a building on the premises, with a bond and mortgage to secure the payment for the work and material to be done and furnished. In October, 1888, defendant was indebted to plaintiff in the sum of $34,401.25 and interest. The defendant desired a new loan of $40,000, and in order to get it it was necessary to have the plaintiff’s mortgage taken off the record. As a consideration for the cancellation of such bond and mortgage, an agreement was entered into whereby the plaintiff agreed to surrender his bond and mortgage and take a new one for $10,000, subordinate to the prior one of $40,000, to be made by the defendant to some third person. Such agreement contained the following clause:
“At any time after the expiration of six months * * * in •case the amount then due to said Bunn is unpaid, the said Bunn is to
The testimony shows that defendant did not pay the $10,000 within the time agreed, and pursuant to agreement plaintiff sold the bond and mortgage for $ 1,000 less than its face, and allowed forty-seven dollars and fifty cents for examining title. It was to recover this amount of $1,047.50 that this action on the covenant was brought.
The claim made by the plaintiff was amply supported. The defendant sought to raise some question as to the good faith of the sale of the bond and mortgage, which it appears was made by plaintiff to his wife. But this upon the testimony was disposed of, there being no contradiction of the facts proven, that from her separate estate the wife advanced the money to purchase the bond and mortgage, and this after the defendant had been requested to procure a purchaser, and after efforts in other directions had proved unsuccessful. As stated, therefore, the plaintiff proved every fact which entitled him, in the absence of any testimony offered by the defendant, to the direction which was made by the court, with one single exception which may now be briefly referred to.
It will be noticed that in the covenant referred to, it was in effect, agreed that if Bunn should negotiate a sale of the bond and mortgage, should he find it necessary to do so, he had the right to allow a discount not exceeding ten per cent and $100 for searching the title; “ which discount and expense is to be paid by said Lett on demand.” There was no demand alleged in the complaint nor proven upon the trial. It is true that proof was furnished that a demand was made for the $10,000 mortgage debt, but there is no evidence that any demand was made after the sale of the bond and mortgage for the $1,047.50. Upon the close of plaintiff’s testimony a motion was made to dismiss the complaint upon the express ground of the absence of such an allegation of demand in the complaint and proof upon the trial, which being overruled, an exception was taken.
The question, therefore, presented is, was a demand necessary to be alleged and proved ? It is difficult to formulate a fixed rule for
“ It is the settled law of this State, announced in many decisions, that when a specific sum of money is made payable by the agreement of the parties upon demand, or at a sjiecified time at a particular place as against the original debtor, no demand at the time or place prior to the commencement of the suit is necessary. The commencement of the suit is itself a sufficient demand.” (Locklin v. Moore, 57 N. Y., 362 ; citing Wolcott v. Van Santwoord, 17 Johns., 248 ; Caldwell v. Cassidy, 8 Cow., 271 ; Haxtum v. Bishop, 3 Wend., 15 ; Nelson v. Bostwick, 5 Hill, 37 ; Mills v. Place, 48 N. Y., 520 ; Watkins v. Crouch, 5 Leigh, 522 .)
Whilst, therefore, Locklin v. Moore {supra) is authority for the position that when a specified sum of money is made payable by agreement of the parties upon demand, at a specified time at a particular place, as against the debtor, no demand is necessary before suit brought, nor is it an essential part of plaintiff’s cause of action; it is also true, as said further on in the opinion in that case, that “ a contract could, doubtless, be so drawn that the demand and place of payment would become part of it so that an action could not be maintained without a demand at the place.” We think that neither this case nor the others cited by the respondent go to the extent of holding that a demand, upon the facts here appearing, which was provided for by the agreement of the parties, was not a condition precedent to plaintiff’s right to bring or recover in the action.
The necessity for a demand becomes apparent when we remember that this was not an agreement by which a specified sum was to be
As stated in the American and English Encyclopeedia of Law (vol. 5, p. 527): “ It is necessary that a demand be made upon the party who is bound to discharge the obligation or perform the contract, unless, indeed, such party has incapacitated himself to discharge the one or perform the other.” And again (p. 528): “ Whenever the fact by which the defendant’s liability is incurred lies peculiarly within the knowledge and the privity of the plaintiff, notice thereof must be given to the defendant.”
Had it not been necessary for the plaintiff to sell the bond and mortgage nothing would have been due from the defendant, assuming that it was paid when, by its terms, the bond and mortgage became payable. In other words, no liability could arise until the plaintiff exercised his option and sold upon terms which should not include a loss to the defendant of more than $1,100; but how much less could only be ascertained when the plaintiff had sold the bond and mortgage and liquidated the amount. We think that, as no specified amount was to be paid, as no time or place for payment was fixed, under such a contract when the parties themselves agree that it shall not be payable until after a demand, such circumstances
We are of opinion, therefore, that the failure to allege and prove such demand was fatal to plaintiff’s right to a recovery, and that the judgment, solely upon that ground, must be reversed and a new trial ordered, with costs to appellant to abide the event.
Yan Brunt, P. J., and Patterson, J., concurred.
Judgment reversed and new trial ordered, with costs to appellant-to abide event.